Sec. 23-35. Permit procedures and requirements.

Sobre este texto

  • As published by Municode, retrieved 2026-11-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Permit required. No land owner or land operator shall receive any of the building, grading, or other land development permits required for land disturbance activities without first meeting the requirements of this article prior to commencing the proposed activity.

(b) Application requirements. Unless specifically excluded by this article, any landowner or operator desiring a permit for a land disturbance activity shall submit to the Authority a permit application on a form provided for that purpose. Unless otherwise accepted by this article, a permit application must include the minimum requirements as defined in this article or LDM in order for the permit application to be considered. See also chapter 21, soil erosion and sedimentation control, for permit requirements.

(c) Application review fees. The Authority may require the submittal of a review fee for review of the stormwater management plan. This review fee shall be based on the amount of land to be disturbed at the site, and the fee structure shall be established by the Macon Water Authority Board. All of the monetary contributions shall be credited to a local budgetary category to support local plan review, inspection, and program administration, and all fees shall be paid prior to the issuance of any development permits.

(e) Permit duration. Permits issued under this section shall be valid from the date of issuance through the date the Authority notifies the permit holder that all stormwater management practices have passed the final inspection required under permit condition.

Should no activity take place on the site, the permit shall expire within one (1) year of issuance.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 10-19-2021(3), § 1(Exh. A); Ord. No. O-22-0016, § 3(Exh. C), 4-5-2022)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:macon-bibb/code/23-35@2026-11-14-22d1d74a9d

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Macon-Bibb County Code of Ordinances, Sec. 23-35. Permit procedures and requirements | Georgia Commons