Section 605.06. Permit procedures and requirements
Sobre este texto
- As posted on the county's website, retrieved 2026-11-23
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
It shall be unlawful for any owner or developer to perform any land development activities without first meeting the requirements of this article and obtaining a stormwater permit prior to commencing the proposed activity.
a) Permit application requirements. Unless specifically exempted by this article, any owner or developer proposing a land development activity shall submit to the Department a stormwater permit application on a form provided by the Department for that purpose. Unless otherwise exempted by this article, a permit application shall be accompanied by the following items in order to be considered:
1) Stormwater management plan in accordance this article;
2) Inspection and maintenance agreement in accordance with this article; and
3) Permit application and plan review fees in accordance with this article
4) Plan Review Submittal Fees Plan Review Fee (Initial Review) $300.00 Required Site Visit $150.00 Second Review $0.00 Subsequent Reviews $125.00
5) As Built Drawing Review Fees As built Review $250.00 Required Site Visit $150.00 Subsequent As Built Reviews $125.00 Subsequent Required Site Visits $150.00 Stormwater management plan requirements. The stormwater management plan shall detail how post‐development stormwater runoff will be controlled or managed and how the proposed project will meet the requirements of this article, including the performance criteria set forth in this article.
b) This plan shall be in accordance with the criteria established in this section and must be submitted with the stamp and signature of a professional engineer (PE) or landscape architect licensed in the state of Georgia, who must verify that the design of all stormwater management facilities and practices meet the submittal requirements outlined in the submittal checklist(s) found in the Georgia Stormwater Management Manual .
c) The stormwater management plan must ensure that the requirements and criteria in this article are being complied with and that opportunities are being taken to minimize adverse post‐development stormwater runoff impacts from the development. The plan shall consist of maps, narrative, and supporting design calculations (hydrologic and hydraulic) for the proposed stormwater management system. The plan shall include all of the information required in the Stormwater Management Site Plan checklist found in the Georgia Stormwater Management Manual. This includes:
1) Common address and legal description of site.
2) Vicinity map.
3) Existing conditions hydrologic analysis. The existing condition hydrologic analysis for stormwater runoff rates, volumes, and velocities, which shall include: a topographic map of existing site conditions with the drainage area boundaries indicated; acreage, soil types and land cover of areas for each sub‐drainage areas affected by the project; all perennial and intermittent streams and other surface water features as noted through field investigation;
all existing stormwater conveyances and structural control facilities that impact design and/or construction of proposed development; direction of flow and inputs to and exits from the site; analysis of runoff provided by off‐site areas upstream of the project site; and methodologies, assumptions, site parameters and supporting design calculations used in analyzing the existing conditions site hydrology. For redevelopment sites, predevelopment conditions shall be modeled using the established guidelines determined by the Department for the portion of the site undergoing land development activities.
4) Post‐development hydrologic analysis. The post‐development hydrologic analysis for stormwater runoff rates, volumes, and velocities, which shall include: a topographic map of developed site conditions with the post‐development drainage area boundaries indicated;
total area of post‐development impervious surfaces and other land cover areas for each sub‐ drainage area affected by the project; calculations for determining the runoff volumes that need to be addressed for each sub drainage area for the development project to meet the post‐development stormwater management performance criteria in this article; location and boundaries of proposed natural feature protection and conservation areas; documentation and calculations for any applicable site design credits that are being utilized; methodologies, assumptions, site parameters and supporting design calculations used in analyzing the existing conditions site hydrology.
5) Stormwater management system. The description, scaled drawings and design calculations for the proposed post‐development stormwater management system, which shall include: A map and/or drawing or sketch of the stormwater management facilities, including the location of nonstructural site design features and the placement of existing and proposed structural stormwater controls, including design water surface elevations, storage volumes available from zero to maximum head, location of inlet and outlets, location of bypass and discharge systems, and all orifice/restrictor sizes; a narrative describing how the selected structural stormwater controls will be appropriate and effective; cross‐section and profile drawings and design details for each of the structural stormwater controls in the system, including supporting calculations to show that the facility is designed according to the applicable design criteria; a hydrologic and hydraulic analysis of the stormwater management system for all applicable design storms (including stage‐storage or outlet rating curves, and inflow and outflow hydrographs); documentation and supporting calculations to show that the stormwater management system adequately meets the post‐development stormwater management performance criteria in this Section; drawings, design calculations, elevations and hydraulic grade lines for all existing and proposed stormwater conveyance elements including stormwater drains, pipes, culverts, catch basins, channels, swales and areas of overland flow; and where applicable, a narrative describing how the stormwater management system corresponds with any watershed protection plans and/or local greenspace program, greenway network plan, and park development.
6) Post‐development downstream flow analysis. A downstream flow analysis will be prepared by the applicant to provide an overview of potential impacts from post development run‐off from the site. At a minimum the downstream flow analysis will include:
i. A map of each point or area along the project site's boundaries at which runoff will exit the property.
ii. Delineation of all downstream structures and property adjacent or within the flow path of the downstream flow analysis.
iii. Identification of any known flooding problems.
iv. If determined through this preliminary review of the items above that the potential exists for downstream flooding resulting from post development conditions, the Director of the Department may require the applicant to conduct and submit a
downstream hydrologic assessment in accordance with the criteria listed in the Georgia Stormwater Management Manual criteria for post development
downstream analysis.
d) Landscaping and open space plan. A detailed landscaping and vegetation plan describing the woody and herbaceous vegetation that will be used within and adjacent to stormwater management facilities and practices. The landscaping plan must also include: the arrangement of planted areas, natural and greenspace areas and other landscaped features on the site plan; information necessary to construct the landscaping elements shown on the plan drawings; descriptions and standards for the methods, materials and vegetation that are to be used in the construction; density of plantings; descriptions of the stabilization and management techniques used to establish vegetation; and a description of who will be responsible for ongoing maintenance of vegetation for the stormwater management facility and what practices will be employed to ensure that adequate vegetative cover is preserved.
e) Operations and maintenance plan. Detailed description of ongoing operations and maintenance procedures for stormwater management facilities and practices to ensure their continued function as designed and constructed or preserved. These plans will identify the parts or components of a stormwater management facility or practice that need to be regularly or periodically inspected and maintained, and the equipment and skills or training necessary. The plan shall include an inspection and maintenance schedule, maintenance tasks, responsible parties for maintenance, funding, access and safety issues. Provisions for the periodic review and evaluation of the effectiveness of the maintenance program and the need for revisions or additional maintenance procedures shall be included in the plan.
f) Maintenance access easements. The applicant must ensure access from public right‐of‐way to stormwater management facilities and practices requiring regular maintenance at the site for the purpose of inspection and repair by securing all the maintenance access easements needed on a permanent basis. Such access shall twenty (20) feet wide and sufficient for all necessary equipment for maintenance activities. All access routes with a grade greater that twelve (12) percent shall have an improved surface. Upon final inspection and approval, a plat or document indicating that such easements exist shall be recorded and shall remain in effect even with the transfer of title of the property.
g) Inspection and maintenance agreements. The applicant must execute an easement and an inspection and maintenance agreement binding on all subsequent owners of land served by an on‐site stormwater management facility or practice in accordance with this article.
h) Evidence of acquisition of applicable local and non‐local permits. The applicant shall certify and provide documentation to the Department that all other applicable environmental permits have been acquired for the site prior to approval of the stormwater management plan.