10.02.04. Preliminary Approval

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A. An application for preliminary plat approval shall be studied by the Planning Commission for compliance with this chapter and with other relevant governmental and public utility company regulations.

B. No preliminary plat shall be acted upon by the Planning Commission without review at a scheduled Planning Commission meeting.

C. The Planning Commission shall indicate on the plat, or by written memorandum attached thereto, comments and any suggested changes that are necessary to meet the intent of this chapter or to serve the best interests of the city.

D. Not more than 30 days after the submission of an application for preliminary plat approval, the Planning Commission shall provide recommendation to the applicant. The Planning Commission shall:

1. Issue a certificate of preliminary plat approval;

2. Issue a certificate of conditional preliminary plat approval, subject to any necessary modifications, the nature of which shall be indicated on the preliminary plat or attached to it in writing; or

3. Disapprove the preliminary plat or any portion thereof, in which case the Planning and Zoning Administrator shall so notify the sub-divider in writing, stating the reasons therefore.

E. Action of the Planning Commission shall be noted on three copies of the preliminary plat. One copy shall be returned to the applicant, one made a part of the Planning Commission's records and the other zoning records.

F. Failure of the Planning Commission to take action on the preliminary plat within 30 days shall be deemed approval of the plat, and the plat shall be transmitted to the applicant, provided:

1. The plat is submitted for preliminary approval not later than five days prior to the next regularly scheduled meeting of the Planning Commission; and

2. The sub-divider does not agree upon an extension of time, if requested in writing by the Planning Commission to further study the preliminary plat.

G. Approval of all preliminary plats shall be governed by the following qualifications:

1. Approval of a preliminary plat is only tentative pending submission of the final plat.

2. Approval of the preliminary plat shall be effective and binding upon the city for a period not to exceed one year, and shall thereafter expire and be null and void except to the extent that work on the subdivision has progressed, unless a request for an extension of the time has been submitted to and is subsequently approved by the city.

3. No improvements, including clearing or grading, shall be undertaken until final engineering plans based on runoff calculations and three-line profiles for the subdivision, or unit division thereof, have been submitted to and approved by the city engineer.

H. Tentative approval of the preliminary plat does not constitute approval of a final plat.

It indicates only approval of the layout as a guide to the preparation of a final plat.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2023-12, § 1, 6-19-23)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:kennesaw/zoning/10.02.04@2026-11-11-2c4d7c9a4c

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Kennesaw Zoning Ordinance, 10.02.04. Preliminary Approval | Georgia Commons