Sec. 113-165. Pipe collection systems.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(1) General requirements.

a. The maximum velocity in a corrugated metal pipe system for the design flow shall be 15 fps. Velocities over ten fps in a pipe of any material shall be

considered a special design with particular attention required to pipe invert protection and the ability of the receiving waterway or detention facility to accept the flow without damage.

b. The minimum allowable slope shall be in accordance with the Georgia Stormwater

Management Manual.

c. The maximum allowable slope for a concrete drainage pipe shall be ten percent, for a corrugated metal pipe shall be 14 percent and for a HDPE pipe shall

be 14 percent. Greater slopes may be approved if installation is in accordance with manufacturer's recommendations.

In cases where the slope is in excess of ten percent, anchor collars may be

required.

d. Catch basins, drop inlets, and junction boxes shall be designed by the

developer's engineer or registered surveyor to GDOT standards and subject to approval by the director.

(2) Methodology. The rational method shall be used to determine the size of all pipe collection systems in accordance with the methodology provided in the Georgia

Stormwater Management Manual. Closed storm drainage systems shall be designed using the 25-year storm event.

(3) Minimum pipe size. Minimum pipe size shall be 18 inches.

(4) Inlet location and gutter spread.

a. Catch basins shall be located at low points of streets and at all points where the gutter spread exceeds one-half of

the width of the travel lane or eight feet whichever is smaller. Flows shall be

based on a 25-year design storm event and shall be calculated as described in the Georgia Stormwater Management Manual. Gutter spread calculations shall be included in the stormwater

management study.

b. Junction boxes or inlets shall be provided at all changes in pipe grades, direction or materials. All junction boxes or inlets shall be provided with metal manhole

frames and lids for access.

(5) Pipe slope. All storm sewer pipes shall be sloped to provide a minimum velocity of 2.5 fps, full flow velocity. In no case shall the slope be less than one percent for corrugated metal pipe or one-half percent for reinforced concrete pipe and HDPE.

(6) Flow and outlet velocity. Maximum flow velocity, actual or full flow, is 20 fps. Maximum outlet velocity, actual or full flow, is five fps with adequate energy dissipation devices installed at the pipe outlet.

(7) Hydraulic grade line. Complete flow, velocity, and hydraulic grade line computations shall be provided for all portions of a closed drainage system. Hydraulic grade lines shall be shown on the storm drainage profiles for the 25-year design storm event. Hydraulic grade line calculations shall include any tail-water or backwater effect from downstream structures.

(8) Easements. Easements shall be required as provided in article XII.

(9) Cover. Minimum cover shall be 24 inches on all drainage pipes, as measured from the bottom of the sub-grade or sub-base if used to the outside top of pipe. Maximum cover shall be as defined in GDOT specifications.

(10) Maximum pipe length. Maximum continuous runs of pipe shall be as follows:

Table 13.5-1 Maximum Continuous Pipe Length Pipe Diameter (inches) Maximum Continuous Length (feet) 18 300 24-60 400 Larger than 60 500

(11) Subdrainage. Subdrainage may be required to be installed to control any surplus groundwater by intercepting seepage or by lowering or regulating the groundwater level where such conditions exist.

(12) Back fill. The back-fill around and over storm sewer pipes, culverts and minor structures shall be of selected material type I or type II.

The back-fill shall be placed and compacted so as to avoid unbalanced loading and to avoid placing undue stress on the structure. Back-fill shall be built up in horizontal layers not more than six inches thick and each layer shall be thoroughly compacted by the use of rapid striking mechanical tampers or hand tampers.

After compaction, the dry weight per cubic foot for each layer of back-fill shall be at least 95 percent of the maximum laboratory dry weight per cubic foot. Back-fills shall be built up and compacted above pipe and culverts to a

thickness of at least two feet or half the vertical inside diameter of the pipe, whichever is greater, unless these dimensions exceed the proposed height of embankment, in which case the

back-fill shall be made and compacted to the height of the embankment.

(13) Outlet location—Culverts and pipe systems.

a. Outlet structures (such as headwalls) shall not be located closer to the project site's property line than the distance

necessary to construct any outlet protection or a flow distance equal to six pipe diameters, whichever is greater. For non-circular conduits, the distance equal to six pipe diameters shall be six times the rise dimension of the conduit. The

design of the outlet protection shall be in compliance with the Manual for Erosion

and Sediment Control in Georgia.

b. The invert elevation of a culvert or pipe outlet shall be no more than two feet

above the elevation of the bottom of the receiving watercourse at the outlet,

unless adequate slope protection and channel are constructed to safely convey the discharge from the outlet of the pipe to the receiving channel.

(14) Energy dissipation. The maximum developed condition flow velocity at the project site's downstream property line with an adjoining tract shall not exceed the maximum

pre-developed condition velocity.

(15) Discharge of concentrated flows.

a. The discharge of concentrated flows of stormwater into public roadways shall

be avoided. Applicant shall demonstrate to the satisfaction of the director that all reasonable efforts have been made to

control stormwater on the project site.

b. In residential subdivisions, the drainage area contributing to the peak flow along any property line between lots within 50 feet of the building setback line for either lot shall not exceed two acres, unless

contained within a piped drainage system or maintained in a natural watercourse. The stormwater conveyance shall be in a drainage easement.

(16) Storm drain stenciling. When required by the city, all residential subdivision and commercial entity storm drainage structures or facilities (catch basins, storm sewer inlets, manholes and other structures that capture and convey stormwater runoff) shall be properly identified as draining to a stream.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2009-06-18, (13.5), 6-29-2009)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:johns-creek/zoning/113-165@2026-11-11-342eb47f30

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Johns Creek Zoning Ordinance, Sec. 113-165. Pipe collection systems | Georgia Commons