a. After the Preliminary Plat of a proposed land subdivision has been reviewed by the Development Review Committee and given approval by the Planning Department, the subdivider may, within one year from approval (2 years if extension has been approved as specified herein), submit to the Planning Department:
(1) A request for review and approval of a final subdivision plat.
(2) Such application fee as may be established by the Mayor and Council from time to time.
(3) Copies of the Final Plat and other related documents in a number as established by the Planning Director.
(4) Title opinion from developer’s attorney certifying clear title to all streets, rights-ofway, drainage easements, well lots, wells and other areas to be dedicated to the Sec. 1229 Procedures for final plat approval.
City of Bogart, and dedication deeds or easement agreements to be accepted by the Mayor and Council.
(5) Conservation or natural resources easement, if required by the provisions under the Environmental Protection Article of this Development Code.
(6) Articles of incorporation of any Owners’ Association required by this Development Code, including the provisions for transfer of control of the Association to the property owners comprising the Association and provisions to address the requirements of this Code for reserve fund funding.
(7) Covenants and/or provisions for maintenance of open space amenities and storm water detention areas.
(8) Petition for creation of any applicable Special Tax District in compliance with the requirements and provisions of Division VI of this Article.
(9) Maintenance surety and performance surety documents in a form acceptable to the City Attorney, as may be required by Sec. 1229.03, below, or other ordinances of the City of Bogart.
b. If development construction plans are or were required, the subdivider shall provide one of the following relative to the installation of required improvements (streets, utilities, drainage, etc.):
(1) A registered Engineer, Land Surveyor, or Landscape Architect’s report certifying that all improvements meet the requirements of this Development Code. Said report shall include the following:
(a) A copy of all inspection/observation reports performed by the Design Professional of Record or designated representative.
(b) A copy of all material testing/inspection reports performed by the Design Professional of Record or designated representative.
(c) A summary of all design and field changes made to the approved construction plans.
(d) Two sets of plans reflecting the “as-built” condition of all improvements and easements as described in Sec. 1018.03.
(e) As built or planned location of water, sewer, gas, electric, telephone, and cable utilities including appurtenances (transformers, pedestals, poles, street lights, etc.).
(f) Summary of actual (or estimated if performance bonded) construction costs by item utilized as the basis for the computation of maintenance surety.
(g) Certification by surveyor that all lot corner pins have been set, marked, and verified in accordance with Sec. 1232.
(h) Certification and supporting data that the storm water management and drainage systems are in substantial conformance with the approved construction plans.
(i) Signed and sealed “Design and Construction” certification by the Design Professional of Record as contained in Sec. 1232.
(2) If, at the time of application for final plat approval, any of the required improvements listed under Sec. 1229.03.a(3) have not been installed or completed, performance surety must be provided in accordance with Sec. 1229.03.a. A certification report for all other required improvements shall be provided in accordance with Sec. 1229.02.b(1), above.