Ir al contenido
Georgia Commons
Menú

Johns Creek · Ordenanza de zonificación

Part II - CODE OF ORDINANCES / Part A - GENERAL ORDINANCES / Chapter 113 - DEVELOPMENT REGULATIONS / Article XI - STREET DESIGN AND CONSTRUCTION REQUIREMENTS

Sec. 113-129. Street construction.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(1) Sub-grade preparation for all streets.

Street construction shall be done in accordance to GDOT standards or these regulations, with the more restrictive requirements controlling.

a. Preparation.Sub-grade preparation shall be in accordance with GDOT

specifications and these regulations.

b. Unsuitable material. If any sections of the sub-grade are composed of topsoil,

organic, or other unsuitable or unstable material, such material shall be removed and replaced with suitable material and

then thoroughly compacted as specified for fill or stabilized with stone or a geo-textile or geo-grid as approved by the director.

c. Compaction. Fill shall be placed in uniform, horizontal layers not more than eight inches thick (loose measurement).

Moisture content shall be adjusted as necessary to compact material to 95 percent maximum laboratory dry density and the top 12 inches to 100 percent maximum laboratory dry density as determined by AASHTO method T-99.

d. Utility installation. After the earthwork has been completed, all storm drainage,

water, and sanitary sewer utilities have been installed within the right-of-way as appropriate, and the backfill in all such ditches thoroughly compacted, the

sub-grade shall be brought to the lines, grades, and typical roadway section

shown on the plans.

e. Compaction testing. Utility trenches cut in the sub-grade shall be backfilled as

specified herein. Compaction tests at the rate of one per 150 feet of trench may be required to verify compaction.

f. Proof-roll. The sub-grade must pass roll testing with a fully loaded dump truck

prior to placement of the base material.

With the approval of the department, a geo-textile or grid may be used to stabilize a sub-grade that does not pass proof rolling.

g. Use of roads as construction roads.

When the street is to be used for construction traffic before the paving work is completed, a layer of stone (except crusher run) shall be laid as a traffic surface. This material shall not be used as a part of the base material. It

may be worked into the sub-grade, or it shall be removed before the base course is set up for paving.

h. Temporary drainage. Provisions shall be made to drain low points in the road

construction when the final paving is delayed. A break in the berm section is required when the curbing has not been constructed. After installation, drainage under the curb to side slopes is required, using minimum four inch diameter pipe

sections.

(2) Base preparation for all streets.

a. Crushed stone base.

1. Base preparation shall be in accordance with GDOT specifications and these regulations. The base material must pass roll testing with a fully loaded dump truck prior to placement of the paving material.

2. Base course thickness shall be in accordance with subsection (3) of this section.

3. Lay one course to a maximum depth of eight inches. If the required depth exceeds eight inches construct two or more courses of equal thickness. Moisture content shall be adjusted as necessary to compact material to 100 percent maximum laboratory dry density as determined by AASHTO method T-180.

b. Prime coat.

1. If a delay in paving is reasonably expected by the developer or the city, the base shall be primed with

0.25 gallon of R.C. 70 per square yard the same day it is compacted, and cured for seven days prior to paving.

2. Prime coats may also be required for cement or lime stabilized bases or sub-bases, regardless of pavement thickness.

3. Prime coats shall not be applied to a wet surface, in air temperatures less than 40 degrees F in the shade or if rain is imminent.

c. Soil cement subgrade.

1. If the subgrade material (resident soil) is unsatisfactory to the city then a soil cement mix design with engineer test results acceptable to the city may be used. The design must come from a geo-technical firm with the results certified by a professional engineer registered in the State of Georgia. The tests required for the design are ASTM D558 or AASHTO T134 or ASTM D559 and/or 560 or ASHTO T135 and 136.

2. The minimum base course shall consist of at least six inches of suitable soil (high mica content not suitable) stabilized with ten percent of Portland cement by volume (approximately 42.3 pounds per sq.

yd.). Where the grade of the street is five percent or greater, a single surface treatment course must be applied before the binder.

(3) Paving standards for all streets.

a. Asphalt streets.

1. Asphalt paving installation shall be in accordance with GDOT specifications and these regulations. Asphalt paving shall not be installed directly on the sub-grade. A graded aggregate base shall be installed in accordance with these and GDOT specifications for all asphalt paving sections.

2. All pavement sections shall be designed by a qualified, registered professional engineer based on the 20-year projected traffic loads for that section. The minimum acceptable pavement sections shall be defined as follows:

Table 11.9-1 Minimum Construction Standards(1) Street Classification Base Binder Topping 9.5 mmType II or 12.5 mm Principal and

minor arterials 12" GAB 6" (2) 1½" Collectors 12" GAB 6" (2) 1½" Nonresidential local 8" GAB 3" 19mm 1½" Residential local and alleys 8" GAB 1½" 19 mm 1½" Notes:

1. Unless otherwise specified by the public works department or GDOT.

2. Binder course shall consist of four inches 25 mm Superpave base and two inches of 19 mm Superpave binder.

b. Concrete streets. On residential streets five inches of 3500 psi concrete is to be applied on a stabilized and compacted

sub-grade with six inches of compacted GAB, or seven inches of compacted GAB on all other streets. The design and construction of the street shall comply with GDOT standards. Use of concrete streets requires the approval of the public works director.

c. Pavement overlays. Where pavement overlays are required they shall comply with the following standards:

1. Finished surface shall be a maximum height of 1.5 inches above the edge of the existing curb and gutter or shoulder, where curb and gutter has not been provided.

Edge grinding shall be required in accordance with this section to meet this standard.

2. When edge grinding has been required it shall be performed for a minimum distance of seven feet along the edges/sides and ten feet at the ends of all overlay sections.

Edge grinding shall be performed to a minimum depth of one inch ±

0.25 inch.

3. At the direction of the city inspectors all base failures, rutting, cracking

and potholes etc. within the area of the overlay section shall be repaired in accordance with GDOT standards prior to resurfacing.

4. A tack coat shall be applied to all surfaces to be overlaid, in accordance with GDOT standards.

(4) Local residential-rural streets. Where allowed local residential-rural streets do not require curb and gutter. The road base shall be extended one foot beyond the edge of pavement, and the shoulders shall extend eight feet from the edge of pavement to a standard ditch section on each side (see standard drawings).

Otherwise, the roadway shall comply with the standards for new residential subdivision streets, above.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2009-06-18, (11.9), 6-29-2009)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:johns-creek/zoning/113-129@2026-11-11-0c67bc4b3d

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.