Ir al contenido
Georgia Commons
Menú

Braselton · Ordenanza de zonificación

Article 9 - STREET DESIGN AND CONSTRUCTION

9.14. Utility Requirements

Sobre este texto

  • As posted on the city's website, retrieved 2026-11-11

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A. In order to promote uniformity in installation and more effective and less damaging

maintenance, a uniform system for locating utilities is hereby established. Applicable utilities and their locations must be noted on subdivision construction plans. For new

developments, all new and existing utilities must be located (or relocated) underground.

Development plans and final plats must include a right-of-way cross section detail that illustrates all utility locations in relation to the street, sidewalks, and other right-of-way improvements.

B. Utility lines must be located in accordance with typical street cross sections provided in the Town of Braselton Water and Wastewater Standards. Underground utilities must be installed with the same surface compaction as for the roadway.

C. Design criteria for storm drain facilities must conform to accepted engineering practices and guidance documents. Pipe materials

must conform with the requirements of Sec.

11.4Q.

D. All fire hydrants, transformer boxes and pedestals, and other public or private utility structures placed above ground within a

public street right-of-way or private street easement must be located at least 6 feet from the back of the street curb (or edge of

pavement) and must not encroach upon the sidewalk.

E. The right-of-way must be cleared and rough graded the full width prior to any utility installation.

F. Underground utilities must be placed in the ground before the base material is in place, or the pipes must be bored if installed after street construction. The facilities for

underground utilities must be in place prior to surfacing of streets.

G. All trenches must be thoroughly compacted in six-inch layers with mechanical compacting equipment.

H. Any disturbance or construction in the completed (seeded and/or sodded) right-ofway by a public utility such as power, gas, phone and cable must be repaired or replaced with the specified materials as called for in the initial improvements.

I. If utility services are installed after a street has been paved, they must be installed by boring under the street. Note that this applies only to services and not the distribution system for the development.

J. When existing base or pavement must be broken to install utility services, or for any other purpose, the subdivider or utility company is financially responsible for

repairing the pavement. The pavement must be repaired with a patch in accordance with standards developed by the Town Engineer, and in accordance with all other specifications of this Article.

K. No existing Town street or road may be open cut unless unusual circumstances warrant it.

L. All utility construction plans within Town rightof-way must be reviewed and approved by the Town Engineer.

M. If a pavement cut is approved, all trenches must be backfilled and compacted the same day the trench is opened. Trenches under the paving must be returned to 95 percent

compaction. The backfill in all such ditches must be thoroughly compacted in 6-inch lifts, the subgrade must be brought to the required lines, grades, and typical street section required.

Leer este código donde se publica (city website (Revize)) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:braselton/zoning/9.14@2026-11-11-a7f7caa80b

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.