Sec. 14-64. Sanitary sewer.

About this text

  • As published by Municode, current through 2026-05-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(1) Sanitary sewer laid within a public road shall be constructed along the centerline of the road at a depth of not less than five feet from the road surface to the top of the pipe. For curved streets, sewer shall be installed between gutter lines to avoid conflicts with other utilities.

(2) Any structures, such as lift stations and manholes located in any 100-year flood plain shall be designed so as not to allow surface drainage inflow until flood elevations exceed one foot above the 100-year flood elevation.

(3) Placement procedures of force main piping shall meet the same requirements as those procedures for the placement of

water lines.

History

The history line the source prints at the end of the section.

(Res. of 6-9-03, 5-4)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:whitfield-county/code/14-64@2026-05-11-7c340d6598

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Whitfield County Code of Ordinances, Sec. 14-64. Sanitary sewer | Georgia Commons