5.5.4. Installation of utilities. After grading is

About this text

  • As published by Municode, current through 2025-03-04
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

completed and approved and before any base is applied, all of the underground utilities—water mains, sewer mains, gas mains and all service connections related thereto, and where available— shall be installed completely in accordance with Appendix B: Monroe County Utility Placement Standards and approved throughout the length of the street and across the flat section. All driveways for houses to be built by the subdivider shall be cut and drained. Where the utility

mains are off the pavement, the subdivider may elect to omit the installation of service connections providing that at such time as these service connections are needed, they may be jacked

across the street without breaking or weakening the existing pavement.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:monroe-county/code/5.5.4@2025-03-04-6d30268ce2

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Monroe County Code of Ordinances, 5.5.4. Installation of utilities. After grading is | Georgia Commons