A. In order to assure that the requirements of this chapter [appendix] are satisfied, all applications for a building permit shall be accompanied by a building site plan which shall conform to the list of requirements, and be reviewed by the zoning administrator to determine compliance with this chapter [appendix] before a building permit is issued;

1. Site location map.

2. The site plan shall be drawn to a minimum scale of one inch equals 100 feet. The building official may request that the plan be drawn by a registered engineer or surveyor certified to work in Georgia if questions of soil suitability or flood zone locations exist within the property for which a building permit is being sought.

3. The plan shall show all property lines.

4. The plan shall show the complete outline of the proposed building at the location where it is proposed to be built.

5. The plan shall show all required building setback lines: front, rear and sides. No part of any permanent structure shall encroach on any required setbacks.

6. The plan shall show all required parking, landscape buffers and all other requirements as set out in this chapter [appendix].

B. After the zoning administrator has reviewed the site plan, a letter stating approval/ disapproval will be sent to the building official.

C. Before inspection of the foundation, the builder shall run string connecting all the iron pins that define the corners of the lot to create an outline of the lot on the ground.

D. At the time the building official conducts the foundation inspection, he will measure from the string determining the property lines to the proposed outermost edge of the building to assure compliance with the requirements of this chapter [appendix] as they pertain to required setbacks.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:marion-county/zoning/4.17@2022-03-08-90f7f0cbf2

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Marion County Zoning Ordinance, Sec. 4.17. Site plan review | Georgia Commons