Sec. 3. Roadway excavation.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

3.01 General. Roadway excavation shall consist of the excavation, hauling and satisfactory placement or disposal of all materials. This work shall also include all ditch excavation with the exception of channel excavation.

All suitable materials excavated from ditches shall be utilized in the construction of roadway embankments except where otherwise directed by the engineer.

Material excavated from the ditches which is unsuitable for roadway construction shall not be deposited or allowed to remain within three feet of the edge of the ditch. Such material shall not be left in unsightly piles, but shall be spread in uniform layers neatly leveled and

shaped. Adequate openings shall be provided in spoil banks to allow surface drainage of adjacent land. When shown on the plans or required by the engineer, surface ditches of adequate dimensions shall be cut at the tops of cut slopes, extending to each end of the cuts in

order to carry the water from the side hill. Side ditches or gutters emptying from cuts to embankments shall be turned outward so as to avoid erosion of the embankments.

When excavation operations encounter artifacts of historical or archaeological significance, such operations shall be temporarily discontinued and not resumed until directed by

the engineer.

All material to be excavated, regardless of its nature or composition, shall be defined as unclassified excavation unless otherwise specified on the plans. All suitable material removed in the excavation shall be used as far as practicable in formation embankments,

subgrades and shoulders and at such other places as may be on the plans or directed by the engineer. The engineer will designate materials which are unsuitable.

3.02 Erosion and siltation control. The contractor shall take whatever measures necessary throughout the life of the project to control erosion and to minimize silting of rivers, streams and impoundments. Construction of drainage facilities as well as performance of all other contract work which will contribute to the control of erosion and siltation shall be carried out in conjunction with earthwork operations.

3.03 Rock excavation. Rock, wherever encountered, shall be removed and disposed of as shown on plans or as directed by the engineer. In a cut, when rock is encountered, any flattening of the slope already begun shall be transitioned to leave the cut with a pleasing appearance.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:cusseta-chattahoochee/zoning/appendix-c-3@2026-11-11-13ee5f649e

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.