Bremen · Ordenanza de zonificación
Part III - LAND DEVELOPMENT CODE / Chapter 104 - CONSTRUCTION AND DESIGN STANDARDS / Article III - WATER AND SEWER FACILITIES
Sec. 104-44. Design standards for waterlines.
Sobre este texto
- As published by Municode, current through 2025-10-13
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Pipe and fittings.
(1) The waterline shall be located five feet inside the right-of-way. The minimum pipe size for any development shall be six inches. Cast iron or ductile iron, three-inch through eight-inch, and ductile iron, ten-inch and above, shall meet 250 psi working pressure and 100 psi surge allowance. Polyvinyl chloride (PVC) shall be Class 150 (DR-18)
AWWA C-900.
(2) All fittings shall be mechanical joint, cast iron or D.I., conforming to AWWA C110 or C153. The pipe and fittings shall be cement lined in accordance with ANSI 21.4. Inside and outside of pipe and fittings shall be coated with coal tar.
(b) Valves. Gate valves shall be resilient seated in sizes two-inch through 12-inch AWWA C-509 "O" ring, working pressure 200 psi. Valves shall be city standard as manufactured by Mueller.
(c) Valve boxes. Valve boxes shall be cast iron, heavy roadway, two piece screw type with drop covers. The word "water" shall be cast in raised letters on the covers. The valve boxes shall be adjustable to six inches up or down from the nominal required cover over the pipe. A concrete protecting slab shall be required when the valve box is not located on a paved area. Installation shall be so the top is flush with the protecting slab. Concrete protecting slabs shall not be smaller than 18 inches square by six inches thick.
(d) Hydrants. Hydrants shall be per AWWA C-502. Hydrants shall be city standard Mueller "Super Centurion." Valve opening shall be not less than 4.5 inches with two 2.5-inch hose connections, and one 4.5-inch pumper connection with four foot depth of cover over the leader pipe and a six-inch shoe connection. Hydrants shall be placed at all intersections and be a maximum of 1,000 feet apart. Hydrant spacing should take into account the density of the development. Hydrants shall be located at the road right-of-way.
(e) Roadway and railroad crossing. The subdivider or his contractor shall install pipe lines across a roadway or railroad in accordance with the applicable regulations of the state department of transportation or governing railroad body. Recently paved city streets shall be bored and cased in steel casing at least 1.5 times the proposed pipe outside diameter. Steel pipe casing shall be manufactured from steel conforming to ASTM A 252 Grade 2 with a minimum yield strength of 35,000 psi before cold forming. The casing ten inches in diameter and less shall be a minimum of 0.375-inch wall thickness. Casing greater than ten inches shall be a minimum of one-half-inch wall thickness. When crossing city streets, the casing shall extend at least five feet off of the edge of pavement on each side. Coating for the casing is not required. The pipe shall be supported by skids within the casing such that the pipe bell does not rest on the bottom of the casing. Each end of the casing shall be sealed to prevent groundwater seepage. When the city street is in disrepair, the street may be open cut trench in accordance with state department of transportation standard 1401.
(f) Installation of pipe.
(1) Pipe shall be installed with a minimum of four feet of cover, and ditchline shall be on a straight even grade with no peaks or valleys. Water and sewer lines shall have a minimum of ten feet horizontal and 24 inches vertical separation. Sufficient excavation shall be made for pipe bells. Ditch bottom shall be fine graded. Ditch in rocky areas shall be undercut and the pipe bedded in at least six inches of crushed stone, gradation #67. Selected backfill consisting of finely divided earth, sand, stone dust, or crushed stone shall be placed and tamped about and over the pipe (in six-inch layers) up to a height of at least 12 inches above the top of the pipe crown.
(2) Before replacing the remaining backfill over PVC pipe, detectable marking tape, labeled with the words "BURIED WATER," shall be placed in the ditch approximately 12 inches above the pipe for the entire length installed. The tape shall be two inches wide.
(3) General backfill material may be used to fill the remainder of the ditch except excessive amounts of rock. Backfill material shall be placed in six-inch layers with each layer thoroughly compacted with a heavy-duty tamper. Wheel loading will not be permitted until the pipe has a minimum cover of 36 inches.
(g) Concrete blocking. The engineering plans shall provide a concrete blocking detail.
Concrete blocking shall be formed and poured at all fittings against undisturbed earth such that no bolts are obstructed.
(h) Customer service connections. Following the main installation, the developer shall provide service connections for all lots. Connections shall include corporation stop, tubing, curb stop, and meter box with lid. Connections shall be made after testing of water main has been completed. Connections shall be made with three-fourths-inch corporation stop at the main and three-fourths-inch type "K" soft annealed copper tubing, from corporation stop to three-fourths-inch curb stop at meter box.
(1) Corporation stops. Corporation stop shall have standard thread conforming to AWWA C-800 on the inlet end. The outlet end shall have a pack joint connection and locking split clamp for connection to three-fourths-inch copper tubing.
(2) Service tubing. Service tubing shall be three-fourth-inch type "K" soft annealed copper.
Fittings shall be cast bronze flared tube type. Dielectric adapters shall be provided where copper or brass pipe connects to steel.
(3) Curb stops. Curb stops shall conform to ASTM B62, shall be constructed of bronze with pack joint connection with locking split clamp and end threaded for meter connection, with a padlock wing. The curb stop shall be designed for 150 psi hydrostatic pressure.
(4) Pipe saddle. Saddles shall be used with corporation stops for customer service connections to water mains. Saddle shall be double strap service saddle with ductile iron body, carbon steel straps and grade 60 (Buna-N) rubber gasket.
(5) Long side services. Long side services shall be encased with a minimum of two-inch casing under the roadway and sealed at each end. If two long side lots are served with one connection, a minimum of one-inch service tubing and Y-connection shall be used.
No more the two long side services are allowed per connection.
(6) Meter box. The meter box shall be set two feet inside the right-of-way. The meter box shall be plastic with dimensions of 14 inches wide × 19 inches long × 12 inches deep.
The lid shall be solid with "WATER METER" cast on top.
(i) Testing. When an adequate section of pipe is installed, the subdivider or his contractor shall perform a leakage test. Wherever conditions will permit, pipelines shall be tested prior to backfilling. All joints then shall be examined during open trench test and all leaks entirely stopped. A test pump, and means for accurate measurement of water introduced into a line during testing, shall be furnished. Furnish and install corporation stops at all high points in the line as required for blowing lines free from air and at the test pump location.
(j) Test pressure and leakage. Test pressure shall be 200 psi for a minimum of two hours;
however, if additional testing is required, such additional testing shall be performed. Leakage allowed during the test per 1,000 feet of pipe shall be:
Size (in.) Leakage Allowed (gal./hr.)
4 0.43 6 0.64 8 0.85 10 1.06
(k) Defective materials and workmanship. Any cracked or broken material, such as pipe, fittings, valves or hydrants shall be removed and replaced with sound pieces. Leaking joints shall be carefully remade. Remade joints and replaced material shall be re-tested under the same conditions of operation. Likewise, if joints or materials are again found to be defective, they shall be done remade and replaced.
(l) Disinfection.
(1) All pipelines and appurtenances including service connections which have been exposed to contamination by reason of this construction shall be sterilized before being placed in service.
(2) Pipelines shall remain filled for a 24-hour period with a solution of water and HTH or chlorine in amounts equivalent to at least the following quantities for each 100 feet of pipe:
Pipe Size (in.) Oz. of HTH 6 2 8 3 10 4
(3) Not less than one ounce of HTH shall be used, per 100 feet, for all mains, sizes two inches and smaller, and the above quantities shall be increases if necessary to secure a chlorine residual of 50 parts per million after 24 hours. The developer shall obtain bacteriological analysis of samples of water taken from the main which are satisfactory to the owner, before the lines will be accepted.
(4) Furnish all HTH or liquid chlorine, equipment and labor required for disinfection. The city will have a bacteriological analysis of the waterline after 24 hours of disinfection.
After receiving positive test results, all mains and piping shall be thoroughly flushed before placing in service.
Historia
(Code 1996, § 82-171; Ord. of 3-8-1999, pt. V, art. 1)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.