Part II - CODE OF ORDINANCES / Chapter 70 - ZONING / Article XXI - SOLAR ENERGY SYSTEMS
Sec. 70-692. General requirements for all ground mounted solar energy systems.
Sobre este texto
- As published by Municode, current through 2026-06-23
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
The following requirements apply to all ground mounted SES facilities, in addition to the specific requirements in this article which apply specifically to intermediate and large scale SESs respectively.
(1) Solar access. Consistent with O.C.G.A. § 44-9-20 et seq., a property owner may obtain a solar easement from another property owner for the purpose of ensuring a ground mounted SES adequate exposure to sunlight.
(2) Impervious surface. Ground mounted structures and components of the ground mounted SES facility, including transformers and foundations, shall be considered impervious. However, for purposes of compliance with the Lee County zoning code's impervious surface coverage requirements, the panels of a ground mounted SES shall be considered pervious if they maintain sheet flow and allow for water to infiltrate under and around them through a pervious surface and into the subsoil.
With respect to the location of solar panels on the land surface, the following shall apply:
a. Arrangement of solar panels on mild slopes (less than ten percent) is encouraged. If the ground slope is steeper than five percent, adding level spreaders in the ground at each dripline will slow the movement of water and maintain sheet flow.
b. Use structures/foundations for the solar energy system that occupy minimal space (no more than five percent of total site area).
c. Include a sufficient distance between rows of panels to allow for capture of rainfall and growth of vegetation beneath and between. This disconnection distance between rows of panels should be greater than the width of a single solar panel.
d. Limit the lowest vertical clearance of the panels to no greater than 10 feet to avoid erosion at the dripline.
(3) Lighting. To reduce light pollution, lighting of a ground mounted SES facility shall:
a. Be limited to the minimum reasonably necessary for its safe operation:
b. Be directed downward where reasonably feasible;
c. Incorporate full cut-off fixtures; and
d. Reasonably utilize motion sensors.
(4) Tree removal. The removal of trees or natural vegetation for a ground mounted SES shall be avoided to the extent reasonably practicable and such removal shall comply with the requirements of the Lee County zoning code.
(5) Decommissioning. Unless otherwise approved by the Lee County Board of Commissioners, decommissioning shall begin no later than 12 months (365 calendar days) after a ground mounted SES has ceased to generate electricity or thermal energy and shall be finally completed no later than 12 months (365 calendar days) after commencement of such decommissioning. Such decommissioning shall be undertaken and completed by the owner or operator of the SES facility at the time of such decommissioning. Such decommissioning shall be accomplished in accord with the following:
a. For a ground mounted SES facility allowed with a permit, the SES facility shall be decommissioned in accordance with the most recent decommissioning plan approved by the Lee County Board of Commissioners, and as further described below and in chapter 70, article 70-697(2)f. related to decommissioning:
b. All sizes of ground mounted SES facilities shall be removed from the premises, and such removal shall include, but shall not be limited to, all materials installed or associated with the facilities, including above ground and below ground materials, and such removed materials shall be either deposited in an appropriate public licensed landfill site recycled or otherwise reused in another facility
c. The real property where the SES facility was located shall be returned to its substantially original condition which existed at the time of approval of the construction of the SES facility by Lee County.
d. For SES facility sites which were forested sites at the time of approval of the construction of the SES facility by Lee County the replanting of the solar site after decommissioning with the same number and species of trees shall be accomplished during the decommissioning process. Replanting with non-native trees or only planting with one type does not capture the same habitat and carbon sink gains that the site originally produced, and is not authorized.
e. A decommissioning plan shall be submitted with each application for the location and construction of an SES facility and must be approved by the Lee County Board of Commissioners as part of the SES facility approval process.
f. In order to facilitate the decommissioning process, and notwithstanding any other provision of this article, the owner or operator of a proposed SES facility shall submit to Lee County pictures, including aerial photographs (including Google Maps' aerial photographs) of the proposed SES facility site as part of the application process for approval and permitting of a SES facility.
Historia
(Ord. of 1-28-2020; Ord. of 10-26-2021, pt. 5)