5-34.6. Permits.
Sobre este texto
- As published by Municode, current through 2024-10-07
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
Types of permits:
a. Manufactured Home Location Permits.A location permit must be obtained by any individual or business seeking to locate a manufactured home within Coffee County as provided by this LDC, unless otherwise exempted. All manufactured homes are subject to an inspection prior to the issuance of a permit unless otherwise exempted.
b. Certificate of Occupancys. No Certificate of Occupancy may be issued unless a Manufactured Home passes the inspections described herein. After the Manufactured Home reaches its destination site, is properly set up, and is connected to all necessary utilities, a Certificate of Occupancy must be issued before the Manufactured Home is occupied.
Minimum requirements for purposes of obtaining a Manufactured Home location permit: The Building Inspector shall inspect all manufactured homes prior to issuing a location permit. The official shall inspect the manufactured home for the following:
a. An inspection to evaluate whether the facilities set forth at section 5-33.4 are available, intact, and functioning as required by that section; and
b. That the Manufactured Home to be relocated otherwise complies with all of the other provisions of this ordinance.
Failure to meet any of the requirements of this section shall result in denial of an application for location of a Manufactured Home.
Minimum requirements for purposes of obtaining a Certificate of Occupancy: The Building Inspector shall inspect all Manufactured Homes prior to residential occupancy. A previously inspected unit shall be required to be re-inspected on being moved to a new location within the County. The Building Inspector shall be granted a final inspection to each home, after set-up, to verify facilities required. Inspections shall include:
a. Proper setbacks.
b. Sufficient off-street parking.
c. Installation of an approved septic tank or an approved sewer system.
d. Inspection of electrical wiring.
e. Inspection of anchoring and tie-down installations.
f. Inspection for proper utilities connections.
g. Inspection for proper sewage connections.
h. Adherence to all applicable Coffee County Codes.
i. Reinspection of the required facilities to ensure that no change in condition or function occurred during transport.
j. All Manufactured Homes that are located in Coffee County, and change ownership, but are not relocated must be inspected on site prior to issuance of Certificate of Occupancy.
k. Individuals purchasing Manufactured Homes that require repairs must understand that if the home fails inspection, Coffee County will not issue a Certificate of Occupancy.
Inspection fees: Inspections conducted within the jurisdictional boundaries of Coffee County are subject to a fee established by the Board of Commissioners in the schedule of fees. Should follow up inspections be required, an additional fee must be paid as established in the schedule of fees.
Revocation of Certificate of Occupancy: All Manufactured Homes within Coffee County shall be subject to inspection at any time. After personal inspection of the manufactured housing unit and upon discovering code violations, the Building Inspector shall notify the owner of the unit in writing of the specific code violations, the corrections, repairs, or changes needed, and the number of days allotted for such. If the cited violations are not corrected within 60 days after receiving written notice of the specific code violations from the Building Inspector and if further inspection reveals that the cited violations have not been corrected, the Certificate of Occupancy may be revoked.
Notice of revocation of a Certificate of Occupancy shall be given in writing.