Lee County · Ordenanza de zonificación

Part II - CODE OF ORDINANCES / Chapter 38 - LAND DEVELOPMENT CODE / Article VII - STORM DRAINAGE SYSTEMS / Division 3 - POST DEVELOPMENT STORMWATER MANAGEMENT

Sec. 38-299. Generally.

Sobre este texto

  • As published by Municode, current through 2026-06-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Drainage collection and conveyance shall be as follows:

(1) All drainage computations must show the drainage area, runoff constraints, time of concentration and discharge for the required storm frequency. These computations must be in a report format and show high waters in feet above the inlet of the pipe or above the flow line of the grate. All structures must have computations for inlet control and outlet control. The methods for calculations shall be clearly stated and all assumptions clearly defined.

(2) These standards are to serve as a guide to engineers versed in drainage analysis and design. Unique circumstances requiring special or alternative design methods shall be brought to the attention of the county early in the project life so that agreement on problem approach can be reached without impacting the project progress.

(3) Peak flow and total runoff volume after development will not exceed the peak flow and total runoff volume prior to development for the following storm events two-year, five-year, ten-year, 25-year, 50-year, and 100-year unless the downstream landowner has granted legal permission to increase flooding.

a. Design storm of collection systems:

1. Ten-year event for drainage sub-basins with ten-year peak flows less than 75 cubic feet per second (hereinafter "cfs").

2. Twenty-five-year event for drainage sub-basins with ten-year peak flows between 75 cfs and 200 cfs.

3. Fifty-year event for drainage sub-basins with ten-year peak flows greater than 200 cfs.

4. As the collection grows in size, the peak flow will increase and when the lower peak flow limits are exceeded then the higher design storm events are required at that point in the system.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Res. No. LD05-A049, 9-23-2005)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:lee-county/zoning/38-299@2026-06-23-1ef04d96ff