Sec. 7.7-84. Application/permit process.

Sobre este texto

  • As published by Municode, retrieved 2026-11-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
  • Tables are shown as their rows, with the cells separated by a bar ( | ).

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A. General. The property owner, developer and designated planners and engineers shall review the general development plans and detailed plans of the issuing authority that affect the tract to be developed and the area surrounding it. They shall review the zoning ordinance, storm water management ordinance, subdivision ordinance, flood damage prevention ordinance, this article, and other ordinances which regulate the development of land within the jurisdictional boundaries of the issuing authority. However, the property owner is the only party that can obtain a permit.

(b) Application requirements.

(1) No person shall conduct any land-disturbing activity within the jurisdictional boundaries of the city without first obtaining a permit from the city to perform such activity.

(2) The application for a permit shall be submitted to the city and must include the applicant's erosion and sedimentation control plan with supporting data, as necessary. Said plans shall include, as a minimum, the data specified in section 7.7-84(c) of this article. Soil erosion and sedimentation control plans shall conform to the provisions of section 7.7-83(b) and (c) of this article. Applications for a permit will not be accepted unless accompanied by two copies of the applicant's soil erosion and sedimentation control plans.

(3) A fee, in the amount of one hundred dollars ($100.00) shall be charged for each project.

(4) Immediately upon receipt of an application and plan for a permit, the issuing authority shall refer the application and plan to the district for its review and approval or disapproval concerning the adequacy of the erosion and sedimentation control plan. The results of the district review shall be forwarded to the issuing authority. No permit will be issued unless the plan has been approved by the district, and any variances required by section 7.7-83(b)(15) and (16) and bonding, if required as per subsection (5)(b) below, have been obtained. Such review will not be required if the issuing authority and the district have entered into an agreement which allows the issuing authority to conduct such review and approval of the plan without referring the application and plan to the district.

(5) a. If a permit applicant has had two or more violations of previous permits, this section, or the Erosion and Sedimentation Act, as amended within three years prior to the date of filing of the application under consideration, the issuing authority may deny the permit application.

b. The issuing authority may require the permit applicant to post a bond in the form of government security, cash, irrevocable letter of credit, or any combination thereof up to, but not exceeding, three thousand dollars ($3,000.00) per acre or fraction thereof of the proposed land-disturbing activity, prior to issuing the permit. If the applicant does not comply with this article or with the conditions of the permit after issuance, the issuing authority may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance. These provisions shall not apply unless there is in effect an ordinance or statute specifically providing for hearing and judicial review of any determination or order of the issuing authority with respect to alleged permit violations.

(c) Plan requirements.

(1) Plans must be prepared to meet the minimum requirements as contained in section 7.7-83(b) and (c) of this article. Conformance with the minimum requirements may be attained through the use of design criteria in the current issue of the Manual for Erosion and Sediment Control in Georgia, published by the State Soil and Water Conservation Commission as a guide; or through the use of alternate design criteria which conform to sound conservation and engineering practices. The Manual for Erosion and Sediment Control in Georgia is hereby incorporated by reference into this article. The plan for the land-disturbing activity shall consider the interrelationship of the soil types, geological and hydrological characteristics, topography, watershed, vegetation, proposed permanent structures including roadways, constructed waterways, sediment control and storm water facilities, local ordinances and state laws.

(2) Data required for site plan:

a. Narrative or notes, and other information: Notes or narrative to be located on the site plan in general notes or in erosion and sediment control notes.

b. Description of existing land use at project site and description of proposed project.

c. Name, address, and phone number of the property owner.

d. Name and phone number of twenty-four-hour local contact who is responsible for erosion and sedimentation controls.

e. Size of project, or phase under construction, in acres.

f. Activity schedule showing anticipated starting and completion dates for the project. Include the statement in bold letters, that "the installation of erosion and sedimentation control measures and practices shall occur prior to or concurrent with land-disturbing activities."

g. Storm-water and sedimentation management systems-storage capacity, hydrologic study, and calculations, including off-site drainage areas.

h. Vegetative plan for all temporary and permanent vegetative practices, including species, planting dates, and seeding, fertilizer, lime, and mulching rates. The vegetative plan should show options for year-round seeding.

i. Detail drawings for all structural practices. Specifications may follow guidelines set forth in the Manual for Erosion and Sediment Control in Georgia.

j. Maintenance statement: "Erosion and sedimentation control measures will be maintained at all times. Additional erosion and sedimentation control measures and practices will be installed if deemed necessary by onsite inspection."

(3) Maps, drawings, and supportive computations shall bear the signature/seal of a registered or certified professional in engineering, architecture, landscape architecture, land surveying, or erosion and sedimentation control. The certified plans shall contain:

a. Graphic scale and north point or arrow indicating magnetic north.

b. Vicinity maps showing location of project and existing streets.

c. Boundary line survey.

d. Delineation of disturbed areas within project boundary.

e. Existing and planned contours, with contour lines drawn with an interval in accordance with the following:

Tabla 1. Esto era una tabla en la fuente. Cada línea es una de sus filas, con sus celdas en orden, separadas por una barra. Una fila puede tener menos celdas que columnas tiene la tabla, así que lea las celdas en orden, no por columna.
  1. Map Scale | Ground Slope | Contour Interval feet
  2. 1 inch = 100 feet or larger scale | Flat 0—2% | 0.5 or 1
  3. Rolling 2—8% | 1 or 2
  4. Steep 8%+ | 2, 5 or 10

f. Adjacent areas and features areas such as streams, lakes, residential areas, etc. which might be affected should be indicated on the plan.

g. Proposed structures or additions to existing structures and paved areas.

h. Delineate the twenty-five-foot horizontal buffer adjacent to state waters and the specified width in MRPA areas.

i. Delineate the specified horizontal buffer along designated trout streams, where applicable.

j. Location of erosion and sedimentation control measures and practices using coding symbols from the Manual for Erosion and Sediment Control in Georgia, Chapter 6.

(4) Maintenance of all soil erosion and sedimentation control practices, whether temporary or permanent, shall be at all times the responsibility of the property owner.

(d) Permits.

(1) Permits shall be issued or denied as soon as practicable but in any event not later than forty-five (45) days after receipt by the issuing authority of a completed application, providing variances and bonding are obtained, where necessary.

(2) No permit shall be issued by the issuing authority unless the erosion and sedimentation control plan has been approved by the district and the issuing authority has affirmatively determined that the plan is in compliance with this article, any variances required by section 7.7-83 (b)(15) and (16). Are obtained, bonding requirements, if necessary, as per subsection (b)(5)b. are met and all ordinances and rules and regulations in effect within the jurisdictional boundaries of the issuing authority are met. If the permit is denied, the reason for denial shall be furnished to the applicant.

(3) If the tract is to be developed in phases, then a separate permit shall be required for each phase.

(4) The permit may be suspended, revoked, or modified by the issuing authority, as to all or any portion of the land affected by the plan, upon finding that the holder or his successor in the title is not in compliance with the approved erosion and sedimentation control plan or that the holder or his successor in title is in violation of this article. A holder or a permit shall notify any successor in title to him as to all or any portion of the land affected by the approved plan of the conditions contained in the permit.

(5) No permit shall be issued unless the applicant provides a statement by the city clerk certifying that all ad valorem taxes levied against the property and due and owing have been paid.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 5-10-01, § V)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:dawson/code/7.7-84@2026-11-14-16762c281e

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Dawson Code of Ordinances, Sec. 7.7-84. Application/permit process | Georgia Commons