Appendix B - SUBDIVISIONS / Article III - PROCEDURE FOR PLAT APPROVAL (NONEXEMPT LAND DIVISIONS)

Sec. 3.3. Planning commission review.

Sobre este texto

  • As published by Municode, current through 2019-03-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Once the preliminary technical and legal reviews are completed, all necessary corrections are made, and all unusual expenses paid, then the city staff shall submit the plat, preliminary legal and technical opinions, and supporting environmental and related technical documents to the planning commission.

The planning commission shall either schedule a hearing or place the preliminary plat on the agenda for its next regularly scheduled monthly meeting, and the subdivider or developer shall be notified of the date, time, and place for the hearing.

At the hearing the planning commission shall give either tentative approval or disapproval to the preliminary plat. A notation of the commission's actions shall be made on three copies of the preliminary plat with one copy being returned to the subdivider or developer, one copy being returned to the city clerk and one copy being retained by the planning commission. Approval of the preliminary plat does not constitute approval of a final plat; it only approves use of the layout as a guide to the preparation of a final plat. Preliminary plat approval shall expire and be null and void after a period of one year unless an extension of time is granted by the planning commission. If a preliminary plat is granted tentative approval, the planning commission may make such approval conditioned upon certain requirements being met. If the subdivider or developer does not comply with the requirements of conditional approval, then the approval is automatically voided and no approval will be granted to the final plat.

The planning commission shall have a minimum of 30 days after submission of a preliminary plat to take action on said preliminary plat. The planning commission shall have a maximum of 90 days to take action on the preliminary plat. If the planning commission fails to take action on the preliminary plat within the 90 days after the date the plat is forwarded from the city clerk to the planning commission, then the preliminary plat shall be considered approved and a certificate of approval shall be issued on demand. However, the applicant may waive this requirement and agree to an extension of time.

If any of the requirements of this ordinance [appendix] are modified or waived under the variance provision, the reasons for such shall be specified in writing to the subdivider/applicant and to the city clerk. No construction is to start until the preliminary plans are approved.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:aragon/zoning/3.3@2019-03-26-ac15220fee

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Aragon Zoning Ordinance, Sec. 3.3. Planning commission review | Georgia Commons