108.04.04. Approval and acceptance of improvements.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A.1) The City of Canton shall officially accept the public improvements if all of the following conditions are met:

a. The final plat has been approved and recorded.

b. All performance and maintenance guarantees have been released.

c. Improvements have been approved for city acceptance.

2) During the 18-month maintenance period the development inspector shall observe the improvements for a full 12-month period. The developer shall be required to contact the development inspector in writing at the end of the 12-month period to initiate the city's approval process.

3) The development inspector shall prepare a punch list to the developer affording him/her a 60-day period in which to make all necessary repairs. The developer shall be required to contact the development inspector at the end of the 60-day period in writing after all punch list items have been completed. The development inspector shall have 30 days to make his/her final review for approval and shall notify the developer in writing of the results of this inspection.

4) An extension of the maintenance guarantee can be granted at the discretion of the city engineer. The amount of the maintenance guarantee will be reviewed by the development inspection manager, to determine if the amount is still acceptable to cover the construction cost of the required repairs, prior to granting any extensions. If any needed repairs are not completed by the developer within the specified period of time, the maintenance guarantee shall be called in to pay for such repairs. Should the amount of the maintenance guarantee be inadequate to pay for the full cost of the repairs, the City of Canton shall have the authority to collect the remaining amount from the developer.

5) At the time that the work is inspected and found free from defects, the development inspector shall provide the developer with written approval and the city engineer shall submit the improvements for city acceptance.

6) Acceptance shall be made as an item of business conducted at the next regular meeting of the Canton City Council.

B. Revisions to approved civil/site documents. Any revisions or changes made to civil/site documents as a result of changes made out in the field are required to be documented under the following criteria:

1) Revised civil/site documents (major).

a. Civil/site documents shall be re-submitted if proposed changes meet the criteria for major changes.

b. A change meeting one or more of the following criteria shall be considered a major change:

i. Any increase in the number of lots.

ii. Any revision to an approved detention pond.

iii. Any shifting of storm drainage pipes resulting in an increase of drainage basin by ten percent or more.

iv. Any revision to a road grade that has been approved at six percent or greater that result in an increase in road grade or in a reduction in road grades of four percent or more.

v. Any revision to a road layout resulting in an increase of road length by ten percent or more.

vi. Any renumbering of lot numbers, blocks, pods, etc.

vii. Any renaming of streets.

c. Documents for all major changes shall be re-submitted in accordance with the plan approval process prior to any construction changes in the field.

2) Revised civil/site documents (minor).

a. The following procedures must be followed for a minor change to be accepted the time of final plat submittal:

i. The change must be minor.

ii. The development inspector must review in the field and communicated his findings with the city engineer.

iii. The engineer of record must contact the city engineer.

iv. The engineer of record must follow-up with a letter indicating the revision or a plan as needed.

b. The following are definitions of what constitutes a minor change:

i. Any decrease in the number of lots.

ii. Any shifting of storm drainage pipes resulting in less than a ten percent increase of drainage basin.

iii. Any revision to an approved road grade that results in a change not exceeding four percent reduction.

iv. Any revision to a road layout resulting in a decrease in road length.

v. Shifting of lot lines within a phase with no increase in the total number of approved lots.

vi. Buffer revisions or variances that have been approved in compliance with this UDC.

vii. Any extension of pipes for aesthetic purposes.

viii. The division of an approved single-phase development into one or more phases.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2014-18, § 2, 8-21-2014)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:canton/zoning/108.04.04@2026-11-11-f72e4dbadf

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Canton Zoning Ordinance, 108.04.04. Approval and acceptance of improvements | Georgia Commons