Intent and Purpose. The M-2 Heavy Manufacturing/Industry District provides a location for those industrial operations and processes that are not public nuisances and are not dangerous to the health, safety or general welfare of the inhabitants of the City of Dacula, Georgia. The M-2 Heavy Manufacturing/Industry District shall be located on or have ready access to a major street, as defined herein.
A. Area, Yard and Height Requirements:
Dist.
Minimum Dwelling Unit Size (Sq.Ft.)
Minimum Lot Area Size (Sq.Ft) Minimum Width (Ft) Setback from Right-of-Way (Ft.)
Minimum Side Yard (Ft.)
Minimum Rear Yard (Ft.)
Maximum Height (Ft.)
Major Street (Ft.)
Interior Street (Ft.)
M-2 - 43,560 100 50 50 20(1) 20(1) 40
(1) Buffer zones are required in addition to side and rear yard where an office-institutional, business, or manufacturing use abuts a Residential District.
B. Permitted Uses:
Only the following permitted uses shall be allowed in the M-2 Heavy Manufacturing/Industry District and no structure shall be erected, structurally altered or enlarged for any use other than a use permitted herein with the exception of: a) uses lawfully established prior to the effective date of the amendment; b) special uses as permitted herein; or c) accessory uses defined in Article III, Definitions; or other uses which are clearly similar to and consistent with the purpose of this District.
1. Aircraft Factory.
2. Alcoholic Beverage Manufacturers.
3. Assembly plant (durable goods).
4. Concrete or Masonry Plant.
5. Chemical Plant.
6. Crematory.
7. Dye Casting Works.
8. Feed Processing Facility.
9. Fertilizer Plant.
10. Manufacturing, outdoor.
11. Metal Smelting/Forging Works.
12. Railroad maintenance terminal, repair/storage yard facilities.
13. Stadium/Concert Hall/Amphitheater (County Board of Education Schools excepted).
14. Rubber/Tire/Retreading Plant.
15. Sugar Refinery.
16. Tannery - Leather Processing.
17. Wood Chipping/Shredding, and Yard Trimmings Composting Facility provided the following conditions are met:
a. Composting materials shall be limited to tree stumps, branches, leaves, and grass clippings or similar putrescent vegetative materials, not including animal products, inorganic materials such as bottles, cans, plastics, metals, or similar materials.
b. Along the entire road frontage (except for approved access crossings), and along the side and rear property lines, provide a three-foot high landscape earthen berm with a maximum slope of three to one and/or a minimum six-foot high, 100 percent opaque, solid wooden fence or masonry wall. The fence/wall or berm must be located outside of any public right-of-way and interior to any landscape strip. The finished side of a fence/wall shall face the exterior property lines.
18. Breweries (10,000 s.f. or greater).
C. Special Exceptions:
Within the M-2 Heavy Manufacturing/Industry District, the following uses may be permitted provided the applicant for such a development is granted a Special Exception subject to the approval of the Mayor and City Council.
1. Caretaker or watchman quarters as an accessory use for the purpose of securing outside storage of equipment and materials that are associated with the primary use of the business.
D. Special Uses:
In addition to the criteria for review listed in Section 1706 for a Special Use Permit, the following criteria shall also be addressed for a Special Use within the M-2 Heavy Manufacturing/Industry District:
1. The proximity of the proposed use to existing residential structures or residentially zoned property;
2. Whether the proposed use will generate pollutants of the air or water and, if so, the method proposed by the applicant for insuring that the proposed use will comply with all state and federal environmental regulations;
3. Whether the proposed use will generate excessive traffic, noise, vibration, smoke, dust, gas fumes, odors, radiation, or create a fire or explosion hazard which may be objectionable due to proximity to surrounding structures, or which will adversely affect the existing use or usability of adjacent or nearby property;
4. How neighboring properties may be affected by the height of any proposed structure; and
5. Whether the use would be consistent with the needs of the neighborhood or the community as a whole, be compatible with surrounding land uses and would not be in conflict with the overall general objectives of the Comprehensive Land Use Plan.
Within M-2 Heavy Manufacturing/Industry District, the following uses may be permitted provided the applicant for such a development is granted a Special Use Permit by the City Council after receiving recommendations from the City Administrator and Planning Commission and after a public hearing:
1. Asphalt Plant.
2. Bulk Storage Tanks including natural gas or fuel storage stations. No above ground storage facilities may be located closer than 500 feet to a Residential District. All storage is to be subject to approval of the Fire Department.
3. Composting Facility.
4. Explosives Plant/Storage.
5. Petroleum Refinery/Processing Plant.
6. Paper/Pulp Mill.
7. Scrap Tire Processing Plant.
8. Solid Waste Transfer Stations.
9. Waste Incineration Facility.
10. Landfills provided the following conditions are met:
a. A minimum 200-foot natural, undisturbed buffer shall be provided between all active waste burial areas and exterior property lines except for approved perpendicular access and utility crossings.
b. A minimum 75-foot natural, undisturbed buffer shall be provided between non-waste disposal operations and exterior property lines except for approved perpendicular access and utility crossings.
c. The limits of any 100-year floodplain or a stream buffer of 200 feet, whichever is greater, shall be preserved as natural, undisturbed area except for approved perpendicular access and utility crossings.
d. The entire site shall be fenced with a minimum six-foot high chain link security fence.
e. The landfill shall be located on or have direct private access to a road designated on the Long Range Road Classification Map as a major collector, minor arterial, major arterial or principal arterial.
f. The applicant shall include with the Special Use Permit application a report detailing the phasing of the landfill and plans for closure and reclamation.
g. The following waste disposal/recycling facilities shall be permitted as accessory uses to landfills meeting the above standards
1. Composting, Municipal Solid Waste.
2. Composting, Yard Trimmings.
3. Gas Recovery/Gas Cogeneration Plant.
4. Recovered Materials Processing Facility.
5. Solid Waste Transfer Stations.
12. A quarry for the removal of minerals and other natural materials, together with necessary buildings, machinery and appurtenances thereto, provided that:
a. Quarry areas being excavated shall be entirely enclosed within a fence located at least ten (10) feet back from the edge of any excavation and of such constructions and height as to be demonstrably able to exclude children and animals from the quarry area.
b. The operators and owners of the quarry present to the Mayor and Council an acceptable comprehensive plan for the reuse of the property at the cessation of the quarry operations.
c. In the case of an existing quarry, an extension of the quarry operations beyond the areas being quarried or approved for quarrying at the effective date of this Zoning Resolution of the City of Dacula, Georgia, shall be permitted and shall not be considered a new operation provided that said extension does not extend to within one thousand (1,000) feet of a residential or commercial Zoning District boundary line.
13. Salvage Operation and Junk Yard providing the following conditions are met:
a. The junkyard is located no closer than three hundred (300) feet to a residential or commercial Zoning District boundary line.
b. The junkyard is completely enclosed with a solid fence not projecting into the rightof-way of any roadway adjoining said junkyard, not less than eight (8) feet high and in no case less than such height as will effectively screen all storage and other operations from view.
c. The junkyard is located no closer than one thousand (1,000) feet from the nearest edge of the right-of-way of any major arterial roadway, within this subpart "major arterial roadway" is defined as any roadway, street or thoroughfare within the City limits of Dacula, Georgia, having a right-of-way of one hundred (100) feet or greater.
14. Distilleries (10,000 s.f. or greater).
15. Data center, provided that the following conditions are met:
a. Minimum Distance from Residential. Any data center building must be located at least 250 feet from the property line of a parcel zoned residential, property with an approved concept plan for residential use, or property developed with residential use.
b. Landscape strip. A planted 50-foot-wide landscape strip shall be provided adjacent to any existing or dedicated right-of-way. Landscape plans must be reviewed and approved by the Planning & Development Director. Natural topography and existing vegetation, supplemented with new evergreen vegetation may be substituted for landscaping at the discretion of the Director.
c. Enclosure.
1. A six (6) foot high opaque fence shall be required along the entire perimeter of the facility.
2. All electric generators and transformers not housed inside a building or structure shall be enclosed behind a solid wall made of concrete or another equivalent sound absorbing material and must be a minimum of four (4) feet higher than the highest point on the generator. The wall shall be painted or finished with decorative or artistic concrete adhesive. Wall design and finish shall be reviewed and approved by the Director.
d. Buffer.
1. Data centers adjoining residential zoned property or property developed with residential use require a 100-foot buffer along the adjoining property line.
2. The first 50 feet along the property line shall remain in an undisturbed, natural state, except for approved fencing, access and utility improvements. The remaining buffer may be disturbed, graded, and replanted. If the buffer is disturbed, a minimum of three (3) rows of varied evergreen shrubs at least 4 feet in height at planting are required to provide screening.
e. Noise abatement.
1. The applicant must submit a noise study demonstrating that the operation of the data center will comply with the following standards:
Maximum Nighttime. Between 10:00 p.m. and 8:00 a.m., the data center shall not generate noise in excess of 55 dB(A) or 10dB(A) above ambient levels (whichever is greater), when measured at the property boundary line shared with a residential use.
Maximum Daytime. Between 8:00 a.m. and 10:00 p.m., the data center shall not generate noise in excess of 65 dB(A) or 10dB(A) above ambient levels (whichever is greater), when measured at the property boundary line shared with a residential use.
Use of backup generators that exceed the maximum sound levels is permitted during emergency power outages. Testing of backup generators is limited to the hours between 9:00 a.m. and 5:00 p.m.
f. Electric Substations. Electric Substations are necessary accessory uses to data centers. If located on the same property as a data center, the substation shall not be located within 300 feet of an adjacent right-of-way and shall be screened from view from adjacent property lines and the right-of-way.
g. Utility. No utility connected data processing center shall be issued a permit until evidence has been provided by the operator that installation of the system would be feasible. Written verification from Gwinnett County Water Resources Department, the electrical provider, and other utility providers as applicable, shall state the following:
1. Adequate capacity is available on the applicable utility lines and substation to ensure available capacity for the proposed use and that capacity is available to serve other needs of the surrounding community is consistent with the normal project load growth envisioned by the data center.
2. Utility supply, equipment and related electrical infrastructure are sufficiently sized and can safely accommodate the proposed use.
3. The use will not cause electrical interference or fluctuations in line voltage on and adjacent to the operating premises.
h. Construction Design Standards.
1. Pitched roofs are prohibited. All roof mounted equipment, such as mechanical units, vent hoods, communication devices, and/or other building system(s) equipment, shall be screened from view on all sides of the building.
2. All building facades shall comply with the Architectural Design Standards within the City’s Development Regulations.
Leer este código donde se publica (city website) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.