Downstream overbank flood and property protection shall be provided by controlling (attenuating) the post-development peak discharge rate to the pre-development rate for the 25-year, 24-hour return frequency storm event. If control of the 1-year, 24- hour storm under subsection

7.13.02 is waived or modified, then peak discharge rate attenuation of the 2-year through the 25-year return frequency storm event must be provided. The City Engineer may modify or waive the provisions of this subsection for sites where the post-development downstream analysis shows that uncontrolled post-development conditions will not increase downstream peak flows, or that meeting the requirement will cause greater peak flow downstream impacts than the uncontrolled post-development conditions.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:carrollton/zoning/7.13.03@2025-11-03-72d8461edd

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Carrollton Zoning Ordinance, 7.13.03. Overbank Flooding Protection | Georgia Commons