26-3.02.20. Standards for areas of shallow flooding (AO Zones).

Sobre este texto

  • As published by Municode, current through 2025-10-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Areas of special flood hazard established in section 26-3.02.06 may include designated "AO" shallow flooding areas. These areas have base flood depths of one to three feet above ground, with no clearly defined channel. The following provisions apply:

(a) All new construction and substantial improvements of residential and nonresidential structures shall have the lowest floor, including basement, elevated to the flood depth number specified on the flood insurance rate map (FIRM), above the

highest adjacent grade. If no flood depth number is specified, the lowest floor, including basement, shall be elevated at least three feet above the highest adjacent grade. Openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of section 26-3.02.18(c), "elevated buildings."

(b) The flood plain administrator shall certify the lowest floor elevation level and the record shall become a permanent part of the permit file.

(c) New construction or the substantial improvement of a non-residential structure may be flood-proofed in lieu of elevation. The structure, together with attendant utility and sanitary facilities, must be designed to be water tight to the specified FIRM flood level plus one foot, above highest adjacent grade, with walls substantially impermeable to the passage of water, and structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. A

registered professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the official as set forth above and as required in section 26-3.02.15(a)(3) and section 26-3.02.15(b).

(d) Drainage paths shall be provided to guide floodwater around and away from any proposed structure.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 18-01, §§ 1, 2, 9-11-2018; Ord. No. 19-05, § 2, 8-13-2019)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:burke-county/zoning/26-3.02.20@2025-10-14-b8a7013ff8