Sec. 4.6. Group Development Projects.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

The standards and requirements of this ordinance may be modified in the case of a plan and program for group development projects or neighborhood unit or planned unit development which are not divided into customary lots, blocks and streets. This Section specifically contemplates and accommodates the desire of a shopping center developer to subdivide the center into tracts which do not meet zoning requirements for lot size, lot width, lot frontage, building setbacks, lot coverage, and other dimensional requirements customarily related to buildings and lot

line configurations, so that each tenant shall own their own building and/or lot.

Notwithstanding zoning ordinance requirements to the contrary, the Zoning Administrator may approve a development proposal and approve a final plat for a subdivision or leasing plan that does not

meet the requirements for lot size, lot width, lot frontage, building setbacks, lot coverage, and other dimensional requirements customarily related to buildings and lot line configurations, subject to the following:

(a) The Zoning Administrator finds that the proposed group development project provides adequate public spaces and improvements

for the circulation and utility needs of the tract when fully developed or populated.

(b) When considered as a whole, the group development project does not exceed the density (unit per acre) or intensity specifications (floor-area ratio or lot coverage) permitted by the zoning ordinance for the entire tract to be subdivided or divided into leaseholds; provided, further, the group development project must observe external building setbacks that would apply in the absence of

approval of the group development project.

(c) A set of covenants, conditions, and restrictions, or other legal mechanism, has been submitted by the applicant, and reviewed

and approved by the Zoning Administrator and City Attorney, so as to insure conformity to and achievement of the plan.

(d) In cases where a lot is proposed that does not meet minimum access and/or lot frontage requirements of the zoning ordinance, access easements must be shown on the

plat to be recorded and the access easement agreement shall be recorded in the deed records of Hall County, or other arrangement acceptable to the Zoning Administrator and City Attorney.

(e) In cases where buildings do not observe side yard requirements (i.e., zero lot line attached buildings), the Building Inspector shall certify that applicable fire and/or building code requirements for fire walls have been met.

(f) Plans for such developments shall be submitted to and approved by the ZoningAdministrator whether or not such plat is to be recorded, and no building permits shall be

issued until such approval of plans and/or final plat has been given.

The ZoningAdministrator may place conditions on the final plat, plan, and/or conditions, covenants and restrictions in order to ensure the purposes of this ordinance are met.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:flowery-branch/zoning/4.6@2026-11-11-0259fb758f

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Flowery Branch Zoning Ordinance, Sec. 4.6. Group Development Projects | Georgia Commons