prepare and present recommendations to the Planning Commission and the Town Council at least 3 days prior to their respective action on such applications.
Procedural requirements of O.C.G.A 36-66 The Zoning Procedures Law, as amended,
shall apply to all zoning actions.
3. Applicants may submit to the Planning Director any conditions, alterations,
changes, or amendments to an application for approval of a special use up to seven days prior to the date at which the
application is to be considered by the Planning Commission. If such conditions, alterations, changes, or amendments have not been submitted as required by this
subsection, the Planning Commission may, at its discretion, defer action on the
application until its next regular meeting.
4. An applicant may request a deferral of their application from the Planning
Commission or the Town Council. The first request for deferral must be via postal mail or e-mail and must be received by the town at least three days prior to the hearing. Any subsequent requests for deferral must be made by the applicant in person at the
hearing. The Planning Commission or Town Council may vote to accept or deny the
deferral request.
5. The Planning Commission may defer their recommendation of an application until
their next scheduled meeting only once without the applicant’s written consent. In such an event, the application and
recommendation will not be forwarded to the Mayor and Council until after a recommendation has been made by the Planning Commission meeting at their subsequent meeting. If the Planning Commission fails to take action (or to defer action with the consent of the applicant) at a subsequent hearing, the application
shall be deemed to be recommended for approval. The Planning Commission may defer action any number of times as long as the applicant requests, or agrees to, the deferral.
6. Following the public hearing, the Planning Director must prepare a summary report of the Planning Commission’s
recommendation on each application reviewed and submit this report to the Town Council prior to the date of the public hearing on the application by the Town
Council.
7. The Town Council, after receiving the recommendation of the Planning
Commission, must take appropriate action on the application at a regularly scheduled meeting. The decision on each special use application must be based on a
discretionary determination as to whether or not the applicant has met the criteria contained in Sec. 14.5F, the use standards contained in ARTICLE 5, the consistency of the application with the Comprehensive
Plan, the requirements of the zoning district in which the use is proposed to be located, and any additional conditions
deemed necessary to ensure the compatibility of the special use with the surrounding properties.
8. An applicant may withdraw their application at any time by submitting a request in writing to the Town Clerk. The Town Council is not required to take action on any withdrawn applications. An
applicant may request a deferral of their application at any time from the Planning Commission or Town Council.
9. The proposed special use may be approved subject to such conditions as may be imposed in order to mitigate impacts on nearby properties which may be expected without the imposition of conditions. Requirements imposed as a condition shall be required of the property owner and all subsequent owners.
Requirements imposed as a condition shall be interpreted and continuously enforced by the Planning Director in the same manner as any other provision of this Development Code. If an applicant or the Town Council wish to request a change to any conditions after they are approved by the Town Council, a new application must be submitted and heard consistent with
the special procedures of this article.
10. If a special use application is denied, the Town may not accept any other special use applications for the same property for 6 months. This time limit begins on the date of a final decision by the Town Council.
11. If a special use application is withdrawn, the Town will not accept any other special use applications for the same property for 3 months.
12. Appeals of a final decision by the Town Council may be appealed within 30 days
after the final decision to the Superior Court of the County in which the subject property is located, de novo.