1101.05. Multi-family and commercial/
Sobre este texto
- As published by Municode, current through 2023-12-05
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
industrial projects.
(a) Project approval is granted upon review and approval of a Preliminary Site Plan for the project by the Planning Commission.
(b) A Land Disturbance Permit, when required, is issued by the Community Development Department based on review and approval by all affected departments and agencies of development plans
for construction of the project.
(c) A Building Permit is issued by the Community Development Department based on review and approval of architectural plans. Buildings
falling under the authority of the State Fire Marshal shall be approved by the State Fire Marshal prior to issuance of the building permit.
(d) Driveway and sign permits are issued by the appropriate departments.
(e) Receipt by the Public Works Director (for streets and drainage) and the Water Department Director (for water and sewer) of accurate surveys of the as-built condition of all public improvements is required in order to authorize issuance of a Certificate of Occupancy.
(f) Occupancy of the building is authorized by the Community Development Director or designee based on final inspection and issuance of a Certificate of Occupancy.
Historia
(Ord. No. 05-23, 12-5-2023)