Fort Oglethorpe · Ordenanza de zonificación

Appendix A - UNIFIED DEVELOPMENT CODE / Chapter 7 - INFRASTRUCTURE IMPROVEMENTS / Article 4 - STREET CONSTRUCTION STANDARDS

Sec. 4.16. Submittal and procedural requirements.

Sobre este texto

  • As published by Municode, current through 2026-03-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) The developer shall submit a pavement design prepared by a Georgia licensed professional engineer for approval of the director of public works. For subdivisions that will be constructed in stages, the pavement design shall be based on the number of lots from all stages and on a field evaluation of the subgrade soils conducted by a geotechnical engineer.

(b) The geotechnical engineer shall complete a field evaluation of the roadway before any roadway construction begins.

(1) The geotechnical engineer shall conduct a field exploration of the soils along the roadway alignment at a spacing of no greater than 500 feet and obtain samples of the subgrade soils for laboratory evaluation.

(2) A composite soil sample of each soil type shall be obtained and tested for plasticity (Atterberg limits, ASTM D4318) and standard proctor moisture-density relationship

(ASTM D698).

(3) California Bearing Ratio (ASTM D1883) tests shall be conducted on a composite sample representative of the soil conditions, as determined by the geotechnical engineer.

(4) The California Bearing Ratio (CBR) test shall be conducted on soaked samples.

(5) CBRs less than six require base, and pavement thickness to be determined by geotechnical engineer evaluation.

(c) A final report by the geotechnical engineer that the quality assurance tests and inspections have been performed and the construction has been completed in substantial compliance with the city design and construction standards, specifications, and applicable portions of this code's regulations will be required before the plat is recorded.

(1) The final report shall be compiled in accordance with all applicable ASTM standards for geotechnical reporting.

(2) One copy of the final report shall be given to the city.

(d) Preliminary or final plat approval does not constitute permission to begin any street or utility construction.

(1) Street and utility construction plans may be approved as a whole or in part.

(2) Construction of approved portions of the work shall not precede issuance of applicable land disturbing activity permits.

(e) Public streets to be accepted by the city will be at the discretion of the city council.

Acceptance will be considered only upon separate written request by the developer, subdivider, or any person or persons who own all fee simple interest in the subject street.

(f) See chapter 8 for final plat approval requirements.

(g) See chapter 8 for requirements pertaining to official acceptance of improvements.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2021-10, § 1, 6-28-2021)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:fort-oglethorpe/zoning/appendix-a-chapter-7-article-4-4.16@2026-03-26-d6de476fe4

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Fort Oglethorpe Zoning Ordinance, Sec. 4.16 (Appendix A, Chapter 7, Article 4). Submittal and procedural requirements | Georgia Commons