Oconee County · Code of Ordinances
Part - CODE OF ORDINANCES / Chapter 66 - UTILITIES / Article 10 - PROJECT DESIGN AND CONSTRUCTION STANDARDS / Division II - PROJECT CONSTRUCTION / 1021 - Installation of streets and utilities.
Sec. 1021.01. Permit for utility installation.
About this text
- As published by Municode, current through 2026-04-07
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
This Section governs the installation of telephone lines, gas lines, water lines, sanitary sewer lines, gray-water reuse lines, electrical lines, fuel lines, steam lines, T.V. cables, open storm drainage, storm sewers and other utilities within county maintained road or street rights-of-way.
a. Application for permit; when required.
(1) New facilities or extensions of existing facilities within county maintained road or street rights-of-way shall require a written application and a permit issued by the appropriate County department.
(2) Service lines and maintenance and repair of existing facilities shall not require a permit unless a pavement cut is required, but all other requirements of this Development Code shall apply to said activities, where applicable.
(3) Emergency cuts without a permit may be made when required. Such cuts shall be followed by a written application or report to the Utilities Coordinator within two working days thereafter. Repairs to the pavement and disturbed soil and all other applicable requirements of this Development Code shall apply to such emergency cuts.
b. Application for permit; requirements. Application for permit for Utility Facility Installation shall be made to the Oconee County Utilities Coordinator.
(1) In the case of water lines and sanitary sewer lines, the applicant must submit four copies of a plan showing the proposed installation to the Utilities Coordinator. Said plans shall be approved or denied, or additional information shall be requested, within 30 days or said plans shall be deemed to have been approved.
(2) A request for breaking of pavement must be described in detail in the application. (See also Sec. 1017.02.)
(3) In those cases where a Georgia Department of Transportation application and permit is required, a copy of the Department of Transportation application and permit along with the expected date of work commencement shall be provided to the Oconee County Utilities Coordinator and said copy shall satisfy the application and permit requirements herein.
c. Installation and construction requirements.
(1) The installation of said facility as authorized shall be subject to the inspection, direction and control of the Public Works Director or Water Resources Department (as appropriate) who shall be notified before work is commenced. Such notification shall include the date and time of the commencement of the construction and/or installation and location of same.
(2) The work shall be performed in a workmanlike manner and all installations shall be done by the utility owner in such a way as to leave free flows in drainage ditches, pipes, culverts or other surface water drainage facilities of the roadway or its connections. No part of any installation shall be attached to any portion of a bridge, culvert or other structure of the roadway without special authorization of the Public Works Director after detailed information is furnished as may be required.
(3) Where breaking of pavement has been approved, a six-inch concrete slab will be poured over the backfilled trench and will rest on undisturbed soil. If the pavement is asphalt, the surface of the six-inch, concrete slab will be 1� inches below the surface of the abutting pavement. The 1�-inch section will be paved with Type E, F, or H plant asphalt. The finished surface will be smooth and flush with abutting pavement.
(4) Underground piping and wiring will be installed and located in accordance with
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.