Sec. 8.2. Development permit.

Sobre este texto

  • As published by Municode, current through 2026-03-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Development activities authorized. A development permit must first be issued to authorize all activities associated with the land development process, including grading; for the construction of such improvements as streets, surface parking areas and drives, sewer systems, stormwater drainage facilities, sidewalks, etc.; or for the construction of multifamily or nonresidential buildings and related structures and improvements in a multifamily or nonresidential project.

(b) Development permit approval. A development permit (which may include grading, clearing, and grubbing) shall be issued at the developer's request and based on an approved preliminary subdivision plat for a single-family or two-family residential subdivision or a site plan for a multi-family or nonresidential project, along with approval of all other development plans and documents required to be submitted under this chapter. All plans approved for a development permit shall expire after six months if no permit is issued within said time period.

(c) Expiration of development permits. A development permit shall expire 12 consecutive calendar months after issuance unless development activity as authorized by the permit are commenced within said 12-month period or if such authorized activities lapse and the project is abandoned for a period exceeding 60 consecutive calendar days. The director of building, planning and zoning may approve one extension not exceeding three consecutive calendar months within which time development activity must commence or the permit shall expire.

Said extension shall be applied for within the first 12 consecutive calendar months after the permit's issuance.

(d) Lapse in construction activity. For the purposes of this development code, a lapse in or suspension of development activity as authorized by a development permit, as a direct result of action or inaction on the part of the City of Fort Oglethorpe completely beyond the control of the developer, shall not be considered as a lapse in activity causing the development permit to expire. The 12 months within which development activity must begin shall exclude any such time period during which the activity is prohibited or has been caused to lapse by said city action or inaction.

(e) Expiration of approved development plans.

(1) If construction activity has not commenced within the permit period and the development permit expires, the director of building, planning and zoning shall require new site plans to be submitted for the project. The new plans must comply with any changes or amendments to these regulations or other ordinances as adopted by the city.

(2) Where development plans have been approved by the director of building, planning and zoning, and no development permit has been issued, new plans shall be submitted after 12 months if a development permit has not been issued and construction has not commenced on the project.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2021-10, § 1, 6-28-2021)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:fort-oglethorpe/zoning/appendix-a-chapter-8-article-8-8.2@2026-03-26-7f10a59a31

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Fort Oglethorpe Zoning Ordinance, Sec. 8.2 (Appendix A, Chapter 8, Article 8). Development permit | Georgia Commons