10.03.01. Building and Fire Inspection Permits
Sobre este texto
- As published by Municode, current through 2024-03-19
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
A. Permit application
1. Unless specifically exempted, any owner, authorized agent or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical, plumbing, or fire protection system, the installation of which is regulated by the technical codes, or to cause any such work to be done, shall first make application to the Department of Building, Planning and Development and obtain the required permit, including fire inspection permit, for the work.
2. The following situations do not require a building permit:
a. Accessory buildings which are 120 square feet or less and do not require a branch circuit panel board and/or a utility service. Accessory buildings which do not require a building permit are still required to meet all setback requirements established in this ULDC.
b. The following mechanical work:
i. Any portable heating appliance;
ii. Any portable ventilation equipment;
iii. Any portable cooling unit;
iv. Any steam, hot or chilled water piping within any heating or cooling equipment regulated by this article;
v. Replacement of any part which does not alter its approval or make it unsafe;
vi. Any portable evaporative cooler;
vii. Any self-contained refrigeration system containing ten (10) pounds (4.54 kg) or less of refrigerant and actuated by motors of one (1) horsepower (746
W) or less.
c. Electrical work on any 120 volt branch circuit work involving two (2) circuits or less, provided that this work is done in an existing structure which otherwise would not require an additional building permit.
3. Work authorized
a. A building, electrical, gas, mechanical or plumbing permit shall carry with it the right to construct or install the work, provided the same are shown on the drawings and set forth in the specifications filed with the application for the permit.
b. Where these are not shown on the drawings and covered by the specifications submitted with the application, separate permits shall be required.
4. Minor repairs. Ordinary minor repairs may be made with the approval of the Building Inspector without a permit, provided that such repairs shall not violate any of the provisions of the technical codes.
5. Information required. Each application for a permit, with the required fee, shall be filed with the Department of Building, Planning and Development on a form furnished for that purpose and shall contain the information required in Section
10.02.01 and shall include a general description of the proposed work and its location. The application shall be signed by the owner, or his authorized agent, and shall be accompanied by the following:
a. The actual dimensions of the lot to be built upon;
b. The size of the building to be erected;
c. The location of the building on the lot;
d. The location of existing structures on the lot, if any;
e. The number of dwelling units the building is designed to accommodate;
f. The layout of off-street parking and loading spaces;
g. Such other information as may be essential for determining whether the provisions of this article are being observed; and
h. Such other information as may be requested by the Building Inspector and/or Fire Inspector or required by any other County ordinance(s).
6. Time limitations
a. An application for a permit for any proposed work shall be deemed to have been abandoned six (6) months after the date of filing for the permit, unless before then a permit has been issued. One (1) or more extensions of time for periods of not more than ninety (90) days each may be allowed by the Building Inspector for the application provided the extension is requested in writing and justifiable cause is demonstrated.
b. Any building permit or other permit issued pursuant to this article shall become invalid unless the work authorized by it shall have been commenced within six (6) months of the date of issue or if the work authorized by the permit is suspended or abandoned for a period of one (1) year.
B. Drawings and specifications
1. Requirements
a. One (1) copy of specifications, and of drawings drawn to scale with sufficient clarity and detail to indicate the nature and character of the work, shall accompany the application for a permit.
b. Such drawings and specifications shall contain information, in the form of notes or otherwise, as to the quality of materials, where quality is essential to conformity with the technical codes.
c. Such information shall be specific, and the technical codes shall not be cited as a whole or in part, nor shall the term "legal" or its equivalent be used, as a substitute for specific information.
d. All information, drawings, specifications and accompanying data shall bear the name and signature of the person responsible for the design.
e. Exception. No drawings or specifications shall be required for:
i. Accessory buildings, except engineered metal buildings shall require design data from the manufacturer which indicates meeting load requirements of the Standard Building Code.
ii. Agricultural buildings, except engineered metal buildings shall require design data from the manufacturer which indicates meeting load requirements of the Standard Building Code.
2. Additional data
a. The Building Inspector may require details, computations, stress diagrams, and other data necessary to describe the construction or installation and the basis of calculations.
b. All drawings, specifications and accompanying data required by the Building Inspector to be prepared by an architect or engineer shall be affixed with their official seal.
3. Design professional. The design professional shall be an architect or engineer legally registered under the laws of the state regulating the practice of architecture or engineering and shall affix his official seal to said drawings, specifications and accompanying data, for the following:
a. All Group A (Assembly), Group E (Educational), and Group I (Institutional) occupancies.
b. Buildings and structures three (3) stories or more high.
c. Buildings and structures five thousand (5,000) square feet or more in area.
d. For all other buildings and structures, the submittal shall bear the certification of the applicant that some specific state law exception permits its preparation by a person not so registered.
e. Exception: Single-family dwellings, regardless of size, shall require neither a registered architect or engineer, nor a certification that an architect or engineer is not required.
4. Structural and fire resistance integrity. Plans for all buildings shall indicate how required structural and fire resistance integrity will be maintained where a penetration of a required fire resistance wall, floor or partition will be made for electrical, gas, mechanical, plumbing, signal and communication conduits, pipes and systems and also indicate in sufficient detail how the fire integrity will be maintained where required fire resistant floors intersect the exterior walls.
5. Site drawings
a. Drawings shall show the location of the proposed building or structure and of every existing building or structure on the site or lot.
b. The Building Inspector may require a boundary line survey prepared by a qualified surveyor.
6. Hazardous occupancies. The Building Inspector or Fire Inspector may require the following:
a. General site plan
i. A general site plan drawn at a legible scale which shall include, but not be limited to, the location of all buildings, exterior storage facilities, permanent accessways, evacuation routes, parking lots, internal roads, chemical loading areas, equipment cleaning areas, storm and sanitary sewer accesses, emergency equipment and adjacent property uses.
ii. The exterior storage areas shall be identified with the hazard classes and the maximum quantities per hazard class of hazardous materials stored.
b. Building floor plan
i. A building floor plan drawn to a legible scale which shall include, but not be limited to, all hazardous materials storage facilities within the building and shall indicate rooms, doorways, corridors, exits, fire rated assemblies with their hourly rating, location of liquid-tight rooms, and evacuation routes.
ii. Each hazardous materials storage facility shall be identified on the plan with the hazard classes and quantity range per hazard class or the hazardous material stored.
C. Examination of documents
1. Plan review. The Building Inspector and Fire Inspector shall examine or cause to be examined each application for a permit and the accompanying documents, consisting of drawings, specifications, computations and additional data, and shall ascertain by such examinations whether the construction indicated and described is in accordance with the requirements of the technical codes and all other pertinent laws or ordinances.
2. Affidavits
a. The Building Inspector and Fire Inspector may accept a sworn affidavit from a registered architect or engineer stating that the plans submitted conform to the technical codes.
b. For buildings and structures, the affidavit shall state that the plans conform to the laws as to egress, type of construction and general arrangement and if accompanied by drawings showing the structural design, and by a statement that the plans and design conform to the requirements of the technical codes as to strength, stresses, strains, loads and stability.
c. The Building Inspector may, without any examination or inspection, accept such affidavit, provided the architect or engineer who made such affidavit agrees to submit to the Building Inspector copies of inspection reports as inspections are performed and, upon completion of the structure, electrical, gas, mechanical or plumbing systems, a certification that the structure, electrical, gas, mechanical or plumbing system has been erected in accordance with the requirements of the technical codes.
d. Where the Building Inspector relies upon such affidavit, the architect or engineer shall assume full responsibility for the compliance with all provisions of the technical codes and other pertinent laws or ordinances.
D. Issuing permits
1. Action on permits
a. The Building Inspector or Fire Inspector shall act upon an application for a permit without unreasonable or unnecessary delay.
b. If the Building Inspector and Fire Inspector are satisfied that the work described in an application for a permit and the contract documents filed therewith conform to the requirements of the technical codes or other pertinent laws or ordinances, the Building Inspector and Fire Inspector shall issue the appropriate permit to the applicant.
2. Refusal to issue permit
a. If the application for a permit and the accompanying contract documents describing the work do not conform to the requirements of the technical codes or other pertinent laws or ordinances, the Building Inspector and Fire Inspector shall not issue a permit, but shall return the contract documents to the applicant with his refusal to issue such permit.
b. Such refusal shall, when requested, be in writing and shall contain the reason for refusal.
E. Contractors' responsibilities
1. It shall be the duty of every contractor who shall make contracts for the installation or repairs of building, structure, electrical, gas, mechanical, sprinkler or plumbing systems, for which a permit is required, to comply with state or local rules and regulations concerning licensing which the applicable governing authority may have adopted.
2. In such case that the state requires a contractor to have obtained a state license before they are permitted to perform work, the contractor shall supply the local government with their license number before receiving a permit for work to be performed.
F. Conditions of the permit
1. Permit intent
a. A permit issued shall be construed to be a license to proceed with the work and not as authority to violate, cancel, alter, or set aside any of the provisions of the technical codes, nor shall issuance of a permit prevent the Building Inspector from thereafter requiring a correction of errors in plans, construction, or violations of this article.
b. Every permit issued shall become invalid unless the work authorized by such permit is commenced within six (6) months after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of six (6) months after the time the work is commenced.
c. One (1) or more extensions of time, for periods of not more than ninety (90) days each, may be allowed for the permit.
d. The extension shall be requested in writing and justifiable cause demonstrated.
e. Permission for extensions shall be in writing by the Building Inspector.
2. Permit issued on basis of an affidavit
a. Whenever a permit is issued in reliance upon an affidavit or whenever the work to be covered by a permit involves installation under conditions which, in the opinion of the Building Inspector or Fire Inspector, are hazardous or complex, the Building Inspector or Fire Inspector shall require that computations be submitted by the architect or engineer who shall supervise such work.
b. In addition, they shall be responsible for conformity with the permit, provide copies of inspection reports as inspections are performed, and upon completion make and file with the Building Inspector a written affidavit that the work has been done in conformity with the reviewed plans and with the structural provisions of the technical codes.
c. In the event such architect or engineer is not available, the owner shall employ in his stead a competent person or agency whose qualifications are reviewed by the Building Inspector or Fire Inspector.
3. Plans
a. When the Building Inspector issues a permit, he shall endorse, in writing or by stamp, the set of plans "Reviewed for Code Compliance."
b. The set of drawings so reviewed shall be returned to the applicant.
c. The permitted drawings shall be kept at the site of work during normal business hours and shall be open to inspection by the Building Inspector or his authorized representative.
G. Fees
1. Prescribed fees.
a. A permit shall not be issued until the necessary fees for such permit have been paid.
b. Nor shall an amendment to a permit be released until the additional fee, if any, due to an increase in the size of the building, structure, electrical, plumbing, mechanical or gas systems, etc., has been paid.
c. All fees shall be as established from time to time by the Board of Commissioners and shall be posted in the Department of Building, Planning and Development.
2. Work commencing before permit issuance
a. Any person who commences any work on a building, structure, electrical, gas, mechanical or plumbing systems, etc., before obtaining the necessary permits shall be subject to a penalty of one hundred (100) percent of the usual permit fee in addition to the required permit fees.
3. Accounting. The Department of Building, Planning and Development shall keep a permanent and accurate accounting of all permit fees and other monies collected, the names of all persons upon whose account the same was paid, along with the date and amount thereof.
4. Schedule of permit fees. On all buildings, structures, electrical, plumbing, mechanical and gas systems or alterations requiring a permit, a fee for each permit shall be paid as required at the time of filing of the application, in accordance with the fees as established by the Board of Commissioners.
5. Building permit valuations
a. If, in the opinion of the Building Inspector, the valuation of building, alteration, structure, electrical, gas, mechanical or plumbing systems appears to be underestimated on the application, the permit shall be denied, unless the applicant can show detailed estimates to meet the approval of the Building Inspector.
b. Permit valuations shall include total cost, such as electrical, gas, mechanical, plumbing equipment and other systems, including materials and labor.
H. Inspections
1. Existing building inspections. Before issuing a permit, the Building Inspector:
a. May examine or cause to be examined any building, electrical, gas, mechanical or plumbing systems for which an application has been received for a permit to enlarge, alter, repair, move, demolish, install, or change the occupancy.
b. Shall inspect all buildings, structure, electrical, gas, mechanical and plumbing systems, from time to time, during and upon completion of the work for which a permit was issued.
c. Shall make a record of every such examination and inspection and of all violations of the technical codes.
2. Manufacturers and fabricators
a. When deemed necessary by the Building Inspector, he shall make, or cause to be made, an inspection of materials or assemblies at the point of manufacture or fabrication.
b. A record shall be made of every such examination and inspection and of all violations of the technical codes.
3. Inspections prior to issuance of certificate of occupancy or completion. The Building Inspector shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building, structure, electrical, gas, mechanical or plumbing system upon completion, prior to the issuance of the certificate of occupancy or completion.
4. Posting of permit
a. Work requiring a permit shall not commence until the permit holder or his agent posts the permit card in a conspicuous place on the premises.
b. The permit shall be protected from the weather and located in such position as to permit the Building Inspector or his representative to conveniently make the required entries thereon.
c. This permit card shall be maintained in such position by the permit holder until the certificate of occupancy or completion is issued by the Building Inspector.
5. Required inspections. The Building Inspector, upon notification from the permit holder or his agent, shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with the technical code:
a. Building
i. Foundation inspection: To be made after trenches are excavated and forms erected.
ii. Frame inspection: To be made after the roof, all framing, fire blocking and bracing are in place, all concealed wiring, all pipes, chimneys, ducts and vents are complete.
iii. Final inspection: To be made after the building is completed and ready for occupancy.
b. Electrical
i. Underground inspection: To be made after trenches or ditches are excavated, conduit or cable installed, and before any backfill is put in place.
ii. Rough-in inspection: To be made after the roof, framing, fire blocking and bracing is in place and prior to the installation of wall or ceiling membranes.
iii. Final inspection: To be made after the building is complete, all required electrical fixtures are in place and properly connected or protected, and the structure is ready for occupancy.
c. Plumbing
i. Underground inspection: To be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place.
ii. Rough-in inspection: To be made after the roof, framing, fire blocking and bracing are in place and all soil, waste and vent piping is complete, and prior to the installation of wall or ceiling membranes. This inspection shall include a pressure test which shall be performed by the contractor.
iii. Final inspection: To be made after the building is complete, all plumbing fixtures are in place and properly connected, and the structure is ready for occupancy.
iv. Note: See section 417 of the Standard Plumbing Code for required tests.
d. Mechanical
i. Underground inspection: To be made after trenches or ditches are excavated, underground duct and fuel piping installed, and before any backfill is put in place.
ii. Rough-in inspection: To be made after the roof, framing, fire blocking and bracing are in place and all ducting and other concealed components are complete, and prior to the installation of wall or ceiling membranes.
iii. Final inspection: To be made after the building is complete, the mechanical system is in place and properly connected, and the structure is ready for occupancy.
e. Gas
i. Rough piping inspection: To be made after all new piping authorized by the permit has been installed, and before any such piping has been covered or concealed or any fixtures or gas appliances have been connected.
ii. Final piping inspection: To be made after all piping authorized by the permit has been installed and after all portions which are to be concealed by plastering or otherwise have been so concealed, and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test which shall be performed by the contractor.
iii. Final inspection: To be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes, to insure compliance with all the requirements of this article and to assure that the installation and construction of the gas system is in accordance with reviewed plans.
6. Written release
a. Work shall not be done on any part of a building, structure, electrical, gas, mechanical or plumbing system beyond the point indicated in each successive inspection without first obtaining a written release from the Building Inspector.
b. Such written release shall be given only after an inspection has been made of each successive step in the construction or installation as indicated by each of the foregoing three (3) inspections.
7. Reinforcing steel, structural frames, insulation, plumbing, mechanical, or electrical systems work of any part of any building or structure shall not be covered or concealed without first obtaining a release from the Building Inspector.
8. Plaster fire protection
a. In all buildings where plaster is used for fire protection purposes, the permit holder or his agent shall notify the Building Inspector after all lathing and backing is in place.
b. Plaster shall not be applied until the release from the Building Inspector has been received.
I. Certificate of occupancy
1. Building occupancy
a. A new building shall not be occupied or a change made in the occupancy, nature, or use of a building or part of a building until after the Building Inspector has issued a certificate of occupancy.
b. Said certificate shall not be issued until all required electrical, gas, mechanical, plumbing, and fire protection systems have been inspected for compliance with the technical codes and other applicable laws and ordinances and released by the Building Inspector.
c. Issuing certificate of occupancy. Upon satisfactory completion of construction of a building or structure and installation of electrical, gas, mechanical and plumbing systems in accordance with all technical codes, reviewed plans and specifications, and after the final inspection, the Building Inspector shall issue a certificate of occupancy stating the nature of the occupancy permitted, the number of persons for each floor when limited by law, and the allowable load per square foot for each floor in accordance with the provisions of the technical codes.
d. Temporary/partial occupancy. A temporary/partial certificate of occupancy may be issued for a portion of a building which may safely be occupied prior to final completion of the building.
e. Existing building certificate of occupancy.
i. A certificate of occupancy for any existing building may be obtained by applying to the Building Inspector and supplying the information and data necessary to determine compliance with the technical codes for the occupancy intended.
ii. Where necessary, in the opinion of the Building Inspector, two (2) sets of detailed drawings, or a general inspection, or both, may be required.
iii. When, upon examination and inspection, it is found that the building conforms to the provisions of the technical codes and other applicable laws and ordinances for such occupancy, a certificate of occupancy shall be issued.
2. Certificate of completion.
a. Upon satisfactory completion of a building, structure, electrical, gas, mechanical or plumbing system, a certificate of completion may be issued.
b. This certificate is proof that a structure or system is complete, is released for use and may be connected to a utility system.
c. This certificate does not grant authority to occupy or connect a building, such as a shell building, prior to the issuance of a certificate of occupancy.
3. Service utilities.
a. Connection of service utilities. No person shall make connections from a utility, source of energy, fuel or power to any building or system which is regulated by the technical codes for which a permit is required, until released by the Building Inspector and a certificate of occupancy or completion is issued.
b. Temporary connection. The Building Inspector may authorize the temporary connection of the building or system to the utility source of energy, fuel or power for the purpose of testing building service systems or for use under a temporary certificate of occupancy.
c. Authority to disconnect service utilities.
i. The Building Inspector shall have the authority to authorize disconnection of utility service to the building, structure or system regulated by the technical codes, in case of emergency where necessary to eliminate an immediate hazard to life or property.
ii. The Building Inspector shall notify the serving utility and, whenever possible, the owner and occupant of the building, structure or service system of the decision to disconnect prior to taking such action.
iii. If not notified prior to disconnecting, the owner or occupant of the building, structure or service system shall be notified in writing as soon as practical thereafter.
J. Posting floor loads
1. Occupancy
a. An existing or new commercial building shall not be occupied for any purpose which will cause the floors thereof to be loaded beyond their safe capacity.
b. The Building Inspector may permit occupancy of a building for mercantile, commercial or industrial purposes, by a specific business, when he is satisfied that such capacity will not thereby be exceeded.
2. Storage and factory-industrial occupancies
a. It shall be the responsibility of the owner, agent, proprietor or occupant of Group S and Group F occupancies, or any occupancy where excessive floor loading is likely to occur, to employ a competent architect or engineer in computing the safe load capacity.
b. All such computations shall be accompanied by an affidavit from the architect or engineer stating the safe allowable floor load on each floor in pounds per square foot uniformly distributed.
c. The computations and affidavit shall be filed as a permanent record of the Department of Building, Planning and Development.
3. Signs required.
a. In every building or part of a building used for storage, industrial or hazardous purposes, the safe floor loads, as reviewed by the Building Inspector on the plan, shall be marked on plates of approved design which shall be supplied and securely affixed by the owner of the building in a conspicuous place in each story to which they relate.
b. Such plates shall not be removed or defaced and, if lost, removed or defaced, shall be replaced by the owner of the building.
Historia
(Res. of 12-20-11)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.