7.13.03. Overbank Flooding Protection

Sobre este texto

  • As published by Municode, current through 2025-11-03
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Downstream overbank flood and property protection shall be provided by controlling (attenuating) the post-development peak discharge rate to the pre-development rate for the 25-year, 24-hour return frequency storm event. If control of the 1-year, 24- hour storm under subsection

7.13.02 is waived or modified, then peak discharge rate attenuation of the 2-year through the 25-year return frequency storm event must be provided. The City Engineer may modify or waive the provisions of this subsection for sites where the post-development downstream analysis shows that uncontrolled post-development conditions will not increase downstream peak flows, or that meeting the requirement will cause greater peak flow downstream impacts than the uncontrolled post-development conditions.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:carrollton/zoning/7.13.03@2025-11-03-72d8461edd

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Carrollton Zoning Ordinance, 7.13.03. Overbank Flooding Protection | Georgia Commons