7-14. Base and Pavement Minimum Requirements.
Sobre este texto
- As published by Municode, current through 2024-10-07
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
a. Roadway Sectional Composition.
i. The applicable standard shall be based on functional classification. See latest edition of the Georgia Department of Transportation (GDOT) Standard Specifications for the Construction of Roads and Bridges for specifications of referenced asphaltic concrete types. For all street classifications, before asphalt pavement is placed, a bituminous prime shall be applied to the base material in accordance with GDOT specifications. Application rate shall be a minimum of
0.15 gallons and a maximum of 0.20 gallons per square yard.
b. Roadways shall be constructed with cross sections according to the following requirements at a minimum. The County will consider alternate designs provided that a suitable pavement design is provided that accommodates the heaviest and maximum traffic counts expected for a particular development.
1. Local Streets.
i. 1.5" - 12.5 mm Asphalt SuperPave (165 lbs./sq. yd.) top course;
ii. 8" - Graded aggregate base (GAB); or 6" - Soil cement (Soil cement shall be mixed in place).
Base shall be compacted to at least 98 percent maximum dry density per standard proctor test ASTM 0698.
2. Collector Streets (for residential and commercial developments).
Asphalt Pavement:
i. 1.5" - 12.5 mm Asphalt SuperPave (165 lbs./sq. yd.) (top course);
ii. 2" - 19 mm Asphalt SuperPave (220 lb./sq. yd.) (binder);
iii. 8" - Graded aggregate base (GAB); or iv. 6" - Soil cement (Soil cement shall be mixed in place);
v. Base shall be compacted to at least 98 percent maximum dry density per standard proctor test ASTM 0698;
vi. Graded aggregate base may include crushed concrete, limerock or granite;
vii. For soil cement, a mix design by a licensed Geotechnical Engineer in the state of Georgia must be submitted to the County Engineer for approval.
3. Arterial Roads (including industrial roads).
Asphalt Pavement:
i. 1.5" - 12.5 mm Asphalt SuperPave (165 lbs./sq. yd.) (top course).
ii. 2" - 19 mm Asphalt SuperPave (220 lb./sq. yd.) (binder).
iii. 3" - Asphaltic base 25mm (330 lb./sy) Asphalt SuperPave.
iv. 8" - Graded aggregate base (GAB); or
v. 6" - Soil cement (Soil cement shall be mixed in place).
vi. Base shall be compacted to at least 98 percent maximum dry density per standard proctor test ASTM 0698.
vii. Graded aggregate base may include crushed concrete, limerock or granite.
viii. For soil cement, a mix design by a licensed Geotechnical Engineer in the state of Georgia must be submitted to the County Engineer for approval.
4. Commercial Development.
Heavy Duty Asphalt Pavement:
i. 1.5"- 12.5 mm Asphalt SuperPave (165 lbs./sq. yd.) (top course).
ii. 2"- 19 mm Asphalt SuperPave (220 lbs./sq. yd.) (binder).
iii. 8"- Graded aggregate base (GAB); or iv. 6"- Soil Cement (Soil cement shall be mixed in place).
v. Base shall be compacted to at least 98 percent maximum dry density per standard proctor test ASTM D698.
vi. Graded aggregate base may include crushed concrete, limerock or granite.
vii. For soil cement, a mix design by a licensed Geotechnical Engineer in the state of Georgia must be submitted to the County Engineer for approval.
Light Duty Asphalt Pavement:
i. 1.5" - 12.5 mm Asphalt SuperPave (165 lbs./sq. yd.) (top course).
ii. 8" - Graded aggregate base (GAB); or iii. 6" - Soil Cement (Soil cement shall be mixed in place).
iv. Base shall be compacted to at least 98 percent maximum dry density per standard proctor test ASTM D698.
v. Graded aggregate base may include crushed concrete, limerock or granite.
vi. For soil cement, a mix design by a licensed Geotechnical Engineer in the state of Georgia must be submitted to the County Engineer for approval.
5. Industrial Development.
Heavy Duty Asphalt Pavement:
i. 1.5" - 12.5 mm Asphalt SuperPave (165 lbs./sq. yd.) (top course).
ii. 2" - 19 mm Asphalt SuperPave (220 lb./sq. yd.) (binder).
iii. 3" - Asphaltic base 25mm (330 lb./sy) Asphalt SuperPave.
iv. 8" - Graded aggregate base (GAB); or
v. 6" - Soil cement (Soil cement shall be mixed in place).
vi. Base shall be compacted to at least 98 percent maximum dry density per standard proctor test ASTM D698.
vii. Graded aggregate base may include crushed concrete, limerock or granite.
viii. For soil cement, a mix design by a licensed Geotechnical Engineer in the state of Georgia must be submitted to the County Engineer for approval.