Part - CODE OF ORDINANCES / Chapter 7.5 - DEVELOPMENT REGULATIONS / Article IV - SEWER SPECIFICATIONS

Sec. 7.5-93. Design criteria and materials for sewers.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(1) General: The criteria listed herein is not intended to cover all aspects of design, but rather to mention the basic guidelines and those particulars that are required by the city water department. For more detailed criteria, the reader should refer to standard references such as "Ten States Standards", Georgia EPD rules, Water Pollution Environment Federation Manual of Practice NO. FD-5, and other available literature.

(2) Types of sewers: All sewers for the conveyance of wastewater shall be designed as separate sanitary sewers in which groundwater, stormwater or other runoff from roofs, streets, parking lots, foundation drains and any source other than wastewater are excluded. Overflows from sewers shall not be permitted.

(3) Design period: Gravity sewer pipelines should, as a minimum, be designed with capacity sufficient to handle the estimated tributary population. Tributary population is considered to be all areas upstream of the discharge point of the system being designed as well as any anticipated pumped flow from other basins.

Sewers will be designed and installed to the uppermost property line of the development being served. Consideration should be given to the maximum anticipated capacity of institutions, industrial parks, etc.

(4) Capacity and size determinations: In determining the required capacities of sanitary sewers, the following factors should be considered:

(a) Maximum hourly sewage flow.

(b) Additional maximum sewage or waste flow from industrial plants.

(c) Ground water infiltration.

(d) Topography of the area.

(e) Depth of excavation.

New sewer systems shall be designed on the basis of an average daily flow of sewage of not less than four hundred (400) gallons per household per day. Normally, all sewers shall be designed for a peak flow of not less than two and one-half (2) times the average flow;

this peak factor will be higher for smaller basins (see design guides). Sewers should be designed to carry the peak flow when flowing at a depth of two-thirds (!) pipe diameter.

No sewer main shall be less than eight (8) inches in diameter, including in culs-de-sac, on hilltops, etc.; No service lateral shall be less than six (6) inches in diameter.

All proposed sewer mains sixteen (16) inches in diameter and larger shall be designed, engineered and constructed at the City's direction and paid for by the developer.

The city land use plan should be consulted and special consideration given to commercial and industrial areas. Where developers are installing major trunk lines or interceptor sewers, the City's long-range plan should be consulted as a guide and the sewer should as a minimum be of the size called for in the long range plan. If proposed land use conditions have changed subsequent to the plan, these changes should be factored into the determination.

(5) Special city requirements.

(a) Distance between manholes: Maximum distance between manholes -shall be four hundred (400) feet.

(b) Depth: Any sewers installed in the street shall, topography permitting, be sufficiently deep to provide five (5) feet of cover over service laterals at the street right-of-way, and over any part of the

main or service within the street rightof-way. The maximum depth for SDR 26 PVC pipe shall be fifteen (15) feet; depths in excess of fifteen (15) feet shall be

ductile iron. Sewers installed in streets shall have maximum depth of twelve (12)

feet unless otherwise noted. Any sewers on off street easements shall have a minimum of three (3) feet of cover unless ductile iron pipe is used. Filling over the pipe to obtain minimum cover is not

allowed. The maximum depth of sewer main shall be reviewed on a case-by-case basis by Cartersville Water Department.

(c) Drop across manhole: All manholes shall be provided with, a minimum vertical

drop across the manhole (between in and out pipes) of twenty-five hundredths (0.25) feet.

(d) Detection tape shall be installed over all sewer pipe. Bury tape eighteen (18) to

twenty-four (24) inches below grade. Use detection wire on all service laterals.

(e) Industrial users shall design, construct, operate and maintain other wastewater

pretreatment facilities whenever necessary to achieve compliance with the limitations in wastewater strength, to meet applicable categorical standards, or to

meet any other wastewater condition or limitation contained in the user's wastewater discharge permit. These pretreatment facilities shall be maintained in proper working condition at all times by the owner at his own expense.

(f) Grease, oil and sand interceptors shall be provided when, in the opinion of the

superintendent, thy are necessary for the proper handling of wastewater containing excessive amounts of grease and oil, or sand; except that such interceptors

shall not be required for residential users.

All interception units shall be of the type and capacity approved by the

superintendent and shall be so located to be easily accessible for cleaning and

inspection. Such interceptors shall be inspected, cleaned and repaired regularly, as needed, by the user at their expense.

Except where more complete pretreatment may be required, grease, oil, and/or sand interceptors shall be provided at all service stations, commercial or industrial food-handling establishments, feed mills, and at any other commercial or industrial establishment or any institution at which such devices are necessary for the proper handling of liquid wastes containing

grease and/or oil in excessive amounts, any flammable wastes, sand or other harmful ingredients except that such interceptors shall not be required for private living quarters or dwelling units.

All interceptors shall be of a type and capacity approved by the director and shall be maintained by the owner. The owner shall provide to the director or his designee, upon demand, proof, which

consists of a completed and legible manifest as included in subsection (c) of this chapter [sic], and/or frequency of

interceptor cleaning. The frequency for maintaining these interceptors shall, at the minimum, be as follows based on the

classifications listed:

Class Description of User Pumping Frequency I Existing food establishments with an underthe-counter grease trap or those that serve less

than 100 customers per day. New under-thecounter grease traps will not be allowed by the

City.

2 times/ year II Food establishments with an inground grease trap(s) up to 2,000 gallons capacity and/or serve more than two

meal times per day and serve less than 500 customers per day.

4 times/ year III Food establishments with an inground grease trap(s) in excess of 1,000 gallon capacity and/or serve three meal times per day or more than 500 customers per day.

12 times/ year The superintendent may in writing increase or decrease user's grease trap pumping frequency on a case-by-case basis based on actual observation of material

buildup in the grease trap.

Pumping requires the complete removal of the entire content of the trap with no reintroduction of any portion of the waste into the trap. The City may seek

additional enforcement action in accordance with Division 10 in the Code of Ordinances.

(6) Slope: All sewers shall be so designed and constructed to give mean velocities, when flowing full, of not less than 2.0 feet per second based on Manning's formula using an "n" value of

0.013. The following are the minimum slopes which should be provided; however, slopes greater than these are desirable:

Minimum Slope in Feet Sewer Size Per 100 Feet 8" 0.40 10" 0.29 12" 0.22 14" 0.17 15" 0.15 16" 0.14 18" 0.12 21" 0.10 24" 0.08 27" 0.067 30" 0.058 33" 0.052 36" 0.046 These minimum slopes will be used only when sufficient flows are expected to maintain a velocity of two (2.0) feet per second and maintain a cleaning action in the line. Sewers shall be laid with uniform slope between manholes. Sewers on ten (10) percent slope or greater, shall be ductile iron pipe and shall be anchored securely with concrete anchors spaced at maximum thirtysix (36) feet center to center (See Standard Details) to prevent displacement by erosion or shock. Maximum slope of sewers shall be twenty

(20) percent and sewers shall be designed at less than ten (10) percent whenever possible unless otherwise approved.

(7) Increasing size: When a small sewer is connected to a large one, the connection shall not be lower than matching the top of both sewers to the-same elevation.

(8) Gravity sewer pipe materials: The City reserves the right to disallow any manufacturer that does not have a consistent, long-term record of quality control and successful product performance. Gravity sanitary sewer pipe up through fifteen (15) inch diameter will normally be polyvinyl chloride (PVC), solid wall type SDR 26 thickness meeting ASTM D3034. Ductile iron pipe (DIP) will be used where certain conditions exist (see discussion of D.I.P.). For eighteen (18) inch diameter pipe and above, the contractor may have the option of using either polyvinyl chloride (P.V.C}or ductile iron pipe.

Bedding for sewer pipe shall be as follows (also see City Standard Details):

For PVC the minimum bedding shall be #57 or #89 crushed stone a minimum of six (6) inches below bottom of pipe extending up to the top of pipe. Installation shall be in accordance with

ASTM D2321.

For ductile iron pipe the minimum bedding shall be #57 or #89 crushed stone a minimum of six (6) inches below bottom of pipe extending up to the top of pipe. Installation shall be in accordance with ASTM A746.

In wet areas, the minimum bedding requirements will be increased as required to ensure a stable support under the pipe and on the sides of the pipe.

(a) Ductile iron pipe (DIP):

1. Scope: Ductile iron sewer pipe shall be required at all utility crossings with less than two (2) feet of clearance, in locations where cover is less than three (3) feet, at stream

crossings, where slopes exceed twenty (20) percent, and where cover exceeds fifteen (15) feet.

Ductile iron pipe shall be designed in accordance with ANSI Specifications A21.50-81. The thickness and class of the pipe shall be governed

by ANSI Specifications A21.50-81, but shall be no less than class fifty

(50) thickness.

Pipe shall be manufactured by American Pipe in accordance with ANSI Specifications A21.51-81 latest revision.

Pipe shall be Protecto 401 Coating epoxy lined and seal coated with approved bituminous seal coat in accordance with AWWA C151, latest revision. Coal tar epoxy lining shall adhere to the following specifications.

2. Joints: DIP joints shall be of the bell and spigot type with push-on joints,

conforming to ANSI Specification A21.11 or mechanical joints.

(b) Polyvinyl chloride (PVC) sewer pipe (four

(4) inches and above):

1. Scope: The contractor shall provide unplasticized polyvinyl chloride (PVC) plastic gravity sewer pipe meeting the requirements of ASTM D3034 (Latest Revision) in the sizes shown unless otherwise indicated on the contract documents.

2. Materials: Pipe and fittings shall meet the requirements as specified under ASTM D3034 (Latest Revision) for pipe through fifteen (15) inches and ASTM F679 for pipe

eighteen (18) inches through twentyseven (27) inches. All pipe and fittings shall be suitable for use as a gravity sewer conduit. Bell joints

shall consist of an integral wall section with elastomeric gasket joint which provides a watertight seal.

The pipe shall be capable of passing all tests which are detailed in this specification. Minimum wall thickness shall be SDR 26.

3. Fittings: All fittings and accessories shall be manufactured and furnished

by the pipe supplier. They shall have bell and/or spigot configurations and compatible with that of the pipe and shall have an equivalent

wall thickness.

4. Pipe and fittings tests: Before shipping any pipe, the manufacturer shall submit shop drawings to the

City and shall furnish written certification that all pipe through fifteen (15) inches meets ASTM Specification D3034 and that pipe eighteen (18) inches through twentyfour (24) inches meets ASTM F679.

The City reserves the right to require additional laboratory testing at the developer's expense to verify minimum quality standards are being met.

5. Pipe stiffness: Minimum "pipe stiffness" (F/Y) at five (5) percent deflection shall be forty-six (46) psi for all sizes, when tested in accordance

with ASTM Standard Method of Test D2412 (Latest Edition), to determine the "External Loading Properties of Plastic Pipe by ParallelPlate Loading." There shall be no evidence of splitting, cracking, or

breaking at a deflection of up to thirty (30) percent of the original diameter.

6. Fusion quality: There shall be no evidence of flaking, swelling, or disintegration when the pipe material is tested in accordance with ASTM D2152, "Quality of Extruded

Poly (Vinyl Chloride) pipe by Acetone Immersion".

7. Joint tightness: Pipe and fitting joints shall comply with ASTM D3212

(Latest Edition) for "Joints for drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals". Joint assemblies shall not leak when

subjected to both an internal and external hydrostatic test at equivalent pressures of ten and eight-tenths (10.8) psi gauge for a period of one (1) hour. Pipes shall be tested in straight alignment, axially deflected position, and by shear load test as otherwise defined in

paragraphs 7.2, 7.3, and 7.4 of ASTM D3212.

8. Installation: PVC pipe will be installed in accordance with ASTM D2321 (Latest Revision). Initial backfill shall be compacted to the densities outlined in D2321. The City may require random compaction tests at the developer's expense to ensure compliance with D2321.

9. Deflection limit: Vertical deflection of installed pipe shall not exceed

five (5) percent of the undeflected diameter as defined in ASTM D3034.

Upon completion of the pipe laying the pipe will be tested for conditional acceptance. The test shall be performed by the contractor pulling a mandrel of specified dimensions through the pipeline. If deflection exceeds five (5) percent, replacement or correction should be made.

(9) Precast concrete manholes.

(a) Manholes: Sewer manholes shall consist of precast reinforced concrete sections

with eccentric top section, or flat slab for shallow manholes, and a base section

conforming to the typical manhole details as shown on the standard detail drawings. Flat top manholes will be approved only if a need for such can be demonstrated by the design engineer. All manholes

must be a minimum of four (4) feet in diameter.

(b) Manhole sections: Precast manhole sections shall be manufactured, tested, and marked in accordance with the latest

provisions of ASTM standard specifications, Serial Designation C 478.

(c) Manhole section joints: Joints of the manhole sections shall be of the tongueand-groove type with the inside tongue in the up position, sections shall be joined using a double strand seal of butyl mastic sealant (Kent Seal, Ram-Nech or equal).

The inside and outside of all joints, lift holes and any bricks or precast adjusting rings shall be covered with non-shrink

grout.

(d) Lift holes: Each section of the precast manhole shall have not more than two

(2) holes for the purpose of handling and laying. These holes shall be sealed before backfilling using either rubber plugs

specially designed for this purpose or with quick-setting cement mortar.

(e) Manhole steps: Manhole steps conforming to the applicable provisions of ASTM Specification C 478, latest edition, shall be of #4 steel reinforcing bars covered

with polypropylene plastic or rubber and shall be supplied with depth rings and

other necessary appurtenances.

(f) Pipe holes: Holes in precast bases to receive sewer pipe shall be precast at the factory at the required locations and

heights. Knocking out of holes in the field will not be permitted on new construction; however, holes can be cored in the field with a coring machine. All

manholes shall have Kor-N-Seal by Press Seal Gasket Corporation (or equal) rubber boots for all pipe entries/exits.

(g) Inverts: Manhole inverts shall be constructed of either "row lock" brick and mortar in accordance with details on

standard detail drawings and the invert (flow channel) shall have the saine crosssection as the sewers which it connects.

The manhole bench and invert shall be carefully formed to the required size and grade by gradual and even changes in

direction. Changes in direction of flow through the invert shall be made to a true curve with as large a radius as the size of the manhole will permit. Inverts shall have a "smooth trowel" finish. The manhole bench shall be sloped thirty

(30°) degrees from the manhole wall toward the invert.

(h) Manhole foundation: The manhole base shall be set upon a twelve (12) inch

minimum thickness compacted mat of Size #57 crushed stone graded level. In wet areas the crushed stone mat shall be thickened as needed to provide a nonyielding foundation.

(i) Brick: Brickwork required to complete the precast concrete manhole shall be

constructed using one (1) part portland cement to two (2) parts clean sand, meeting ASTM Specifications, Serial Designation C 144, thoroughly mixed to a workable plastic mixture. Brickwork shall be

constructed in a neat and workmanlike manner. Nonshrink grout shall be used to grout interior and exterior exposed brick joints and faces. No more than three (3) courses of brick with nine (9) inch maximum total depth of bricks may

be used to adjust manhole covers.

(j) Frame and cover: The cast iron frame for the manhole cover shall be set at the

required elevation and thoroughly anchored to the masonry in a bed of mortar. Frames and covers shall be City of Cartersville standard casting design by Vulcan Foundry, Standard Model V 1327-1-CWD (see standard drawings).

Where manholes are constructed in paved areas, the top surface of the frame and cover shall be tilted, if necessary, to conform to the exact slope, crown and grade of the existing adjacent pavement.

In areas where manhole tops may be submerged by street runoff or high flood waters, the manhole lid shall be watertight by Vulcan Foundry, water-tight Model V2327-1-CWD.

(k) Masonry work: Masonry work shall be allowed to set for a period of not less than twenty-four (24) hours before being placed under traffic or in operation. All loose or waste material shall be removed from

the interior of the manhole.

(l) Location: Manholes shall be installed at the end of each line; all changes in grade, size, or alignment; at all intersections;

and at distances normally not greater than four-hundred (400) feet. Cleanouts may be used only for special conditions and shall not be substituted for manholes nor installed at the ends of laterals greater than one-hundred fifty (150) feet in length.

Manholes in cross-country areas shall be elevated so that the top is twenty-four

(24) inches above ground.

(m) Drop manholes: A drop pipe shall be provided for a sewer entering a manhole at an elevation of more than two (2.0) feet above the manhole invert. The drop pipe shall be of PVC materials with ductile iron mechanical joint fittings. All outside ninety (90°) degree elbows shall have concrete support blocking poured

below the elbow to rest on stable undisturbed earth. Outside drop manhole will be noted on the construction plans at any time the drop exceeds two (2.0) feet.

Where the difference in elevation between the incoming sewer and the manhole

invert is less than two (2.0) feet, the invert shall be sloped from invert to invert to prevent solids deposition. Areas around the pipe will be backfilled with

#57 or #89 crushed stone.

(10) Casings.

(a) Steel casing pipe shall be used where boring and jacking of mote than twenty

(20) feet in length is required for installation.

(b) Steel casing pipe shall be Standard Class thickness with a minimum yield strength

of thirty-five thousand (35,000) psi and shall conform to the requirements of

ASTM Al39. It shall be fully coated on the exterior and interior with a coal tar coating. The casing pipe diameter shall

be six (6) to eight (8) inches greater than the "bell" diameter of the earner pipe.

(c) Wherever steel casing is required, the carrier pipe shall be ductile iron pipe

with push-on joints or PVC. Approved spacers made of stainless steel straps with nylon skids shall be used to center the carrier pipe; two (2) spacers per

section of pipe will be used.

(11) Wastewater lift stations. The following minimum requirements apply to wastewater lift stations:

(a) General:

1. Minimum pump size for pump stations shall be a minimum rated capacity of one-hundred fifty (150)

gpm with ten (10) hp rated motors.

Lift stations shall utilize two (2) submersible centrifugal pumps each having a capacity equal to the design flow. Provide a spare pump of identical capacity.

2. Lift stations having a capacity of five-hundred (500) gpm or more shall be reviewed on an individual basis and may have requirements differing from those outlined herein.

3. Force mains shall be sized to provide a velocity of at least two (2) feet per

second.

4. The design shall allow for easy removal of any pump or equipment item without the need of shut-down of the entire lift station.

5. The design engineer should consult the City water department after preliminary design data has been developed for information on approved pump manufacturers. The City reserves the right to review each application on. an individual basis and to reject the use of nonapproved manufacturers or designs.

(b) Submittals:

1. Submittal of construction plans shall include the following lift station

information:

a. Capacity calculations: Use two

(2) gpm capacity per house/ living unit on residential development of less than twohundred (200) units, except that the minimum pump capacity

shall be one-hundred fifty (150) gpm.

b. System head calculations;

tabulated and plotted on the pump curve. Include a plot of force main velocity.

c. Standard drawings, details and specifications sufficient to ascertain compliance with these regulations.

d. Cycle time. Calculations showing determination of wet well volume and cycle time at design

conditions. Wet well volume should be sufficient to provide a cycle time of no less than five

(5) minutes from a pump "on" to the next pump "on" time.

e. Storage volume. Calculations showing the volume of storage available in the event of a power outage. The storage zone shall be delineated on plan and profile drawings of the sewer system. (See subsection "standby power" below.)

f. Construction drawings and specifications in sufficient detail to ascertain compliance with these regulations.

g. Buoyancy computations showing that structures are protected against flotation.

2. Shop drawings. After construction plan approval but before purchasing any lift station equipment, shop drawings shall be submitted including the following information:

a. Manufacturer's catalog sheets, performance curves, installation drawings, specifications, and list of options for the

specific pump that is offered for approval.

b. Similar catalog data for controls, valves, hatches, yard hydrants, precast wet well and other manufactured items.

3. Certification. After installation and before placing the system into full

operation, the work must be inspected by the developer's engineer who must then issue a certification to the City verifying that all work has been done in accordance with approved plans. After acceptance of the work by the City, a factory representative shall inspect and start up the system certifying rotation, capacity, amperage draw, lack of vibration and other standard check points. This certification shall state the beginning date of the warranty and include a copy of the warranty.

The factory representative shall provide a minimum of four (4) hours training.

4. O & M manuals. On or before the date of start-up, five (5) sets of factory O & M Manuals shall be delivered to the City. These shall include the name of the purchaser;

the serial numbers of pumps, detailed wiring schematics, telephone number and address for purchase of parts.

5. After construction is complete, asbuilt drawings shall be furnished including one (1) set of mylar sepias

plus two (2) sets of prints.

(c) Spare parts.

1. Lift stations shall be supplied with a spare complete pump plus a complete set of manufacturer's recommended spare parts.

(d) Standby power.

1. The minimum requirement for standby power for lift stations shall be that each station have a permanent in-place generator and shall have an automatic transfer switch.

2. Emergency standby power will be supplied by an on-site emergency generator. The generator shall be diesel powered with an automatic transfer switch and provisions for an automatic exercise cycle.

(e) Site requirements:

1. Flooding. Lift stations shall remain fully operational and accessible during the twenty-five (25) year flood. All electrical controls shall be above the one-hundred (100) year flood level. All motors and mechanical equipment shall be protected against physical damage from the

one-hundred (100) year flood.

2. Access road. Access roads shall be paved with a twelve (12) foot wide surface of either concrete (four (4) inch thick with wire mesh) or asphalt (six (6) inches graded aggregate base plus two (2) inches Type E asphalt).

Maximum grade shall be twenty

(20) percent.

3. Ownership. Both the lift station site and the access road right-of-way

shall have ownership dedicated to the City, and this shall be indicated on the subdivision plat. The dedicated space for the lift station shall include sufficient space for parking of two (2) trucks, plus turnaround, plus slope maintenance. The dedicated width on road right-ofway shall be thirty (30) feet minimum.

4. Fencing. Lift station sites shall be fenced with a minimum of six (6) foot-high chain link fencing topped with three (3) strands of barbed wire. Access gates shall be a minimum of fifteen (15) feet in width.

The space inside the fencing shall be large enough to facilitate service vehicle access to the pumping station wet well and other facilities. A paved tum around area shall be

provided whenever the access road length exceeds two-hundred (200) feet or when the road grade exceeds ten (10) percent.

5. Water supply. A metered water supply line (three quarter (3/4) inches minimum size) shall be installed to the site, and a freeze-proof yard hydrant located near the wet well.

The hydrant shall be equipped with a suitable backflow preventer.

6. Lighting. One (1) pole-mounted, photo cell controlled, one-hundred fifty (150) watt mercury vapor security light shall be installed. It shall be equipped with a manual on/off switch (located in the main control panel) to override the photo cell control.

7. Screening. Where natural screening is not present to screen the site from view of residences, special plantings shall be installed to screen the site.

8. Ground covers. All unpaved ground areas inside the fence and extending four (4) feet beyond the fence shall be treated with an herbicide

and covered with a geotextile fabric, followed with a four (4) inch thick layer of no. 57 stone. The geotextile fabric shall be a non-woven polypropylene weighing 8 oz./S.Y.

with a minimum burst strength of two-hundred fifty (250) psi, such as Amoco type 4553 or equal.

(f) Design features:

1. Wet well volume. The wet wall volume shall be sized to limit pump cycles to no more than four (4) cycles per hour under worst conditions.

2. Ventilation. For wet wells, the minimum requirement shall be a single six (6) inch vent with stainless steel mesh screen designed for natural ventilation. Where conditions are conducive to formation of hazardous conditions (in the design

engineer's opinion) then mechanical ventilation shall be provided. For dry wells, mechanical ventilation shall be required.

3. Structures. Submersible lift stations shall have a wet well structure and a separate valve pit. Both

structures shall be precast concrete with a monolithic base. The valve pit shall be a minimum of four (4) foot x four (4) foot x five (5) foot deep with manhole steps, and provided

with a floor drain pipe, and a three

(3) foot x three (3) foot lockable aluminum access hatch. Wet wells may be either round or rectangular and shall have a diameter or width of at least four (4) feet. Wet wells shall be sized to meet cycle time requirements with a drawdown (i.e.

the distance between high water level and low water level) of not more than three (3.0) feet. The wet well shall have a lockable aluminum hatch large enough for easy removal of pumps. Riser sections in precast units shall be sealed watertight using two (2) strands of mastic and a coating of mortar on the inside and outside of the structure. Structures shall be adequately reinforced for all loading conditions normally encountered during shipping, construction and service. All openings (for pipes, hatch, conduits) shall be either cast in place or neatly cut.

Sewer pipe connections shall utilize rubber boot connectors and be watertight. The wet well shall be equipped with an aluminum ladder.

4. Accessories. All materials inside the wet well and valve pit shall be

corrosion resistant. Mechanical equipment requiring ferrous metals shall have a coal tar epoxy coating.

Guide rails for pumps shall be stainless steel. Miscellaneous metals including fasteners shall be

aluminum or stainless steel; anchor bolts shall be stainless steel.

5. Pressure gage. A pressure gage shall be installed on the force main downstream of the gate valves, inside the valve pit and visible from ground level. A corporation stop shall be installed on the tap to allow removal of the gage.

6. Valves. The discharge pipe of each pump shall have a check valve followed by a gate valve before the two

(2) pipes join into a common force main.

7. Surge control valves. The pumping system shall be checked to determine if a surge control valve is required.

If a valve is required, it shall be located within the valve pit on the common force main and a drain line installed to drain to the wet well.

(g) Pump features:

1. Pump shall have the following features:

a. Non-clog impeller.

b. Be capable of passing a three

(3) inch sphere.

c. Be capable of dry operation without overheating.

d. Have dual mechanical seals with seal leak indicator light in the control panel.

e. Pump and motor casing shall be cast iron, and all fasteners shall be stainless steel.

f. Motor shall be selected to be non-overloading under all operating conditions.

g. Motor winding shall have a heat sensor with auto reset to prevent overheating; threephase motors shall have two

(2) sensors.

h. Operating speed of the pump shall not exceed one-thousand eight-hundred (1800) rpm without special approval.

i. Motor shall have upper and lower roller bearings.

j. The pump shall be automatically connected to the discharge connection elbow when lowered

into place and shall be easily removed for inspection or service. There shall be no need for personnel to enter pump well. Sealing of the pumping unit to the discharge connection elbow shall be accomplished by a simple linear

downward motion of the pump.

k. Each pump shall be equipped with a chain (of aluminum or other non-corrosive material) for easy removal.

(h) Force main.

1. The force main shall be sized for a minimum velocity of two (2) feet per second.

2. Force mains shall be ductile iron pipe.

3. The force main profile shall slope continuously upward where practical. If high points occur where air could be trapped in the pipe, then

an air release valve (of the type made for swage applications) will be installed (in a manhole) at the high points.

(i) Electrical:

1. Lift station controls and electrical components shall be factory-wired in completely weatherproof stainless steel metal cabinets (NEMA 4X stainless steel). The cabinet shall

be provided with condensate heaters. Spare fuses of each type that is used in the electrical/control system

shall be furnished.

2. A main circuit breaker shall be installed lo disconnect power to the entire station.

3. Three (3) phase power will be provided for all motors.

4. Protection against voltage surge and loss of a phase shall be provided.

5. The factory-wired panel shall be equipped with a ground bus and neutral bus. Terminal shall be suitable for either aluminum or copper wire. All internal panel wiring shall

be copper.

6. Motors shall be suitable for either two-hundred thirty (230) volt or forty

(40) volt operation. Design engineer shall consult with the City electri- cal department to verify specifics pertaining to electrical power availability.

7. Wet well level shall be controlled by four (4) sealed mercury tube float

switches. All floats shall be provided with twenty-five (25) feet of Type SJO flexible cord and shall be attached to a bracket mounted at the top of the wet well. Float functions shall be as follows:

Float No. 1 Low Level (Pumps Off) Float No. 2 High Level (Lead Pump On) Float No. 3 Extra High Level (Lag Pump On) Float No. 4 Surcharge Level (Alarm Activated)

8. The pump control system shall include the following features:

a. Lead pump/lag pump alternator.

b. Alarm light and horn to indicate high water level.

c. Seale failure indicating light.

d. Pump failure indicating light.

e. Condensate heater.

f. Lead pump selector switch.

g. H-O-A switch and run light for each pump.

h. Control voltage shall be onehundred twenty (120V) volts.

i. Wiring shall be neatly tied, and number coded to facilitate.

maintenance. A schematic diagram shall be furnished with the panel.

j. A one-hundred twenty (120) V.

GFCI type electrical receptable shall be located at the control panel.

k. Pump stations will be equipped with a remote transmitting unit and telemetering circuitry connecting to the city's SCADA system. The design engineer

should consult the City for specific requirements at the beginning of design.

(j) Warranty:

1. Regardless of the manufacturer's warranty terms, the developer will be responsible for all repairs necessary within one (1) year from the date the station is completed and

approved by the City. The developer will be required to furnish such assurances to the City as deemed appropriate by the City to ensure prompt action.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 43-24, § 1, 10-3-24)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:cartersville/zoning/7.5-93@2026-11-11-fca9c132e3

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Cartersville Zoning Ordinance, Sec. 7.5-93. Design criteria and materials for sewers | Georgia Commons