Sec. 3.22. Improvements guarantee.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) An improvements guarantee, as required by the subdivision regulations, shall provide for and secure to the city a guarantee that the actual construction, performance and installation requirements of the city have been met and that a two-year test period shall be met. The improvements guarantee shall be with a surety company or bank licensed to do business in the state and acceptable to the city. The improvements guarantee shall contain the following provisions:

(1) Indemnify the city for the maintenance and performance of the installations and improvements required by this ordinance and the zoning regulations in the development for two years following the date for final subdivision approval and acceptance of the improvements by the city council;

(2) Allow the city to acquire the guarantee prior to the end of the two-year test period of requested repairs have not been completed within the guidelines of this ordinance; and

(3) The surety company or bank securing the guarantee may release the guarantee only after the manager of development services has written stating his approval upon the completion of the two-year period.

(b) The improvements guarantee amount shall be ten percent of the total cost of all construction. Proof of the total cost of the project shall be submitted to the manager of development services prior to the request for final construction approval.

(c) After final construction approval and during the two-year improvements guarantee period if repairs are required, the manager of development services shall make written reports after each inspection and forward the reports to the planning director, the developer and the surety company or bank providing and insuring the guarantee.

(d) All repairs shall be completed within 30 days. If emergency repairs of deficiencies are determined to be required by the manager of development services in conjunction with the planning director, the repairs shall be completed within ten days. If improvements are not completed within the specified time limit, the manager of development services shall begin the process for acquiring the improvements guarantee.

(e) If any reported deficiencies have not been repaired by the specified time, the manager of development services shall make a written report to the planning director concerning the deficiencies, the required repair date, the failure to meet the repair date, and the guarantee expiration date. The planning director shall make such determinations as necessary about the deficiencies and whether or not to acquire the improvements guarantee in reference to the good of the public and the city.

(f) The procedures for administering the inspections for the guarantee is as follows:

(1) The manager of development services or his designee shall make three inspections of the guaranteed improvements on a six-month interval basis. If any deficiencies exist, a written report outlining the deficiencies shall be prepared by the manager of development services and given to the developer. The developer shall make any necessary repairs.

(2) Forty-five days prior to the expiration date of the guarantee the manager of development services shall make inspections for the approving of the release of the guarantee.

If any deficiencies exist a written report outlining the deficiencies shall be made and given to the developer. The developer shall make any necessary repairs.

(3) Fifteen days prior to the expiration date a final inspection shall be made. If any new deficiencies exist a final written report shall be made by the manager of development services and presented to the developer and planning director. The planning director shall review said report and determine whether to seize the guarantee to fix the deficiencies.

(g) If at the expiration date inspection there are no deficiencies or all deficiencies have been corrected, the manager of development services shall make a final written report describing the satisfactory completion of the two-year test period and authorize the release of the guarantee.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:leesburg/zoning/appendix-c-article-iii-division-2-3.22@2026-11-11-6c67750eb6

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Leesburg Zoning Ordinance, Sec. 3.22 (Appendix C, Article III, Division 2). Improvements guarantee | Georgia Commons