Lovejoy · Ordenanza de zonificación
Appendix A - ZONING / Article XII - ADMINISTRATION AND ENFORCEMENT
1201.3. Building construction.
Sobre este texto
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(A) A building permit issued by the building inspector is required in advance of the initiation of construction, erection, moving or alteration of any building or structure where the estimated cost of such construction, erection, moving or alteration is estimated to be in excess of $100.00.
(B) The developer or builder shall stake out, or cause to be staked out, with markers at least 24 inches in height, the required setback distances (front, rear and side yards), building footprint and property lines. This staking shall be in place at the time the building inspector conducts the foundation/footings inspections.
(C) Upon completion of the build foundation up to the first floor of the building, the builder or developer shall obtain a survey by a registered land surveyor or professional engineer specifying the elevation of the building's first floor, elevations of any floodplain on the lot on which the building is being constructed, and elevations of the ground in all directions 20 feet from the building. This survey shall be required before any further inspections are made or work is undertaken but only if any of the following conditions are met:
(1) The final plat of the subdivision in which the lot is located shows a floodplain line on any portion of the subject lot.
(2) The zoning administrator indicates the apparent presence of a 100-year floodplain on the property unless a survey by a registered land surveyor or professional engineer states to the contrary.
(3) A review of the flood boundary and floodway maps for the city prepared for the Federal Insurance Administration indicates a possibility of the presence of a 100-year floodplain on the subject property unless a registered land surveyor or professional engineer certifies to the contrary.
1201.4. Final certification of zoning compliance. Any development requiring the zoning administrator's approval of predevelopment plans under subsection 1201.2 of this section is also subject to the requirements of this subsection. Accordingly, prior to obtaining a certificate of occupancy for any such development, the builder/developer shall obtain a final certification of zoning compliance from the zoning administrator. To obtain such final certification, the builder/ developer must submit an as-built site plan to the zoning administrator in accordance with such policies and procedures which the zoning administrator is to establish. In lieu of a complete as-built site plan, the builder/developer may submit an as-built site plan for only those items developed different from the approved predevelopment site plan.
1201.5. Certificate of occupancy. Upon the completion of construction activity requiring a building permit, the developer or builder shall obtain a certificate of occupancy. It shall be unlawful to use or occupy or permit the use or occupancy of any building or premises, or both, or part thereof, so requiring a certificate of occupancy without first obtaining a certificate of occupancy for said building or lands. The building inspector shall be responsible for issuance or non-issuance of said certificate. Applications for a certificate of occupancy shall be made on such forms and contain such materials as required by the director of the permits and licenses department.
Historia
(Ord. No. 2024-02, § 1, 6-17-2024)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.