Bogart · Ordenanza de zonificación
Article 12 - Procedures and Permits
Sec. 1203.05. Multi-family and nonresidential projects.
Sobre este texto
- As posted on the city's website, retrieved 2026-11-14
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
a. Project Approval is granted by the Planning Director upon review and approval of a Preliminary Site Plan for the project by the Development Review Committee.
b. A Development Permit is issued by the Planning Department based on review and approval by all affected departments and agencies of development plans for construction of the project.
c. A Building Permit is issued by the Planning Department based on review and approval of architectural plans. Buildings falling under the authority of the State Fire Marshal shall be approved by the Fire Marshal prior to issuance of the building permit.
d. Driveway and sign permits are issued by the appropriate departments.
e. Receipt by the City Engineer/ Public Works Director (for streets and drainage) and the Water Resources Director (for water and sewer) of accurate surveys of the as-built condition of all public improvements is required in order to authorize issuance of a Certificate of Occupancy.
f. Occupancy of the building is authorized by the Planning Director based on final inspection and issuance of a Certificate of Occupancy.