Appendix A - UNIFIED DEVELOPMENT ORDINANCE / Chapter 8 / Article 6 - INSTALLATION OF STORMWATER DRAINAGE FACILITIES
Section 8.6.4. Maintenance and Ownership Responsibilities.
Sobre este texto
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
A. Ownership.
1. Private Ownership Required. Any stormwater management facility that services a single lot or commercial and industrial development shall be privately owned and maintained.
2. Residential Areas. Developers of stormwater management facilities in residential areas may petition the City to accept maintenance of those private facilities if those facilities meet current standards. In order to consider acceptance, the City must determine compliance with the standards listed below.
(A) Ownership. The City is granted ownership of the parcel of land on which the stormwater management facility is located. Ownership is to include a minimum of a 20-foot right-of-way access to the facility.
(B) Standards of Construction, Operation and Maintenance. The facility meets current standards for acceptance at the time of petition.
(C) Repair and Cleanliness. The facility is in good repair and is clean prior to acceptance.
(D) Ease of Maintenance. The facility is easily accessible for maintenance.
B. Maintenance.
1. Maintenance Responsibility. It shall be the responsibility of the developer to maintain all facilities required by the stormwater management site plan during construction and for a two year maintenance period following approval of the final subdivision plat or issuance of a certificate of occupancy, as applicable. If the developer takes the extra measures defined in the Georgia Stormwater Management Manual, the maintenance period may be reduced to one year.
The developer shall be responsible for removing temporary structures or facilities at the completion of the construction.
2. Maintenance Bond. A continuous bond to cover maintenance and construction shall be provided at acceptance. The bond will remain in force until the criteria, described in the Georgia Stormwater Management Manual, have been complied with, as determined by the Department of Engineering.
3. Maintenance following Two Year Period. The owners of the property shall be responsible for maintaining the permanent facilities identified by the stormwater management site plan to remain after construction is complete, following the two-year maintenance period.
4. Failure to Maintain. Should an owner or developer, whichever is the responsible party, fail to maintain the stormwater management facilities in a state of service intended by the stormwater management site plan, then the Department of Engineering shall notify the responsible party in writing within three days of the deficiencies and of specific minimum maintenance requirements to remedy such deficiencies.
(A) Failure to Perform Maintenance. If the responsible party fails to perform the required maintenance work within 10 days then the owner shall be in violation of the provisions of this Ordinance.
(B) Liens. Should it become necessary for the City to perform work in order to maintain a private facility then the City may place a lien against the property until full reimbursement for the work performed by City forces is recovered.
C. Inspections.
1. Schedule of Inspections. A representative from the Department of Engineering shall determine inspection schedules necessary to enforce the stormwater requirements. Inspections may include, but are not limited to, the following:
(A) An initial inspection prior to stormwater management site plan approval;
(B) A bury inspection prior to burial of any underground drainage structure;
(C) Erosion control inspections as necessary;
(D) A finished inspection when all work, including installation of drainage facilities, has been completed; and
(E) A maintenance inspection of private facilities to insure their continued proper operation.
2. Entry for Inspections. A representative from the Department of Engineering shall be permitted to enter all properties, including those for which the City holds a negotiated easement for repairs and maintenance, for regular inspections in accordance with this Chapter. The engineering representative shall duly notify the owner/operator of said property, or representative on site, except in the case of an emergency.
3. Inspection Reports. Inspection reports shall be maintained in a permanent file located in the office of the Department of Engineering. All such records shall be open to the public.