Fort Oglethorpe · Ordenanza de zonificación
Appendix A - UNIFIED DEVELOPMENT CODE / Chapter 6 - NATURAL RESOURCE PROTECTION / Article 4 - STORMWATER MANAGEMENT
Sec. 4.15. Post-development stormwater management performance criteria.
Sobre este texto
- As published by Municode, current through 2026-03-26
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Generally. The following performance criteria shall be applicable to all stormwater management plans, unless otherwise provided for in this article.
(b) Water quality. All stormwater runoff generated from a site shall be adequately treated before discharge. It will be presumed that a stormwater management system complies with this requirement if:
(1) It is sized to treat the prescribed water quality treatment volume from the site, as defined in the Georgia Stormwater Management Manual;
(2) Appropriate structural stormwater controls or nonstructural practices are selected, designed, constructed or preserved, and maintained according to the specific criteria in the Georgia Stormwater Management Manual; and
(3) Runoff from hotspot land uses and activities identified by the city are adequately treated and addressed through the use of appropriate structural stormwater controls, nonstructural practices and pollution prevention practices.
(c) Stream channel protection. Protection of stream channels from bank and bed erosion and degradation shall be provided by using all of the following three approaches:
(1) Preservation, restoration and/or reforestation (with native vegetation) of the applicable stream buffer;
(2) Twenty-four-hour extended detention storage of the one-year, 24-hour return frequency storm event;
(3) Erosion prevention measures such as energy dissipation and velocity control.
(d) Overbank flooding protection. Downstream overbank flood and property protection shall be provided by controlling (attenuating) the post-development peak discharge rate to the pre-development rate for the 25-year, 24-hour return frequency storm event.
(e) Extreme flooding protection. Extreme flood and public safety protection shall be provided by controlling and safely conveying the 100-year, 24-hour return frequency storm event such that flooding is not exacerbated.
(f) Structural stormwater controls.
(1) All structural stormwater management facilities shall be selected and designed using the appropriate criteria from the Georgia Stormwater Management Manual.
(2) All structural stormwater controls must be designed appropriately to meet their intended function.
(3) For other structural stormwater controls not included in the Georgia Stormwater Management Manual, or for which pollutant removal rates have not been provided, the effectiveness and pollutant removal of the structural control must be documented through prior studies, literature reviews, or other means and receive approval from the city before being included in the design of a stormwater management system.
(4) If hydrologic or topographic conditions, or land use activities warrant greater control than that provided by the minimum control requirements, the city may impose additional requirements deemed necessary to protect upstream and downstream properties and aquatic resources from damage due to increased volume, frequency, and rate of stormwater runoff or increased nonpoint source pollution loads created on the site in question.
(5) Applicants shall consult the Georgia Stormwater Management Manual for guidance on the factors that determine site design feasibility when selecting and locating a structural stormwater control.
(g) Drainage system guidelines. Stormwater conveyance facilities, which may include but are not limited to culverts, stormwater drainage pipes, catch basins, drop inlets, junction boxes, headwalls, gutter, swales, channels, ditches, and energy dissipaters shall be provided when necessary for the protection of public right-of-way and private properties adjoining project sites and/or public right-of-ways. Stormwater conveyance facilities that are designed to carry runoff from more that one parcel, existing or proposed, shall meet the following requirements:
(1) Methods to calculate stormwater flows shall be in accordance with the stormwater design manual;
(2) All culverts, pipe systems and open channel flow systems shall be sized in accordance with the stormwater management plan using the methods included in the stormwater design manual; and
(3) Design and construction of stormwater conveyance facilities shall be in accordance with the criteria and specifications found in the stormwater design manual.
(h) Dam design guidelines. Any land disturbing activity that involves a site which proposes a dam shall comply with the Georgia Safe Dams Act and Rules for Dam Safety as applicable.
Historia
(Ord. No. 2021-10, § 1, 6-28-2021)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.