17.16.110. Expiration of approvals.
Sobre este texto
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
Most development projects commence quickly and finish within a reasonable time period, but not all projects do this, some development projects linger for months and years. For development projects that linger, the original approvals do expire after a set period of time.
A. Development project approval. When a project is approved administratively by the BZA or by an ordinance of the mayor and city council, the city assumes that the project shall commence in a timely matter.
B. Approval expirations. The countdown for when an approval expires begins on the
day the project was originally approved by the city. The expiration period for various project types are as follows:
1. Exterior façade. Six (6) months with one (1) ninety-day extension is allowed;
2. Signs. Six (6) months with one (1) ninety-day extension is allowed;
3. Variances. One (1) year with one (1) six-month extension is allowed;
4. Zoning amendment. One (1) year.
Preliminary plat must have commenced, or the project must have made substantial progress. A zoning
amendment is allowed two (2) sixmonth extensions;
5. Preliminary or final plat. If work has not commenced in one (1) year, two (2) six-month extension are allowed;
6. Conditional uses. One (1) year.
Conditional uses have to start the renewal process before the first year expires;
7. Special use permits. One (1) year.
Special use permits have to start the renewal process before the first year expires;
8. Concept plan. One (1) year, no extensions;
9. Land development permit. One (1) year with two (2) six-month extensions are allowed;
10. All permit applications that have not been approved within one hundred eighty (180) days of the process being initiated (acceptance of first set of plans) shall expire after one hundred eighty (180) days.
Extensions are granted at the discretion of the director.
C. Phased projects. The first phase must begin within one (1) year of the initial approval. Subsequent phases must start
within one (1) year of the previous phase's completion. If not, the approval on all
subsequent phases will expire immediately, and the remaining phases of the project will revert to their preapproval state.
D. Extensions. To file for an extension, the community development office must
receive an application for an extension thirty (30) days before the original approval expires. Any extension requests received within less than thirty (30) days of expiration will pay double the application fee. If an extension is requested within thirty (30) days of the approval
expiring, the application fee will be tripled.
E. Expiration. Once the original approval expires, the city has the right to revert the property or use back to the state that the property existed before the development project was approved.
F. Previous approvals. Any Development projects approved three (3) years before the effective date of Title 17: Zoning
update on January 1, 2025, these development projects have one (1) year to apply for an extension. If no extension is
requested by January 1, 2026, the city shall reserve the right to let any previous approvals expire and revert to the state of the property prior to the original
approval. Projects that received their approval prior to January 1, 2022, have one (1) year to contact the community development department before their approvals may be rescinded or modified by action of the mayor and city council.
(Ord. No. 25-01-02, § 1, 1-2-2025)
CHAPTER 17.24 �FOR SALE� RA
RESIDENTIAL-AGRICULTURAL
DISTRICT
Sections:
Reuniones que se refieren a esta sección
- McDonough Planning Commission, 10 de marzo de 2026 (Actas)Se refiere a esta sección en las actas: “Section 17.16.110”
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.