Sec. 120-38. Review procedures for subdivision construction plans.
Sobre este texto
- As published by Municode, current through 2025-10-13
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) The developer shall submit three copies of the engineered construction plans, one full size set and two half size sets.
(b) The city engineer shall review the engineered construction plans and coordinate with each city department likely to be affected by or having jurisdiction with respect to any land subdivision matter. Such departments will review the plans and will forward comments to the city engineer.
(c) The city engineer shall promptly advise the subdivider in writing of the action taken on his submittal.
(d) Upon staff review and approval of the subdivision construction plans, and a finding that no major deviations from the preliminary plat have occurred, the secretary of the planning and zoning commission shall notify the planning and zoning commission; and the developer may then apply for a land-disturbing activity permit. In the event, that the construction drawings significantly deviate from the preliminary plat submitted to the planning and zoning commission, the staff will advise the developer that a formal presentation of such changes shall be required to be presented to the planning and zoning commission. The developer shall provide an explanation for the deviations at the next regularly scheduled meeting of the planning and zoning commission, prior to applying for a land-disturbing permit. The installation of utilities is contingent upon approval of the sanitary sewer extension submittal, water system extension, and any other necessary requirements mandated by state or federal agencies.
(e) Prior to commencing work, the developer must coordinate with the city engineer concerning the following inspection requirements, and give adequate notice (a period of not less than 48 hours) prior to commencing work:
(1) Erosion control.
(2) Water/sewer installation (if accomplished by the developer).
(3) Storm drainage construction.
(4) Subgrade preparation.
(5) Curb and gutter installation.
(6) Sidewalk installation (when installing).
(7) Base preparation.
(8) Asphalt placement.
(f) Required improvements. Prior to the commencement of construction of any building within the subdivision, the following elements must be completed when a performance bond has not been issued to the city:
(1) Storm drainage system including satisfactory stormwater discharge on or off the subdivision site.
(2) Street grading.
(3) Satisfactory erosion control.
(4) All-weather hard surfacing of the roads.
(5) Concrete curb and gutters shall be installed.
(6) Sidewalk and crossing ramps shall be installed according to GDOT specifications reference #9031W, when installing.
(7) Bridges if any are necessary for public access along any street proposed for public dedication shall be constructed.
(8) Satisfactory completion of the sanitary sewer system including on- or off-site disposal of wastewater.
(9) Satisfactory completion of the water distribution system with fire hydrants and any off-site extensions of city water supply to the subdivision.
(10) All buffer area improvements and augmentations.
(11) Approval and filing of the documents of record by the city engineer.
Historia
(Code 1996, § 82-85(i), (j); Ord. of 3-8-1999, pt. II, art. 9)