Chapter 89 - UNIFIED DEVELOPMENT CODE / Article X - PROJECT DESIGN STANDARDS

Sec. 89-1191. Stormwater conveyance facilities.

Sobre este texto

  • As posted on the city's website, retrieved 2026-11-11

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Storm drains.

(1) Sizing and location of all existing and proposed drainage structures shall be the responsibility of a registered design professional subject to approval by the reviewing agency.

(2) Storm drainage pipes shall be sloped so as to maintain a minimum velocity of three fps at design flow or lower so that sediment will not collect. Minimum slopes for RCP pipe shall be 0.5 percent, and for CMP pipe shall be one percent.

(3) State Highway Standard 1030D (or most current) shall be used in determining class (concrete) or gauge of pipe under fill, method of backfilling and pipe installation.

(4) Drainage formula used in determining size of drainage structure shall be determined by the developer's registered design professional according to accepted engineering practice, subject to approval of the reviewing agency.

(5) A registered design professional shall certify the storm drainpipe sizes with supporting calculations verifying capacity of the system.

(6) The 25-year storm event shall be used in designing the storm drains. In cases where a spring, creek, or other watercourse traverses the property, the 100-year storm event will be used for design. In cases where upstream property drains through the development, the storm drain system passing this flow shall be designed using the 100-year storm event for the area draining to the property. No increase in watersurface elevation or ponding shall be allowed on upstream offsite property without consent of the upstream offsite property owner.

(7) Storm sewer catch basins, drop inlets, manholes, and junction boxes shall be designed by the developer's registered design professional to GDOT State Highway Standard Specifications and subject to final approval by the reviewing agency. Catch basins shall be located outside of intersection radii unless unusual circumstances cause undue hardship, in which case the reviewing agency may waive this requirement. Catch basins shall be constructed to GDOT standard specification 1033D or 1034D, as amended.

(b) Street drainage.

(1) Street water runoff shall be designed using the gutter spread formula and shall be limited to a maximum spread of eight feet.

a. Culs-de-sac on downhillstreet gradesshall require catch basin throat design and cul-de-sac grading detail.

(2) Subdrainage will be installed to control the surplus ground water by intercepting sidehill seepage or by lowering or regulating the ground water level where such conditions exist.

(3) A certification by the supplier of the pipe specifications for each pipe shall be required before installation.

(4) (Bridges shall be designed for a 100-year storm event with a minimum freeboard of 1.5 feet measured from the centerline of roadway.

(5) Provide riprap or other energy dissipation measure at all downstream discharge points of storm drains.

The area of riprap or size/configuration of energy dissipation measure required shall be determined using design equations in the current edition of the "Georgia Stormwater Management Manual."

(c) Cross drain and side drain pipes.

(1) Cross drain and side drain pipes shall not be less than 18 inches in diameter when under the street. No storm drain pipe running parallel to the existing primary road shall be located beneath the proposed acceleration/deceleration lanes. The reviewing agency may modify or waive this requirement if unusual circumstances exist such as topography.

(2) The minimum allowable pipe diameter shall be 18 inches except driveway pipes may be a minimum of 15 inches.

(3) The inlet and outlet end of all storm drain pipes (except driveway pipe) shall have either flared-end sections or rectangular concrete headwalls that meet the standards of Georgia Department of Transportation 1120 or 1125. Driveway pipe shall have safety flared end sections according to latest GDOT standards.

(4) Storm drain pipes shall extend 50 feet back from the front building line with a minimum length of 120 feet on the downhill side of the road.

(5) Maximum continuous length of pipe shall be 200 feet for pipes less than 42 inches. Junction boxes or other manhole structures allowing access shall be installed in pipes longer than 200 feet.

(6) Junction boxes having accessto the pipe shall be constructed to meet the requirements of State Standard 1011A (or most current).

(d) Stormwater channels. All channels between storm drain pipes and downstream of storm drain pipe shall be designed by a registered design professional. The design plans shallshow the velocity, depth and flow quantity for each channels. Stormwater velocity shall not exceed five fps during the 25-year storm event unless the channels are lined with riprap or other energy dissipation materials as approved by the reviewing agency. In addition, for channels passing flows from upstream properties, the channel shall be evaluated using the 100- year storm.

(e) Materials and installation.

(1) Table 10.7 sets out guidelines for the use of storm sewer pipes by pipe material and type of installation.

(2) All pipe materials shall meet the minimum requirements of the Georgia Department of Transportation's Standard Specification for Construction of Transportation Systems, most current edition.

(3) Pipe installation shall conform to Georgia Department of Transportation Standard Specifications for Construction of Roads and Bridges. Before any traffic over a storm drain is allowed, the developer shall provide an adequate depth and width of compacted backfill to protect the structure from damage or displacement. The developer shall remove any debris or silt that constricts the flow through a pipe as often as necessary to maintain drainage. All pipe structures shall be cleaned before the work is accepted.

Any damage or displacement that may occur due to traffic or erosion shall be repaired or corrected at the developer's expense. Trench construction for storm drainage pipe shall be in accordance with State Highway Standard 1030D (or most current).

(4) Storm drainage pipe shall be bedded in Type 57 gravel if required due to pipe trench conditions.

(5) Backfilling of trenches shall be accomplished immediately after the pipe is laid. The fill around the pipe shall be placed in layers not to exceed six inches with each layer being thoroughly compacted. All material shall have an in place density of 98 percent standard proctor to a depth of six inches below the finished grade, and 95 percent standard proctor at depths greater than six inches below the finished grade.

Compaction requirements shall be attained by the use of mechanical compaction methods. Each layer of backfill shall be placed loosely and thoroughly compacted in place.

(6) All backfillshall be non-plastic in nature, free from roots, vegetative matter, waste, construction material or other objectionable material. Said materialshall be capable of being compacted by mechanical means and shall have no tendency to flow or behave in a plastic manner under the tamping blows.

(7) Material deemed by the reviewing agency as unsuitable for backfill purposes shall be removed and replaced with selected backfill material.

(8) Water shall not be permitted to rise in trenches that are not backfilled after the pipe has been placed.

(9) Benching is required in the bottom of all structures. The invert channels shall be constructed as to cause the least possible resistance to flow. The shapes of invert channels shall conform uniformly to inlet and outlet pipes. Inverts may also be precast into the structure.

(f) Minimum clearances.

(1) One foot between the bottom of the base or sub-base, if used, and the exterior crown of the culvert are required under the roadway.

(2) Pipes included in easements shall have a minimum cover of one foot or at the manufacturers' recommendations.

(3) A minimum of one foot between underground utilities and exterior crown of culverts.

(g) Driveway culverts.

(1) Where a wet weather drainage ditch exists between the proposed road and 20 feet into the lot, the design professional shall size the driveway culvert as if the driveway was at the lowest point on that lot.

Sizing shall be based on the 25-year storm with one and one half foot of freeboard. The construction plans shall show the minimum driveway pipe size required.

(2) Driveway culverts in the right-of-way may be any of the types of pipe materials shown on

(3) Table 10.7 for longitudinal pipe installation.

(4) The inlet and outlet end of all driveway culverts shall have safety flared-end sections that meet the standards of Georgia Department of Transportation 1120 or 1125.

(h) Inspections.

(1) Responsibility for inspection. The developer's contractor will be responsible for the quality, accuracy and workmanship of the contractor's completed work. Town’s designee will review the quality of work during construction and oversee inspection on all installed infrastructure. The Town or its designee shall have the right to review and inspect all construction and may reject any work that does not meet quality control standards.

(2) Access to project. Authorized representatives of the town, which may include Barrow County employees and the county’s engineering consultant, as well as state or federal agencies, shall have access to the site for inspection at any time.

(3) Communications. The developer, contractor(s) and the developer's professional responsible for construction will be required to attend a pre-construction conference with the Town or its designee. At the pre-construction conference, the contractor will submit to the Town or its designee, in writing, the date they propose to begin construction. The contractor will provide notification by phone any time the work is to be vacated for longer than 72 hours and will provide notice by phone prior to resuming work.

The applicable departments may have informal verbal communications with the contractor foreman or superintendent at any time during construction. The Town or its designee will not direct the actions of contractor's workmen. Requests for inspections shall be made at least 24 hours prior to when the inspection is needed.

(4) Concealed work. The contractor shall notify the Town’s designee and receive inspection approval prior to concealing certain work such asstorm sewers and bedding,storm drainage structures, etc. Inspections shall be made and passed prior to continuation of further activity.

(i) Final acceptance. The developer's professional will provide the Town’s designee copies of as-built drawings.

After the submittal of these items the Town’s designee will schedule a final inspection. A representative of the developer's professional and the contractor will be present during this final inspection. This final inspection will generally include spot checks of storm sewers, drainage system, drainage easements, and a complete overview of the project. The developer shall be responsible for correcting any deficiencies identified in the final development inspection prior to approval.

(j) Responsibility for work. References in this section to the various responsibilities of contractors and design professionals are to clarify the role each is expected to play in the permitting process. No such references relieve the owner from its ultimate responsibility for compliance with this section. The owner shall ensure that its contractors and design professionals comply with the requirements of this section.

Table 10.7: Selection Guidelinesfor Storm Sewer Piping* Reinforced Concrete

AASHTO

M-170 Corrugated Steel AASHTO M-36 Corrugated Steel AASHTO M-245 Corrugated Aluminum

AASHTO

M-196 Plastic AASHTO M-294 Reinforced Concrete Box Culvert Type of Pipe Installation Reinforced Concrete Pipe

(RCP)

Aluminized Type II

CMP

Polymer Coated

CMP

Aluminum Alloy CMP Corr. High Density Polyethylene Smooth Lined Per Ga.

DOT

Standards

LONGITUDINAL

Grade lessthan 10%

YES YES YES YES YES n/a

LONGITUDINAL

Grade 10% or more

NO NO YES NO YES n/a

CROSS DRAIN

Local Street YES NO NO NO NO n/a

CROSS DRAIN

Collector or Arterial St.

YES NO NO NO NO n/a

CROSS DRAIN

25 year flow < 200 cfs Fill depth < 18 feet See Note 2 NO NO NO NO YES

* See corresponding notes below:

Note 1: Only reinforced concrete pipe (AASHTO M-170) shall be used inside the roadbed. Concrete pipe shall not be used on grades exceeding 10%. Metal and corrugated high density polyethylene pipe may be used outside the roadbed.

Note 2: Corrugated high density polyethylene pipe, smooth lined type "S" must be manufactured and installed in strict compliance with AASHTO M-294 and ASTM D-233.1. HDPE applications shall not exceed 48 inches in diameter.

Note 3: Reinforced concrete box culverts are required under excessive flow and/or fill depth conditions. Approved pipe materials may be utilized in some instances, based on the Mayor or his or her designee’s assessment of existing conditions and future maintenance requirements.

Note 4: In the case of a flowing stream Reinforced concrete pipe (AASHTO M170), or Concrete Box Culvert, shall be used.

Leer este código donde se publica (city website) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:bethlehem/zoning/89-1191@2026-11-11-0e6cd92a3a

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Bethlehem Zoning Ordinance, Sec. 89-1191. Stormwater conveyance facilities | Georgia Commons