Sec. 114-281. Bypass discharges.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Definitions. The following words, terms and phrases, when used in this section, shall have the meanings ascribed to them in this subsection except where the context clearly indicates a different meaning:

(1) Bypass means the intentional diversion of wastestreams from any portion of a user's treatment facility.

(2) Severe property damage means substantial physical damage to property, damage to the treatment facilities which causes them to become inoperable, or substantial and permanent loss of natural resources which can reasonably be expected to occur in the absence of a bypass. Severe property damage does not mean economic loss caused by delays in production.

(3) Permitted. A user may allow any bypass to occur which does not cause pretreatment standards or requirements to be violated, but only if it also is for essential maintenance to assure efficient operation.

These bypasses are not subject to the provision of paragraphs (c) and (d) of this section.

(b) Notice. Notice shall be given as follows:

(1) If a user knows in advance of the need for a bypass, it shall submit prior notice to the city manager, at least ten days before the date of the bypass, if possible.

(2) A user shall submit oral notice to the pretreatment coordinator of an unanticipated bypass that exceeds applicable pretreatment standards within 24 hours from the time it becomes aware of the bypass. A written submission shall also be provided within five days of the time the user becomes aware of the bypass. The written submission shall contain a description of the bypass and its cause; the duration of the bypass, including exact dates and times, and, if the bypass has not been corrected, the anticipated time it is expected to continue; and steps taken or planned to reduce, eliminate, and prevent reoccurrence of the bypass. The city manager may waive the written report on a case-by-case basis if the oral report has been received within 24 hours.

(c) Enforcement. Bypass is prohibited, and the city manager may take an enforcement action against a user for a bypass, unless:

(1) Bypass was unavoidable to prevent loss of life, personal injury, or severe property damage;

(2) There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate back-up equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass which occurred during normal periods of equipment downtime or preventive maintenance; and

(3) The user submitted notices as required under paragraph (c) of this section.

(d) Grant of approval. The city manager may approve an anticipated bypass, after considering its adverse effects, if the city manager determines that it will meet the three conditions listed in subsection (d) of this section.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2017-0921-01, § 1, 9-21-2017)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:canton/zoning/114-281@2026-11-11-3b5cb14db4

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Canton Zoning Ordinance, Sec. 114-281. Bypass discharges | Georgia Commons