Helen · Ordenanza de zonificación
Part II - CODE / Chapter 34 - LAND DEVELOPMENT CODE / Article IV - LAND DEVELOPMENT ORDINANCE / Division 2 - ADMINISTRATION AND ENFORCEMENT
Sec. 34-527. Building permit.
Sobre este texto
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Required. No building or other structure shall be erected, moved, extended, enlarged, repaired, painted, or structurally altered, nor shall any excavation or filling of any lot for the construction of any building be commenced until the city manager or designee has issued a building permit for such work. Permits shall be issued and fees charged according to the provisions of the city safety codes. If such permit involves the erection, extension, or enlargement of any building or structure in a commercial zoning district, a survey prepared by a Georgia registered land surveyor or engineer showing the proposed location of the improvements shall be submitted as part of the application process. Upon completion of the project, as built surveys prepared by a Georgia registered land surveyor or engineer shall be a pre-requisite on all completed building projects located within any commercial district before the issuance of a certificate of occupancy under section 34-538, in addition to all other requirements of that section.
(b) Application. Application to the city manager or designee for a building permit shall be in accordance with the provision of the city building codes and shall be accompanied by site plans in five copies (per the provisions of section 34-576). Any building permit issued shall become invalid 12 months after date of issue subject to renewal upon application to the city manager.
(c) Performance bond. In addition to the other requirements of this section, all applications for a permit for a building project in the C-1 or C-2 zoning districts, as described in sections 34-183 and 34-184 of this code, must be accompanied by a performance bond equal to 125 percent of the cost of the project. The performance bond may be submitted in a form acceptable to the city manager or designee with a surety company licensed to do business in the state, to enable the city to complete the project on public and/or private property in the event the contractor or the contractor's insurance company fails to pay for the project's completion. No building permit shall be issued for the C-1 or C-2 zoning districts until such a performance bond has been received.
(d) Appeal from denial. If a building permit is denied, the applicant may appeal such denial as such process is provided for in the applicable safety code. If such safety code does not contain an appeal process, the appeal shall go to the board of appeals as provided for in this chapter.
Historia
(Code 1987, §§ 14-502—14-504; Ord. No. 10-04-01, 4-20-10; Ord. No. 24-10-02, 11-19-24)