Chamblee · Ordenanza de zonificación
Appendix A - UNIFIED DEVELOPMENT ORDINANCE / Title 3 - DEVELOPMENT AND PERMITTING / Chapter 350 - INFRASTRUCTURE / Article 1 - STREETS AND SIDEWALKS
Section 350-6. Curbs and gutters.
Sobre este texto
- As published by Municode, retrieved 2026-11-14
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Curb and gutter required. All new streets and Project Access Improvements shall be provided with curb and gutter. All gutters shall drain smoothly with no areas of ponding.
(b) Curbing.
(1) When an existing street within the overlay is improved, extended or rebuilt, the curbing for such street improvement, extension or reconstruction shall be granite curbing of a similar size and type as the granite curbing used on such existing street.
(2) When an existing street with granite curbing is improved, extended or rebuilt, the curbing for such street improvement, extension or reconstruction shall be concrete curbing or granite curbing of a similar size and type as the granite curbing used on such existing street.
(3) Otherwise, new curbing shall meet the following requirements:
a. Concrete shall be Class "A" (as defined by Georgia Department of Transportation) and have a minimum strength of 3,000 PSI at 28 days.
b. Typical minimum section shall be 6" x 24" x 12".
c. See UDO Addendum 3(e) for Typical Curbing Details.
d. Roll curbing as shown as Type I in UDO Addendum 3(e) may be permitted subject to approval of the Public Works Director.
(c) Construction methods. Curb and gutter shall be set true to line and grade, horizontal be field staked, and finished to the section shown on the plans. Along the Project Access Improvements of a road which the Department of Public Works has identified for resurfacing within one year of the new construction, the grade of the new gutter shall be placed 1" above the Project Access Improvement pavement grade in areas where drainage will not be adversely affected.
(1) Line and grade shall be field staked for grades less than two percent and grades over 12 percent, and within 100 feet in both directions from all low points.
(2) One-half inch expansion joints or pre-molded bituminous expansion joint material shall be provided at all structures and radius points and at intervals not to exceed 250 feet in the remainder of the curb and gutter.
(3) Inferior workmanship or unprofessional construction methods resulting in unacceptable curb and gutter will be cause for rejection of the finished work.
(4) Disturbed areas along all curbing shall be backfilled, stabilized and grassed.
Historia
(Ord. No. 743, 12-19-17; Ord. No. 828, 11-21-23)