Section 8.10. Duration of Approval. [added via Ord.

Sobre este texto

  • As posted on the city's website, retrieved 2026-11-14

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

TA 2024-04, adopted 11-19-24]

(a) Findings, purposes and intentions.

1. It is in the public interest to ensure that development projects receiving variance, conditional use, and/or rezoning approvals through public hearing processes are completed as represented and approved. Inaction or the lack of progress over time with respect to a given land development that has gone through a public hearing process can cast doubt on the integrity of the public hearing process and the development project proposed and approved. It is also in the public interest to mitigate land speculation at the expense of the general public.

2. A project that does not commence, or for which substantial progress has not been accomplished according to a schedule proposed by the applicant and approved by the City Council, can have adverse impacts on the city and county providing services, since local governments are required to plan for, finance, and construct public improvements in support of developments as represented and approved. The expenditure of funds for capital improvements supporting development projects are still required to be made by local governments, whether or not said projects have commenced or made substantial progress toward completion. For instance, any loans secured by a local government for capital improvements supporting the development must be paid, whether or not a given development project has paid development, utility connection, building, and development impact fees.

3. It is recognized that developers need flexibility to meet consumer demand and adjust to market forces, because they face a host of challenges to commence and make substantial progress toward completion of development projects including a variety of extenuating circumstances. Owners should be afforded the opportunity to request and receive adjustments to approved project schedules and to request additional time to commence or make substantial progress toward completion of projects, as conditions warrant.

(b) Definitions.

Commencement: Commencement shall include but shall not necessarily be limited to the following: Submission to the city of a complete application for land disturbance permit, development permit, or building permit; submission of completed application for an encroachment permit to the Georgia Department of Transportation; and/or submission of any other complete application for regulatory approval by a state or federal agency.

Substantial progress: Substantial progress shall include but shall not necessarily be limited to the following: acquisition of off-site easements required for the project;

installation in whole or in part of utilities or improvements on the site; payment in whole or in part of required water and sewer connection fees, and dedication of right of way required as a condition of approval or as may be required by the Georgia Department of Transportation for access to a state route.

(c) Applicability. This section shall apply to applications for official zoning map amendment (rezoning), conditional use permits, and variances.

(d) Imposition of a project schedule. On or after November 19, 2024, the City Council may grant a variance, approve a conditional use permit, or rezone property conditioned upon the completion of a project schedule by the applicant. A project schedule may include a commencement date, a substantial progress date, and/or an anticipated completion date.

(e) Criteria supporting imposition of a project schedule. In deciding whether to impose a project schedule, based on Section 8.10(a), the City Council may consider any applicable criteria, including but not limited to the following:

1. The application relates to one of the following zoning districts: Planned Unit Development (PUD), Mixed Use (MU), Multiple Family Residential (MFR), Commercial Motor Vehicle Service and Repair District (C-3), or Light Industrial District (M-1); and/or

2. The zoning administrator has recommended in writing that a project schedule be imposed, and the reasons for imposing a project schedule; and/or

3. The owner or applicant owns one or more parcels of land in the city for which a rezoning, conditional use, or variance application was approved by the city, and eighteen or more months have elapsed since such approval was granted and development in accordance with the approved application has not commenced;

and/or

4. The owner or applicant does not propose to occupy the development if approved and constructed, and the owner or applicant has not identified the name or names of a specific end-user(s), tenant(s), or occupaat(s) for the proposed development; and/or

5. The proposed development, if approved and constructed, will require the city to expand, extend or improve one or more public facilities and services (e.g., police, roads, water, sewer, etc.) beyond a level that exists or is programmed to occur at the time the application is approved.

(f) Requirements if a project schedule is imposed. If a project schedule containing commencement, substantial progress, or anticipated completion dates is made a part of the condition of approval of a variance, conditional use permit, or rezoning, the project proposed in the application shall:

1. Commence or receive a certificate of occupancy or certificate of completion within eighteen months from the date of approval of City Council; otherwise the approval shall be subject to the procedure for lapse of an approved project schedule established in this section; provided, however, an owner may request and the City Council may grant an extension of time, in accordance with this section.

2. Following commencement, achieve substantial progress within thirty months from the date of approval of city council; otherwise the approval shall be subiect to the procedure for lapse of an approved project schedule established in this section; provided, however, an owner may request and the City Council may grant an extension of time in accordance with this procedures in this section.

(g) Process for extensions. An owner may request an extension to an approved project schedule to commence or make substantial progress toward a development project, in accordance with this subsection.

1. Applications for an extension to a project schedule shall be made in writing to the zoning administrator; a fee may be charged if a fee for a project schedule extension is included in a fee schedule adopted by resolution of the City Council.

2. The application shall include the reasons for the extension request, the amount of time requested for the extension, and a proposed (revised) project completion schedule.

3. An extension of a project schedule shall not be deemed to require a formal amendment to the conditions of approval and the grant of a project schedule extension by City Council shall not be required to adhere to zoning procedures for public hearings.

(h) Standards for extensions. One or more of the following standards may be cause for applying for and granting an extension to a project schedule. The applicant may request, the zoning administrator may recommend, and the City Council may approve. an extension to a project schedule if the applicant can demonstrate that one or more of the following standards exist:

1. The owner has a significant monetary investment in the project to date, extending beyond the preparation of civil engineering plans and purchase of the real estate;

and/or

2. The owner has demonstrated he or she has proceeded with due diligence and in good faith to complete the project and has made reasonable if not substantial progress to date on the development and completion of the project; and/or

3. One or more extenuating circumstances exist, including but not limited to documented delays beyond the control of the owner, caused by: delay in approval from a regulating agency, complications in real estate transactions, unforeseen physical property conditions, adverse health of a responsible individual, adverse weather conditions, delays in the scheduling of utility relocations, challenges in securing project financing, severe macro- or micro-economic conditions, and local, state or national emergencies.

(i) Effect of extension. City Council approval of an application for project schedule extension shall supersede the previously approved project schedule without the need to amend conditions of approval imposed on the project approved.

(j) Lapse of project schedule. If a project schedule, made a condition of approval by the City Council (on or after November 19, 2024) as a part of its approval of a rezoning, conditional use permit, and/or variance has not been met, and if a complete application for extension of the approved project schedule has not been made, the following procedures shall be required:

1. The zoning administrator shall send a written notice by Certified United States Mail, Return Receipt Requested, to the owner as stated in the original application for variance, conditional use or rezoning, as well as to the current owner of record according to the tax records of the Jackson County Tax Assessor associated with development project, if different, that the project schedule has lapsed.

2. The zoning administrator shall schedule the matter of a lapsed project schedule for consideration by the City Council. The zoning administrator shall provide written notice to the applicant of the date, time and place of the City Council meeting(s) during which the lapse of project schedule will be scheduled for consideration. The owner or any other person with interest in the project may appear and shall be afforded an opportunity to speak to City Council concerning the matter.

3. At a scheduled voting session, the City Council may, but is not necessarily required to, initiate a process consistent with zoning procedures law and procedures of this zoning ordinance to revoke a variance or conditional use permit previously approved on or after September 17, 2024, but for which a project schedule has lapsed, or to modify the zoning classification granted or revert the zoning classification granted to the zoning district that existed prior to September 17, 2024. Any such action shall be consistent with procedures of this zoning ordinance for notice and public hearings for the type of application with a project schedule that has lapsed. Alternatively, the City Council may elect to take no action to initiate a reversion or revocation process.

4. The City Council may, after following applicable required procedures, in regular session approve an ordinance or resolution, as the case may be, to reverse or revoke a previously approved conditional use permit or variance or revert the zoning district for the project to the zoning category that existed for the subject property prior to approval for the project with a lapsed project schedule. Alternatively, the City Council may elect to take no action, or it may grant an extension to the approved project schedule based on information provided by the owner, the zoning administrator, or on its own initiative that such an extension is appropriate.

(k) Monitoring. It shall be the responsibility of the zoning administrator to monitor all approvals of variance, conditional use permit and rezonings on or after September 17, 2024, for which a project schedule has been imposed by City Council, and to initiate actions specified in this section in cases where a required project schedule has lapsed.

Leer este código donde se publica (city website) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:hoschton/zoning/8.10@2026-11-14-3e20250d2a

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.