(a) All projects shall have a posted land disturbance permit on the job site.
(b) First inspection by the ordinance/inspection department will occur after debris and timber have been cleared, burned, [and]removed from road right-of-way, [and] sediment and erosion control devices [have been] installed and functioning. The developer/subdivider shall notify the department when such has been completed.
(c) The road superintendent should be notified at least one full working day in advance before grading the right-of-way begins.
(d) Once cleared and graded, subgrade shall be tested for compaction. The city shall be notified so as to observe testing. The city shall be provided with test certifications.
(e) The road superintendent should be notified at least one full working day in advance before curb and gutter installation. All storm pipes and structures are to be in place and functional. All curbing, throat, [and] top mix shall be 3,000 PSI concrete. Separate inspections must be scheduled if throats and tops are not installed during curb and gutter construction. All tops and throats shall be inspected prior to pouring of concrete.
(f) Notify road superintendent at least one full working day in advance before material is applied.
After installation of base, certification of testing shall be provided.
(g) Once base material is applied, notify road superintendent at least one full working day in advance before paving so testing may be observed.
(h) Once the base is approved, paving may commence in accordance with above material and weight specifications; plus paving inspections will be conducted during operations, compaction will be required at 95 percent and completed under confined and temperature controlled conditions. No asphalt will be compacted less than 185 degrees Fahrenheit. The asphalt institute recommends desired compacted thickness equal to 1.25 times spreader thickness. All asphalt surfaces are to have uniform crown at catchbasins, and all asphalt above the gutter line on the curb and gutter.
(i) After pavement edges are backfilled, shoulders, ditch, back slopes, and all disturbed areas should be seeded and 80 percent stand of grass should be visible.