Ir al contenido
Georgia Commons
Menú

Oconee County · Ordenanza de zonificación

Part - CODE OF ORDINANCES / Chapter 66 - UTILITIES / Article 12 - PROCEDURES AND PERMITS / Division I - APPROVAL OF A ZONING CHANGE / 1213 - Developments of regional impact.

Sec. 1213.03. Process for DRI review.

Sobre este texto

  • As published by Municode, current through 2026-04-07
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

The DRI review process shall conform to the rules adopted by the Georgia Department of Community Affairs for Developments of Regional Impact. To the extent that the provisions of this Section differ with said rules, said rules shall control and take precedence.

a. Submission to the regional development center.

(1) First request for project approval.

(a) Upon determination by the Planning Director that an application qualifies for DRI review, the applicant shall provide such information as necessary for the DRI review on forms available from DCA.

(b) The DRI review forms prepared by the applicant shall be submitted by the Planning Director to the Northeast Georgia Regional Development Center

(RDC).

(c) Once the RDC has accepted the DRI forms as complete, the 30-day review period officially begins.

(d) Throughout the DRI process, the applicant shall coordinate with the Planning Department and the RDC and provide such additional information as may be needed to complete the DRI evaluation.

(2) Subsequent requests for project approval. Once the development project has been reviewed by the RDC and the first governmental action has been granted, no further reviews by the RDC of subsequent governmental actions need to be reviewed by the RDC unless the project is revised by an increase of 10% or more in the applicable threshold factor.

b. Final action by the county. Approval of the first request for governmental action by the County shall not be made on a Development of Regional Impact until either:

(1) Any inter-jurisdictional conflicts related to the DRI have been brought to a conclusion; and

(2) A report has been received from the RDC reflecting its public findings and comments, if any; or

(3) Said report is not received within 30 days of official determination by the RDC that the DRI application is complete.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:oconee-county/zoning/1213.03@2026-04-07-b450957cc1

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.