10.03.09. Procedures for Subdivision Construction Plan
Sobre este texto
- As published by Municode, current through 2024-03-19
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
A. Following the review of the sketch plat, the developer shall submit to the Planning Department five (5) sets of copies of the subdivision construction plans, or six (6) sets if on-site wastewater disposal is proposed. The Planning Department shall distribute the plans to the reviewing entities as follows (if applicable):
1. Building, Planning and Development Department.
2. Engineering Consultants (if applicable).
3. Water and Sewer Utility Provider.
4. Gordon County Soil Conservation Service.
5. Gordon County Board of Health (if applicable).
6. Gordon County Public Works Department.
7. Gordon County Fire Department.
8. Any other department as deemed necessary by the Planning Department.
B. The construction plans shall be prepared and certified by an appropriate state approved professional, and shall include such information as will allow each reviewing entity to assess the proposed development for conformance to the applicable Gordon County regulations and standards. Specific information required to be included with the construction plans is listed in Section 10.02.01.
C. Each reviewing entity shall review the construction plans and indicate their written approval or disapproval, providing the reasons for such disapproval. All copies will then be returned to the Planning Department, who will notify the developer of the results. If a reviewing entity takes no action within fifteen (15) consecutive calendar days from the date of submittal of the construction plans, the plans shall be considered approved and certification of approval issued on demand.
D. The developer shall then revise the construction plans based on the comments of the individual reviewing entities, and resubmit the plans only to those reviewing entities which did not grant approval. This process shall continue until all reviewing entities approve the construction plans.
E. After approval is granted by all reviewing entities, the developer shall prepare seven
(7) sets of the revised construction plans (eight (8) if on-site wastewater disposal is proposed) and return these to the Planning Department. The Planning Department shall have each set stamped or signed by each of the reviewing entities and shall affix the Gordon County approval stamp on each set. The Planning Department shall then distribute a set of approved plans to each reviewing entity, and one (1) set to the developer for construction.
F. Revisions to the approved construction plans may be accomplished by the developer coordinating directly with the applicable reviewing entity. Approved revisions will be sent to the Planning Department and the developer to be attached to the approved plans. Minor revisions to the final construction plans may be made by the individual reviewing entities in indelible red ink and initialed on all sets of plans.
G. The land disturbance permit will be issued only after construction plans have been approved. The Planning Department shall be notified by the developer before actual construction begins, and at such stages in the construction process as stipulated in these regulations. A clearing and grubbing permit may be issued before tile construction plans are approved it a detailed soil erosion control plan prepared by an appropriate state approved professional is submitted. Such plan shall include analysis of storm water runoff and hydrology, and shall be approved by the Planning Department. The clearing and grubbing permit shall not authorize any grading work to be done. All requirements of the Land Disturbing Permit shall be in place prior to any building permit being issued for the development.
H. Further, prior to beginning any work on a new development advance warning signs with speed reduction advisory plats shall be placed on connecting thoroughfares at one thousand (1,000) feet and five hundred (500) feet points on either side of the intersection. The signing shall be reviewed and approved by the Road Department prior to commencing work. This signing detail shall be shown on the construction plans.
I. See Section 6.01.05 concerning DOT permits and approvals on state routes.
Historia
(Res. of 12-20-11)