A. The community development department shall review each application for a grading or clearing permit to determine its conformance with the provisions of this UDC.

B. Within 30 business days after stamping a completion date on an application, the community development department shall, in writing:

1) Approve the permit application;

2) Approve the permit application subject to such reasonable conditions as may be necessary to enforce the objectives of this regulation, and issue the permit subject to these conditions, providing the applicant an opportunity to comment within ten business days on the reasonable conditions stated; or

3) Disapprove the permit application, indicating the deficiencies and the procedure for submitting a revised application.

C. The community development director shall give notice to the applicant of the decision of the City of Canton by hand delivery or by mailing a notice, by certified mail, return receipt requested, to the address on the permit application on or before the thirtieth business day after the community development director has stamped completion date on an application. If mailed, notice shall be deemed to have been given upon the date of the mailing in conformity with this section.

D. If an application is revised and resubmitted, such application shall be assigned a new submission date.

If the application is denied because it does not contain the required information or the information is inaccurate or false, a new application shall be submitted to the community development department with all of the required information and such application shall be assigned a new submission date.

E. Upon expiration of the 30-business day period without a decision being issued, the applicant shall be permitted to begin mass grading or clearing activities under this UDC.

F. Upon making a final decision, the community development director shall stamp each application, and the permit if applicable, with a decision date.

G. If a permit applicant has two or more violations of previous permits of this UDC or permits under section

107.09.00 (Soil erosion, sedimentation and pollution control) of this UDC within three years to the date of filing of the application under consideration, the community development director shall deny the application.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2014-18, § 2, 8-21-2014)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:canton/zoning/107.11.05@2026-11-11-f3a8b1dab5

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Canton Zoning Ordinance, 107.11.05. Review and approval | Georgia Commons