Appendix C - LAND DEVELOPMENT REGULATIONS / Article VII - STORM DRAINAGE SYSTEMS / Division 1 - GENERALLY

Sec. 7.10. Residential subdivision lot drainage.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Residential subdivision lots shall be laid out so as to provide positive drainage away from all buildings, and individual lot drainage shall be coordinated with the general storm drainage pattern.

(b) Drainage shall be designed so as to avoid concentration of storm drainage water from each lot to adjacent lots.

(c) For new dwelling structures and appurtenances to include all infrastructure facilities and garages directly serving any dwellings located on any lot within a "major" subdivision as defined in the subdivision regulations the following requirements shall apply:

(1) Requirements.

a. All dwelling structures and appurtenances on any major subdivision lots shall have all finished floors elevated to at least 24 inches above the centerline of the road.

b. Earthen fill shall be placed around the foundation of all dwelling structures so that the elevation of the finished grade immediately adjacent to the foundation of the structure shall be at least 12 inches above the road centerline. The grade shall be sloped away from the structure for a distance of not less than 25 feet at a minimum grade of four percent (25:1 slope) and a maximum grade of 25 percent (4:1 slope).

(2) Permit process.

a. At building permit application submittal the builder shall:

1. Sign an elevation affidavit form (provided by the building inspection department). On the affidavit the builder shall indicate the proposed elevation of the structure's finished floor and of the finished soil grade immediately outside of the structure. The finished floor elevation and the soil grade elevation shall be measured in relation to the road centerline elevation immediately adjacent to the structure (for lots with double road frontages the elevation may be to either of the roads). This may be as simple as stating:

i. Existing road centerline elevation plus zero inches.

ii. Finished soil grade elevation plus 12 inches above road centerline and iii. Finished floor grade elevation plus 24 inches above road centerline.

(3) Field verification.

a. For field verification the builder shall:

1. Drive a two-inch by four-inch stake in the ground immediately outside of the foundation at the side of the structure facing the road. The stake shall have three marks. The marks on the stake shall indicate the elevation of the road centerline, the finished soil grade elevation, and the finished floor elevation.

It shall be the builder's responsibility to determine the elevations and to verify to the building inspector that the three elevations are correct before any concrete is poured. If there is any discrepancy in the elevations as determined by the building inspector the builder shall be required to prove to the building inspector's satisfaction that the elevations are at least the minimum height above road centerline elevation. If the builder is not able to verify the elevations to the satisfaction of the building inspector then concrete shall not be poured until the problem is resolved.

(4) Exemptions.

a. Exemptions for relief due to extreme sloping lots and changes in topographic contours (downward and away from the roadway) that would make it unreasonable to construct the structure with finished floors two feet above the road centerline may be granted provided the following information is submitted prior to a building permit being issued:

1. A topographic survey of the lot showing one-foot contours stamped by either an engineer or surveyor licensed in the State of Georgia shall be submitted. The survey shall indicate the proposed location of the structure and all associated supporting infrastructure to include any well, septic tank and drain field, HVAC, etc.

2. A letter from the engineer or surveyor detailing the reasons why the exemption should be granted shall accompany the topographic survey document.

3. An engineer or surveyor licensed in the State of Georgia shall also determine whether the lot is located within or adjacent to a closed contour based upon local topography. If the lot is within or adjacent to the confines of a closed contour the engineer or surveyor shall certify that the building site for the dwelling is already at least three feet above the 100-year high water level. If the building site is not already at least three feet above the 100-year high water level the engineer or surveyor shall establish a finished floor elevation (FFE) so that the finished floor is at least three feet above the 100-year high water elevation of any potential ponding stormwater.

a. The 100-year high water elevation shall include pre- and post-developed runoff coming to the site and shall include any stormwater retention or detention area whether manmade or natural. This shall include the ponding of stormwater on the lot in question or any

adjacent lot or lots within the confines of a sub-basin drainage area located in the subdivision. This shall also include any basin area adjacent to the immediate subdivision phase but still impacting lots within that subdivision phase.

b. If a finished floor elevation is required to be established then the formal elevation certificate process shall be followed; requiring that a flood elevation certificate shall be submitted prior to the building permit being issued and another one after the first finished floor is established to verify that the finished floor is at least at or above the established elevation. All applicable construction practices and floodplain development requirements shall be adhered to.

(d) For any dwellings and appurtenances to include all infrastructure facilities and garages directly serving any dwellings built on individually subdivided lots located outside of the confines of a major subdivision or any lot located in a minor subdivision as defined in the subdivision regulations the following shall apply:

(1) Requirements.

a. All dwelling structures shall have the finished floors built to an elevation that is at least three feet above the highest adjacent natural soil grade immediately outside of the footprint of the foundation.

b. Earthen fill shall be placed around the foundation of all dwelling structures so that the elevation of the soil grade immediately adjacent to the foundation of the structure shall be no more than 18 inches below the first finished floor on any side of the structure facing an uphill grade. (This requirement may be waived on any side of the structure where the natural grade falls away from the foundation.) The earthen fill shall slope away from the structure at a minimum grade of four percent (25:1 slope) and no steeper than a 25 percent (4:1 slope) from the foundation to the point where it ties in to natural dirt grade on the uphill side or sides of the structure.

(2) Permit process.

a. At building permit application submittal the builder shall:

1. Sign an elevation affidavit form (provided by the building inspection department). On the affidavit the builder shall indicate the proposed elevation of the structure's finished floor as related to highest existing natural dirt grade immediately outside of the structure. This may be as simple as stating:

i. Highest adjacent natural soil grade plus zero feet.

ii. Finished soil grade on the uphill side of foundation to be not less than 18 inches below the first finished floor.

iii. Finished floor grade plus three feet above highest adjacent natural soil grade.

(3) Field verification.

a. For field verification the builder shall:

1. Drive a two-inch by four-inch stake in the ground immediately outside of the foundation at the point where the highest adjacent natural soil grade exists immediately outside of the foundation. The stake shall have three marks.

The marks on the stake shall indicate: (1) the elevation of the highest adjacent natural soil grade; (2) the finished soil grade on the uphill side of foundation; and (3) the finished floor elevation. It shall be the builder's responsibility to verify to the building inspector that the three elevations are correct before any concrete is poured. If there is any discrepancy in the elevations as determined by the building inspector the builder shall be required to prove to the building inspectors satisfaction that the elevations are at least the minimum height above road centerline elevation. If the builder is not able to verify the elevations to the satisfaction of the building inspector then concrete shall not be poured until the problem is resolved.

(4) Exemptions.

a. Exemptions for relief due to extreme sloping lots and changes in topographic contours (vertically upward and away from the roadway) that would make it unreasonable to construct the structure with finished floors three feet above the highest adjacent natural dirt grade may be granted by the development services director provided the following information is submitted prior to a building permit being issued:

1. A topographic survey of the lot showing one-foot contours stamped by either an engineer or surveyor licensed in the State of Georgia shall be submitted. The survey shall indicate the proposed location of the structure and all associated supporting infrastructure to include any well, septic tank and drain field, HVAC, etc.

2. A letter from the engineer or surveyor detailing the reasons why the exemption should be granted. The letter shall indicate whether the existing natural dirt grade at the proposed building site is at least two feet above the centerline of the roadway fronting the structure.

i. If the documentation provides supporting information that the requirement to elevate the first finished floor three feet above the highest adjacent natural dirt grade is extreme or unreasonable and that the structure shall not be threatened by any ponding stormwater then the development services director may wave the elevation requirement.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:leesburg/zoning/7.10@2026-11-11-ecf61e65cf