3.17.3A. Requirements for approval and final inspection.

Sobre este texto

  • As published by Municode, current through 2026-08-04
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

1. Pond of less than one acre of disturbed area. Construction of the pond shall cease within six months of the approval date. The pond may be subject to a final inspection.

2. For any excavation activity between one acre and ten acres that is approved as a conditional use in AR-1 or AR-2, and requires a state mining permit, or is a GDOT-approved borrow-source or pit for a GDOT-approved project, the bond shall be submitted to DNR, if required. Excavation activities shall cease within three years of DNR or GDOT approval date. Extension of excavation activities beyond three years will require approval by the board of commissioners, after review by the planning board. Business operator shall maintain an annual occupation tax certificate, pursuant to article II, business and occupation tax, for a license to operate a surface mine. Applicant shall submit a survey of the completed excavation site to development services. A final inspection is required. All DNR reclamation requirements shall be met.

3. For any excavation activity greater than one acre that requires a state mining permit and is permitted in PD-MR, or is a GDOT-approved borrow-source or pit for a GDOT-approved project, the bond shall be submitted to DNR, if required. Excavation activities shall cease within five years of DNR or GDOT-approval date. Extension of excavation activities beyond five years shall require approval by the board of commissioners, after review by the planning board. Business operator shall maintain an annual occupation tax certificate, pursuant to article II, business and occupation tax, for a license to operate a surface mine. Applicant shall submit a survey of the completed excavation site to development services. A final inspection is required. All DNR reclamation requirements shall be met.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:effingham-county/zoning/3.17.3a@2026-08-04-bd92002cc0

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Effingham County Zoning Ordinance, 3.17.3A. Requirements for approval and final inspection | Georgia Commons