Oglethorpe County · Ordenanza de zonificación
Article XI - Project Design and Construction Standards / 1119 - Installation of streets and utilities.
Section 1119.05. Construction methods; roadways.
Sobre este texto
- As posted on the county's website, retrieved 2026-11-23
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
a) Roadway grading and embankments.
1) All streets and roads shall be graded to their full width by the sudivider so that pavements and sidewalks, where required or proposed for future installation, can be constructed on a level plane as shown in the cross‐sections on the approved plans.
2) The entire area within the typical grading section shall be cleared and grubbed of all trees, bushes, stumps and debris. Such debris shall be disposed of in a lawful manner, and shall not be buried in the right‐of‐way or within the project limits.
3) Road fill of suitable material free of organic matter shall be placed in uniform eight‐inch layers compacted to at least 95 percent of maximum density throughout as specified for construction and testing in the Georgia DOT standards for embankments. Embankment compaction tests shall be taken at an interval not exceeding 2500 cubic yards. All storm drainage and other underground utilities installed under the roadbed and the backfill in all ditches shall be compacted to at least 95 percent maximum density. Compaction testing of backfill for said structures shall be taken at a minimum interval not less than once between any 2 structures. Compaction test results shall be reported to the county immediately after results are obtained.
4) Cut and fill slope ratios shall start at the edge of the right‐of‐way and shall not exceed 3:1 in the right‐of‐way and 2:1 outside of the right‐of‐way. In lieu of a cut or fill slope, a retaining wall may be utilized where necessary with the approval of the county.
5) Cut or fill slopes shall be uniform for each section of cut or fill. The depth of cut or fill shall be constructed to the maximum cut or fill occurring in any one section. When a cut made in rock requires blasting, the slope may be changed to an alternative slope grade upon written approval of the county.
6) If paving is to be delayed, provisions shall be made to drain low points in the roadway. If curbing has not been installed, a break in the berm section may be provided. If curbing is in place, 4‐inch pipe sections shall be used to provide drainage under the curb to side slopes.
7) All work must be approved by the County Engineer prior to preparation of the subgrade. It is the design professional’s duty to inspect to determine whether the road grading specifications have been met. The developer will provide to the county a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for roadway grading. The developer shall also provide to the County certification by a professional land surveyor or engineer licensed in the state that grading has been completed to the lines and grades to a tolerance of +/‐ 6 inches. The developer will also provide staking of the roadway centerline in conjunction with said certification for verification by the Roads Inspector. Upon presentment and approval of such documentation by the County, road construction may continue.
b) Preparation of subgrade.
1) All boulders, organic material, soft clay, spongy material and any other objectionable material shall be removed and replaced with approved material. The sub‐grade shall be properly shaped, rolled and uniformly compacted to conform with the lines, grades and typical cross‐sections as shown on the drawings approved by the County.
2) The subgrade shall be scarified to a depth of 8 inches, and compacted to 95% maximum dry density and within +/‐ 3 percent of the optimum moisture content. Subgrade compaction shall be determined by field testing at intervals not to exceed 1500 feet. Compaction testing shall be accomplished in accordance with the standardized testing protocols of GDOT.
Written test results shall be provided to the County immediately after results are obtained.
3) It is the design professional’s duty to inspect to determine whether subgrade preparation specifications have been met. The Developer will provide to the county a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for roadway subgrade preparation. Upon presentation and approval of such documentation by the County, roadway construction may continue.
c) Preparation of aggregate base course.
1) Base course shall be installed as described in the latest edition of the GDOT Road Construction Manual.
2) Graded aggregate base shall meet the requirements of Georgia DOT Specifications for graded aggregate. Graded aggregate base compaction tests shall be taken at an interval not exceeding 1 per 1500 linear feet and shall meet all GDOT compaction requirements.
3) After the base course has been installed and inspected, and before any surface is applied, all residential streets shall be primed with suitable asphaltic materials as per Georgia DOT Specification 412 unless asphalt paving commences within two weeks from acceptance of the certification from the period March 1 to December 1 or within 24 hours during the period December 1 to March 1.
4) It is the design professional’s duty to inspect to determine whether graded aggregate base course preparation specifications have been met. The Developer will provide to the county a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for roadway graded aggregate base course preparation. Upon presentation and approval of such documentation by the County, roadway construction may continue.
d) Asphaltic concrete construction.
1) Material, equipment, seasonal and weather limitations, preparation of road surface, material application and construction methods shall be the same as set out in the Georgia Department of Transportation’s Standard Specifications for Road and Bridges, latest edition, and any amendments thereto.
2) Mix design(s) shall be provided to the County for approval at least a minimum of 2 weeks prior to paving operations.
3) If paving will not be completed within 2 weeks after the base course is completed during the period March 1 to December 1, then, the base will need to be primed in accordance with GDOT Standards with the roadway being barricaded thereafter. The above will be required within 24 hours during the period of December 1 ‐ March 1.
4) One asphaltic concrete extraction test per type mix shall be taken per subdivision. Extraction test results shall be reported to the county immediately after results are obtained.
5) Asphaltic concrete compaction tests for each type mix shall be taken at an interval not exceeding 1 per 1000 linear feet per 1 lane of roadway. All asphalt courses shall conform to GDOT compaction requirements and Compaction testing shall be accomplished in accordance with the appropriate standardized protocols set forth in the GDOT Sampling, Testing, and Inspection Manual. Compaction test results shall be reported to the county immediately after results are obtained.
6) Where a binder course is provided on streets, a tack coat shall be applied to all prepared road surfaces as provided in Georgia DOT Specifications.
7) On streets where a binder course is provided, the final layer of asphalt shall be placed no later than 1 year after the binder course is laid or when 80 percent of the project is built‐out, whichever comes first.
8) The County Engineer shall require that all work meet or exceed the above requirements.
e) It is the design professional’s duty to inspect determine whether the roadway asphaltic concrete construction specifications have been met. The Developer will provide to the county a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for road‐ way asphaltic concrete construction. Upon presentation and approval of such documentation by the county, roadway construction will be considered as complete for the purpose of final plat.
f) Base, asphalt and compaction testing.
Depth testing. The County reserves the right to require depth checks on base materials and asphalt cores to be taken at random locations at five hundred foot intervals along each road at the discretion of the County Engineer or Road & Bridge Inspector. Any area found deficient shall be brought up to the required thickness prior to placing any additional layer of material. All asphalt core holes shall be filled with hot mix asphalt of similar grade prior to final acceptance.
g) Additional testing requirements/coordination. All testing shall be scheduled with the Roads Inspector, or his/her duly appointed representative no less than 24 hours in advance. Compaction testing shall not be performed until the surface/material is to the lines and grades shown on the plans. Once an embankment, subgrade, or base course has been certified then that material shall not be disturbed or additional testing will be required. All areas or sections of the subgrade and base course, which do not pass compaction testing, shall be corrected. Once the Developer makes all necessary corrections, it shall be his/her responsibility to schedule any and all subsequent tests. The Roads Inspector may require that in addition to the compaction testing required, a roll test be performed in accordance with Section 1108.05.k. All certifications provided shall contain all test data and results to support certification.
h) Seasonal limits. No roadway construction material shall be deposited or shaped when the subgrade is frozen at any depth or thawing at any depth or during unfavorable weather conditions including rain of any intensity. Paving material installation shall be subject to temperature and weather conditions as contained in Georgia DOT construction standards. The time period from December 1 to March 1 will require special construction procedures unique to the individual sites and weather conditions.
The Contractor/Developer shall consult with the Public Works Department during a supplemental Pre‐Construction Conference prior to beginning or continuing any roadway construction work during this period. It shall be the responsibility of the Developer to schedule this conference.
Leer este código donde se publica (county website (oglethorpecountyga.gov)) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.